1 / 38

The Panorama of the Future Radioactive Areas from now to 2020

The Panorama of the Future Radioactive Areas from now to 2020. S. Roesler on behalf of DGS-RP. Workshop on remote manipulations and diagnostics in radioactive areas and handling of radioactive material CERN, May 6, 2013. Outline. Present radiological classification

rlorrie
Download Presentation

The Panorama of the Future Radioactive Areas from now to 2020

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Panorama of the Future Radioactive Areas from now to 2020 S. Roesler on behalf of DGS-RP Workshop on remote manipulations and diagnostics in radioactive areas and handling of radioactive material CERN, May 6, 2013

  2. Outline • Present radiological classification • Measured residual dose rates and comparison to FLUKA simulations • Operational scenarios until LS3, scaling factors for dose rates • Evolution of dose rates 1. LHC: 2. LHC injectors: • SPS, PS, PSB • Residual dose rates and present radiological classification 3. Target Areas: • North, East and AD target areas • Measured dose rate maps • Evolution of dose rates with cooing time 4. ISOLDE: • Measured and calculated residual dose rate maps • Calculated dose rates for target recovery scenario 5. ALARA: • Reminder on ALARA rules • Work-and-dose planning • Optimization during design Not covered: CNGS, nTof, Linacs, Experimental Areas,… Remote Manipulations Workshop, 6 May 2013

  3. Radiological classification of the LHC during 2012 low-occupancy permanent

  4. LHC Point 7 Ambient dose equivalent rates in µSv/h at 40cm measured on Dec 20, 2012 (last “good” fill on Dec 5, i.e. cooling time >1week) Scaling factors based on generic Studies for IR7: Remote Manipulations Workshop, 6 May 2013

  5. LHC Point 7 FLUKA calculations for nominal parameters Collimator (1 week cooling) Absorber (1 week cooling) good agreement between FLUKA results and measurements (after scaling to nominal conditions) Remote Manipulations Workshop, 6 May 2013

  6. LHC Point 6 500 µSv/h 222 µSv/h Ambient dose equivalent rates in µSv/h at 40cm measured on Dec 17, 2012 (~1 hour after last dump) 83 µSv/h 17. Dec 2012, 8am 40 µSv/h factor 4 110 µSv/h factor 2 1 week 1 day Remote Manipulations Workshop, 6 May 2013

  7. LHC Point 6 40 µSv/h 110 µSv/h FLUKA calculations for nominal parameters 100 µSv/h 10 µSv/h FLUKA calculations: J.Vollaire et al. Remote Manipulations Workshop, 6 May 2013

  8. LHC Point 1 FLUKA calculations for LS1 (1 week cooling) Courtesy: C.Urscheler et al. Ambient dose equivalent rates in µSv/h at 40cm measured on Dec 17, 2012 (last “good” fill on Dec 5, i.e. cooling time >1week) Remote Manipulations Workshop, 6 May 2013

  9. LHC Point 5 FLUKA calculations for LS1 (1 week cooling) Courtesy: C.Urscheler et al. Ambient dose equivalent rates in µSv/h at 40cm measured on Dec 17, 2012 (last “good” fill on Dec 5, i.e. cooling time >1week) Remote Manipulations Workshop, 6 May 2013

  10. Operational scenario(s) L.Rossi / HiLumi Workshop, Frascati Assumptions on the operational parameters as obtained from ATLAS and CMS Remote Manipulations Workshop, 6 May 2013

  11. Dose rate evolution until LS3 – ATLAS LS1 Ambient dose equivalent rates in µSv/h after one week of cooling (also representative for a TS during the run prior to the respective LS) Courtesy: C.Urscheler et al. LS3 LS2 Remote Manipulations Workshop, 6 May 2013

  12. Dose rate evolution until LS3 – CMS LS1 Ambient dose equivalent rates in µSv/h after one week of cooling (also representative for a TS during the run prior to the respective LS) Courtesy: C.Urscheler et al. LS2 LS3 Remote Manipulations Workshop, 6 May 2013

