Output, employment and productivity over the business cycle: 1988-2010, annualized quarterly data. Hungry Henry's Restaurant (Ch 3, #16). Solution to Hungry Henry’s. Critical Path is A-B-E--G-I 24 weeks. But A-C-D-F-H-I is close, so we should check both paths.
E N D
Output, employment and productivity over the business cycle: 1988-2010, annualized quarterly data
Solution to Hungry Henry’s Critical Path is A-B-E--G-I 24 weeks. But A-C-D-F-H-I is close, so we should check both paths. VAR(ABEGI) = ΣVAR = .69 + 1.78 + 1.78 + 1.36 + .44 = 6.05 VAR(ACDFHI) = ΣVAR = .69 + 1 + .25 + .25 + .11 + .44 = 2.74 << 6.05 so only the critical path is of concern σ = √6.05 = 2.46, and P(X < 26) = P(Z(obs) < Z(26) = (26-24.67)/2.46 = .54) From the Z table on page 745. we get ≈ .70