1 / 23

HQ TransÉnergie Response To Blackouts or Catastrophic Events

HQ TransÉnergie Response To Blackouts or Catastrophic Events. Jean-Marie Gagnon Manager Interconnected Networks Hydro-Québec TransÉnergie October 3rd, 2003 IEEE Centennial Panel, Toronto. Typical Response. Power Market Week (September 15th)

rinaldo
Download Presentation

HQ TransÉnergie Response To Blackouts or Catastrophic Events

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HQ TransÉnergie Response To Blackouts or Catastrophic Events Jean-Marie Gagnon Manager Interconnected Networks Hydro-Québec TransÉnergie October 3rd, 2003 IEEE Centennial Panel, Toronto

  2. Typical Response Power Market Week (September 15th) What will have happen if the August 14th blackout will have lasted a week or two and not just a day? The author suggests three typical responses: Political: call for greater oversight and standardisation Market: less regulation and market force Technical: determine what failed and technical steps so it will not happen again

  3. To be covered • Key data about HQ system • Impact of August 14th Blackout on HQ system • Actions following HQ blackouts • HQ Defence Plan • HQ 1998 Ice Storm • Concluding remarks

  4. CDN$ (millions) Assets 18 259 Revenue 3 027 Net Income 389 • Generation is located more than 1000 km from the interconnecting points and major load centers • The installed generation capacity on the North American interconnected system is 15 times bigger than that of HQ • Solving the stability problem resulting from synchronous interconnection would be excessively expensive HQ TÉ 2002 Key Data • Not synchronized with the Eastern Interconnection • Single control area • Own reliability coordinator

  5. HQ Transmission System Characteristics • Remote generation (1000 km) • Design of a reliable and cost effective transmission system • Major concern: system stability • Development of the 735 kV-AC • Fast protection systems • Static excitation systems • Power system stabilizers • Dynamic-shunt compensation • Series Compensation • Special protection systems • 505 substations • 32 227 km of lines (11 280 km of 735 kV)

  6. 1 200 MW 1 470 MW 2 305 MW 2 125 MW 785 MW 870 MW New Brunswick Ontario 1 870 MW 1 000 MW New England New York Interconnections Installed capacity of interconnections with neighbouring systems Import 4,525 MWcapacity +5,200 MW Export 7,100 MWcapacity EXPORT IMPORT

  7. La Grande-2 La Grande-2A 6 16 735 kV Chissibi 735 kV La Grande-1 Nemiscau 12 315 kV Radisson 2 250 MW ± 450 kV Nicolet 735 kV 1 022 km 2 138 MW 105 km Des Cantons 690 MW 735 kV Sherbrooke Québec New England 171 km Comerford Legend 690 MW Generation 214 km Sandy Pond 2 000 MW DC converter Transformer 345 kV Québec-New England MTDC line Phase I • In 1986, the Des Cantons (HQ) to Comerford (New England) HVDC interconnection was commissioned • 690 MW converter stations • 170 km ±450 kV DC line Phase II • New firm energy contract was signed with NEPOOL for 70 TWh over a 10 year period • In 1990, the Radisson (HQ) and Sandy Pond (NE) converters were commissioned • In 1992, the Nicolet (HQ) converter was commissioned • First large scale multi-terminal • 2000 MW converter stations • 1500 km DC line Islanding breaker

  8. August 14th Blackout • Not much happen in Québec • Tripping of generators and radial load isolated on Ontario system • HVdc ties with NY and NE continue operation • Northern NY and NE did not blackout • Highgate HVdc Back-to-back stop • HQ sustained restoration of power in NY and Ontario and offered additional support if required

  9. HQ 1989 Blackout • Turning point • Before 1989: '82 and '88 blackouts • Generation rejection scheme • Dedicated SPS for foreseeable events (Churchill loss) • Review of planning criteria • Due compliance process through NPCC • After the '89 blackout • Political and social response • Clear direction to do something • Technical response • Strengthen the system • Revised system design philosophy against extreme contingencies

