1 / 15

GLAST Large Area Telescope: Stato della costruzione in Italia Alessandro Brez INFN Pisa

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Stato della costruzione in Italia Alessandro Brez INFN Pisa. Stato della torre EM. La torre EM e’ rimasta assemblata per evitare di danneggiare i fragili cavi smontandoli e rimontandoli

rio
Download Presentation

GLAST Large Area Telescope: Stato della costruzione in Italia Alessandro Brez INFN Pisa

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Stato della costruzione in Italia Alessandro Brez INFN Pisa

  2. Stato della torre EM • La torre EM e’ rimasta assemblata per evitare di danneggiare i fragili cavi smontandoli e rimontandoli • Questo ha impedito il test dei tray in camera termica e il completamento dell’ incapsulazione delle microsaldature fra ladder e tray (solo 4 tray sono completi) • Il tempo rimasto fra test vibrazionale e test termovuoto non permette di effettuare queste ciclature • La Plyform ha il materiale per assemblare le nuove sidewalls che saranno pronte entro 2 settimane, in tempo per il test previsto per il 17/11. • In produzione sono: • Tavola di interfaccia shaker verticale – fixture torre (Pisa) • Tavola di interfaccia camera termovuoto - fixture torre (Pisa) • Nuova fixture (SLAC) • Nuovo frame salva-cavi (SLAC)

  3. Assembly of EM Tower in G&A Trays alignment onassembly jig Cabling Geometrical tolerances well within limits (0.3 mm).

  4. Attivita’ flight in corso • Ricevimento e test SSD • Produzione ladders in G&A • Start produzione trays in Plyform

  5. SSD Electrical Test Rate Received :9452 (82% del totale, ultimi 2000 in ordine dall’ASI) Tested: 8388 (89% dei ricevuti, 73% del totale) Rejected ~1%

  6. SSD Electrical Properties Specification: leakage current <500 nA at 25C and 150 V

  7. Produzione Ladders 690 flight ladder tested (25% of total) 15 rejected (2.2%) Ladder assembly tool Manual fast AND precise method 24 ladder assembly tools used in parallel Very good ladder alignment obtained

  8. Encapsulation • Dam & Fill encapsulation • Dam Nusil 1142 • Fill Nusil 15-2500 • Requirements: • Height <0.5mm • Lateral overflow <0.05mm • Coverage of all the bondings and pads Fast system to check encapsulation height

  9. Electrical Tests: Results • Electrical test results: • Ladder tested 690 • Accepted 675 (98%) • Broken edge 4 • Probe accident 2 • Fill accident 1 • Not understood 8 • The causes of problems 3, 4 and 5 have been corrected, foreseen rejection rate ∼1% Bad channels caused by bonding or by probing (coupling shorts)=0.016% (accepted limit 1%) No broken or bad bondings

  10. E.M. Tray Production

  11. E.M. Results: DIMENSIONS

  12. E.M. Results: FLATNESS

  13. E.M. Results: ORTHOGONALITY & PARALLELISM

  14. Stato costruzione dei tray • Incoming materiali in corso : • problemi su qualita’ honeycomb • Problemi su prima serie di CC (yeld 75% su 40) • Taglio tungsteni 18%Xo • Previsione: primi tray sotto test vibrazionale e bakeout a dicembre 4mm

  15. Programma a breve • Produzione di 10-20 tray entro dicembre (con test vibrazionale e bakeout) • Produzione tray a ritmo di 10 tray/settimana per gennaio • Ricevimento di ~20 elettroniche con meccanica (pitch adapter) migliorata ma GTRC-6 (TOT e Clock problems) entro novembre • Assemblaggio di 5 trays con ladder funzionanti per costruzione di minitower #2 entro dicembre • Gennaio-marzo test estensivi minitower: • Test con cosmici in configurazione minitower e su rack di test • Test termico passivo • Test termovuoto attivo • Test vibrazionale • In parallelo • Assemblaggio dei ladder sui tray • ~marzo MCM con GTRC7  inizio produzione torre A

More Related