1 / 17

Power Purchase and Grid Connection Procedures

Building Your Biogas System Workshop 10 th March 2009. Power Purchase and Grid Connection Procedures. Aidan Foss ANF Energy Solutions Inc. amfoss@ieee.org. ANF Energy Solutions. DG grid connection specialists No project ownership Current projects.

rianne
Download Presentation

Power Purchase and Grid Connection Procedures

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Building Your Biogas System Workshop 10th March 2009 Power Purchase and Grid Connection Procedures Aidan Foss ANF Energy Solutions Inc. amfoss@ieee.org

  2. ANF Energy Solutions • DG grid connection specialists • No project ownership • Current projects • Increasing involved in research due to new connection issues

  3. REVENUE METER REVENUE METER M M M REVENUE METER The Grid Connection POWER EXPORTER NET METERING UTILITY FEEDER HV DISCONNECT HV EQUIPMENT OWNED BY FARMER HV FUSE HV FUSE INTER-TIE TRANSFORMER INTER-TIE TRANSFORMER LV DISCONNECT LV FUSE TO OTHER LOADS INTER-TIE CIRCUIT-BREAKER LV DISCONNECT TO DIGESTER & POWERHOUSE LOADS LV FUSE GENERATOR CIRCUIT-BREAKER GENERATOR CIRCUIT-BREAKER BIOGAS GENERATOR BIOGAS GENERATOR

  4. Getting Connected • Power Purchase Options • Grid Access • Grid Connection Costs • Grid Connection Process

  5. Power Purchase Options: • Embedded Retail Generator – market price • Net Metering – to 500kW • RESOP – Renewable Energy incentive • CESOP – Clean Energy incentive - ?? • Green Energy Act – will replace RESOP

  6. Renewable Energy Standard Offer Program (RESOP) • Launched in Nov 2006 • 11c/kWh + 3.52c/kWh for peak • 20 year contract with OPA • Up to 10MW, 50kV • Requires a CIA • Green, Yellow & Orange zones • Driver for flood of projects • Suspended in May 2008 • Biogas OK to 5MW • Will be superseded by Green Energy Act

  7. Grid Access Rights • No guaranteed access rights • Distribution Code has limited capacity • Until 12 February 2009, Distribution Code was ‘First-come First-served’ for all generation in 10kW-10MW range

  8. Hydro One Queue • Capacity limits due to feeder, switchgear and transformers • Speculative projects ahead in the queue could delay your application by 2-3 years per project

  9. Hydro One Queue Analysis • From Hydro One queue 31-Oct-08 • Over 80% in 9-10 MW range • Blockages started in windy areas – Great Lakes • Blanket applications in Eastern Ontario Aug/Sept 07 • Small biogas being shut out from many agricultural areas

  10. Wind & Farm Biogas

  11. Distribution Code Modification 12th February 2009 Amendment • Up to 250kW: Queue exempt on feeders below 15kV • Up to 500kW: Queue exempt on feeders above 15kV

  12. Grid Connection Costs • All costs up-front – unlike load customer • Distribution Network designed for load customers • Deep Entry – Watch out for $$$: • Protection upgrades • Anti-islanding protection • Recloser replacement • Voltage regulators

  13. The Single-phase Hydraulic Recloser • Extensively deployed across Ontario • Restores load customers in 1-2 seconds • Simple, reliable • Can be a big problem for generation

  14. Grid Connection Process • Initial Feasibility Assessment • Connection Impact Assessment • Gives queue position • 12 months to CCRA • Connection Cost Estimate • Connection Cost Recovery Agreement • Connection Agreement

  15. Grid Connection Process • Distribution Code timescales not met – Hydro One swamped • Generator responsibility for connection design, equipment procurement and protection design • No simplified process for small generation

  16. Terryland Farm 180kW Biogas • Form A submitted Sept 2006 • CIA issued May 2007 • Commissioned August 2007 • Major delay due to Anti-islanding Protection

  17. Fepro Farms 499kW Biogas • July 2007 – 1st Form B and CIA • Highlighted several areas of unclear connection policy • Pilot for new Anti-islanding protection strategy • Scheduled for March 2009

More Related