  10. Basic Principles to System Design Four categories of events:

  11. Defence plan against extreme contingencies … First Level: Normal Events • Increase system strength • HQ TransÉnergie has adopted NPCC Design criteria to upgrade the reliability of its transmission system • This resulted in the implementation in the 90's of a major transmission upgrade program with the addition of: • Series compensation (11 000 MVAR) • Local shunt reactors automatic switching scheme to control voltage installed in 22 transmission 735 kV substations

  12. … Defence plan against extreme contingencies Second Level: Extreme Contingencies • Wide area SPS to mitigate impact at high transfer level • Fully operational since 2000 • This automatic defence scheme relies on: • a generation rejection and remote load shedding system covering extreme contingencies in 15 735 kV substations • an under frequency load shedding system distributed in about 150 distribution substations • Complementary action of the 735 kV shunt reactors automatic switching system • a under voltage load shedding system

  13. UVLS in the Montréal area

  14. … Defence plan against extreme contingencies Third Level: Beyond Extreme Contingencies • SPS to protect majorequipment from damage • Installed in the 1980’s • Protect against overvoltage from system separation • Local action results in controlled separation • Not a global separation scheme • Input • Loss of corridor (LC) • Overfrequency (OF) • Power swing relays (PS) • Overvoltage (OV) • Action • Switch-in special surge arresters (sacrificial) • Limit overvoltage at 1.4 pu • Trip local line breakers in series

  15. What are the Benefits • We already see the benefits • No blackout since 1989 • TÉ system has suffered major incidents with limited impact • In 1998, the consequence of the Ice storm could have been much more dramatic • Improved operating flexibility in particular with regard to interconnection operation

  16. Québec 1998 Ice Storm 1998: A VERY UNUSUAL STORM • THE DURATION: 5 days from 5th to 9th of January • THE AFFECTED AREA:100 X 250 km in Québec • THE STORM INTENSITY: more than 75mm of radial ice on conductors

  17. …Québec 1998 Ice Storm 116 TRANSMISSION LINES OUT OF SERVICE ON JANUARY 9th 1998

  18. …Québec 1998 Ice Storm • A second turning point • Political response • Two commissions (public and internal) • Clear mandate to minimize impact • Technical response • Set security objectives for power system restoration • Sources substation must be secured on BPS • Restore 50% of load in 4 days • Restore 100% of load in 21 days • Study of other catastrophic events

  19. …Québec 1998 Ice Storm • Major system reinforcement program to minimize impact in affected area in the future • Major 735 kV loop projects in Montreal, South-shore, Québec, Outaouais area and new interconnection between Ontario and Québec • Mechanical reinforcement of 735 line sections • Line de-icing will be used to limit ice building • One Statcom/DC installed at Lévis and Boucherville substation (not approved) • Conductor heating on the regional network • current circulation in the line • Low voltage short-circuit • Load transfer • Mobile emergency generators (30 MW)

  20. Prioritized Projects for the Bulk Power System • Two mechanical reinforcement projects • Two line de-icing installations

  21. Conclusion • CEA Actions for assuring the electric system reliability Continuing and accelerating: • The development and the implementation of operating systems; • The training of the operating personnel; • The enforcement of compliance to the criteria's required to support the reliable and efficient operation of the existing facilities • These steps are needed and HQ supports them

  22. …Conclusion • The question about blackouts goes beyond normal reliability, it is on a philosophy on how to address extreme events and preserve system security • So, we must try to prevent them • Or, at least try to minimize their impact • Adoption of automatic action schemes like tripping load • The public will accept them if the benefit can be demonstrated • It means: • A lot of studies • Consideration to profound re-design • A lot of $ • That's the challenge before us: can't it be avoided?

  23. Thank you • I would like to thank… • Jean-Pierre Gingras • Gilles Trudel • at TransÉnergie

More Related