  13. Dose rate evolution until LS3 – Scaling factors Short cooling times: - dominated by short-lived nuclides - dose rate reflects interaction rate (instantaneous luminosity) - increase, e.g., ATLAS from now until 2021: (peak lumi: 2.0×1034 / 0.7×1034) 2.9 (energy) ~1.5 (total) ~4.4 Long cooling times: - dominated by longer-lived nuclides - dose rate reflects integrated luminosity - e.g., as calculated with FLUKA Remote Manipulations Workshop, 6 May 2013

  14. Residual dose rates LS3 – ATLAS one month 6 months 4 months one year Remote Manipulations Workshop, 6 May 2013

  15. Residual dose rates LS3 – CMS one month 6 months 4 months one year Remote Manipulations Workshop, 6 May 2013

  16. Residual dose rates LS3 – TAS at Point 5 one week 4 months 1 month one year Remote Manipulations Workshop, 6 May 2013

  17. Residual dose rates LS3 – TAN at Point 1 4 month cooling top side inside Remote Manipulations Workshop, 6 May 2013

  18. SPS – Ring Survey (1) • Performed during annual shutdown • Usually done 30 hours after beam stop and at end of annual shutdown • Use of motorized tractor • Measurements with plastic scintillator every meter • Complemented by more detailed measurement at specific work-sites and most radioactive components in order to define radiological classification Remote Manipulations Workshop, 6 May 2013

  19. SPS SPS – Ring Survey (2) 1 mSv/h 10 µSv/h 1 mSv/h 10 µSv/h Remote Manipulations Workshop, 6 May 2013

  20. SPS – Detailed Survey Example: Sextant 1 • Radiological classification as Limited Stay Area with local • postings of “hot spots” • Dose rates not expected to change dramatically during coming • years Remote Manipulations Workshop, 6 May 2013

  21. PS • shown here: results 32hrs after beam stop 18/12/2012 • radiological classification as Limited Stay Area • dose rates not expected to change dramatically • during coming years • several optimization measures planned • (e.g., dummy septum) Remote Manipulations Workshop, 6 May 2013

  22. PSB Ring Remote Manipulations Workshop, 6 May 2013

  23. PSB Injection 600 µSv 300 µSv • Dose rate reduction: • factor of two between 1-2 hours and 32 hours • factor of two between 32 hours and two months cooling time Remote Manipulations Workshop, 6 May 2013

  24. North target area Residual dose rates in µSv/h 25 Oct 2002 (38 days after proton run) Remote Manipulations Workshop, 6 May 2013

  25. North target area 2 hours 5 hours factor 2 1 day factor 2 1 week Remote Manipulations Workshop, 6 May 2013

  26. East target area • Shown here: 2 months of cooling • Dose rates higher by about a factor of 7 • after 1-2 hours cooling • Very crowded and not optimized w.r.t. • modern RP Remote Manipulations Workshop, 6 May 2013

  27. AD target area • Shown here: 3 months of cooling • Dose rates higher by about a factor of 9 • after 1-2 hours cooling Remote Manipulations Workshop, 6 May 2013

  28. ISOLDE Example: Survey measurements from shutdown 2011 (about 2 months cooling time) 170 mSv/h 60 mSv/h 650 mSv/h (1 m from target) 450 mSv/h (2 m from target) 60 mSv/h 15 mSv/h 10 mSv/h Remote Manipulations Workshop, 6 May 2013

  29. ISOLDE • (Pessimistic) Example: • Five years of operation with UC target at 1020 protons/year • Residual dose rate calculated with FLUKA for different cooling times after target removal 1 day of cooling Courtesy: J.Vollaire et al. Remote Manipulations Workshop, 6 May 2013

  30. ISOLDE Probibited area (100 mSv/h) • (Even more pessimistic) Example: • target recovery scenario • About 9 days of operation with UC target at • 1019 protons delivered (~2 µA) • Residual dose rates calculated with FLUKA 3 days of cooling 3 days of cooling Courtesy: J.Vollaire et al. Remote Manipulations Workshop, 6 May 2013

  31. Optimization – Safety Code F Optimization starts with the design! Remote Manipulations Workshop, 6 May 2013

  32. Optimization – ALARA procedure Optimization is legal requirement if accumulated dose exceeds 100 μSv (ALARA) Optimization includes: • work coordination • work procedures • handling tools • design • material Group 1 criteria 5 mSv Group 1 criteria: determine ALARA Level classification Group 2 criteria: can be used by RP/RSO to increase classification Formal work-and-dose-planning (DIMR) as from ALARA Level 2 ALARA committee if ALARA Level 3 Group 2 criteria

  33. Optimization – ALARA procedure Work- and dose planning (DIMR)

  34. Optimization during design – Intervention doses Methodology: Calculation of residual dose rate maps Calculation of individual and collective intervention doses Revision of design and/or work scenario • for cooling times typical for interventions on the respective component • based on nominal operational parameters • definition of geometry and materials as detailed as needed (and available) • based on as realistic as possible work scenarios, including locations, duration, number of • persons involved,.. • identification of cooling times below which work will be impossible • (design criterion: 2 mSv/intervention/year) • communication of results and constraints to equipment groups • start with work steps that give highest individual or collective doses • consider optimization measures (distance, tooling, material choices, etc.) • identify if remote handling is possible New design ? Step 1 Revised work scenario ? Step 2 Start of iteration: Remote Manipulations Workshop, 6 May 2013

  35. Recent example – Linac 4 dump 1 2 3 4 Courtesy: D.Grenier Remote Manipulations Workshop, 6 May 2013

  36. Summary (1) • LHC: • Activation and residual dose rates in LSS1, 5, 3, 7 will increase until LS3 by factors up to 16 and • approach levels of the present SPS. • LSS1 and LSS5 will become Limited Stay Areas until LS3 with residual dose rates (few months • cooling) in the aisle of about 100 µSv/h, reaching several mSv/h close to most radioactive objects. • LSS7 may become High Radiation Area with dose rates of 2-10 mSv/h (few days of cooling) around • collimators and absorbers. • Dose rate around the inner parts of the experiments and their forward shielding will increase to • several mSv/h. • Upgrade studies should include the development of tools and work procedures for maintenance, • repair and dismantling. • As successfully done during the LHC design, all components to be installed in high-loss regions • must be optimized for future handling and radioactive waste disposal (see also next presentation) • Radiological assessments, including detailed FLUKA calculations, will be performed as soon as design • choices have been made which may then serve as input to assess design options. Remote Manipulations Workshop, 6 May 2013

  37. Summary (2) • SPS, PS, PSB: • Dose rates have reached saturation and remain at the present levels. They are classified as • Limited Stay Areas with local areas where dose rates exceed 2mSv/h. • Loss locations may vary and, if possible, should be moved to passive robust elements that need • little maintenance (e.g., PS dummy septum 15). • Target areas: • The North, East and AD target areas are among the most radioactive areas at CERN and not • always optimized with regard to modern RP (crowded, corrosion, ageing components, some • without ventilation,…). • In order to reduce waiting times before interventions and dose to personnel they are presently • in the focus for development of remotely operated devices. • Consolidation projects are ongoing for all of them. Remote Manipulations Workshop, 6 May 2013

  38. Summary (3) • ISOLDE • The ISOLDE target area is one of the very few areas at CERN where fully remote handling is • mandatory. Its robot will be replaced during this LS (see presentation by J. L. Grenard). • Its laboratory area will change completely and include in the future significant handling activities • of highly radioactive objects (ISOLDE targets, Medicis samples). • ALARA: • CERN’s ALARA rules are being used with great success since several years now and have just • been revised. • - Moreover, they are now fully integrated into the activity planning and approval process (IMPACT). Many thanks to: C. Adorisio, C.Urscheler, D. Forkel-Wirth, N. Conan, H.+H. Vincke, J. Vollaire, C. Tromel, R. Fröschl, G. Dumont,… Remote Manipulations Workshop, 6 May 2013

More Related