1 / 31

Sinking in Concrete

Learn how to calculate costs for fire pits, curbs, and more using precise measurements and material estimations. Discover total expenses to streamline pricing for landscaping projects.

rmasters
Download Presentation

Sinking in Concrete

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sinking in Concrete Day 4 – Firepit and Curbs

  2. What Information? • After you talked to Mr. Johansen, you discovered that he would like a 2’ border surrounding his firepit. • Mrs. Johansen would only like the garden border around the new edges and not around the natural walls. She would like them to be 4” high and 6” wide. To do this you will need the curb to extend 2” below the ground.

  3. Materials • For the Firepit, you will need gravel, concrete, rebar and plywood. • For the curbs you will need ready mix concrete and plywood.

  4. Fire Pit • The Fire pit will be found similar to sidewalk #1. We will need to find the area of the big circle and subtract the area of the small circle. 2’ 2’

  5. Abig-Asmall • The area will be 25.13 square feet • Remember this is the amount of rebar needed. • Add it to the chart

  6. Gravel • V= Abase * Height • V= 25.13 * 0.5 • V=12.57 cubic feet

  7. Concrete • V= Abase * Height • V= 25.13 * 0.42 • V=10.55 cubic feet

  8. Plywood • We will need the circumfrence of both circles for the plywood measure. • First do the big ring • Then the small • Now add them together! 6.28 +18.85=25.13’

  9. Plywood Cost • Remember there are 8’ in one strip • 25.13/8 = 3.14 • That is less than one sheet since you can get 8 in one sheet! • 3.14/8 = .39 of a sheet • We will order 1 sheet

  10. Rebar Cost • Recall there are 32 square feet in one sheet of rebar. • We need 25.13 • 25.13/32 = .79 • We will order 1 sheet

  11. Gravel Cost • Convert your units! • 12.57 * 0.037 = 0.47 cubic yards • We will order 1 cubic yard

  12. Concrete Cost • Convert to cubic yards first, then to cubic meters. • 10.55 * 0.037 = 0.39 • 0.39 * 1.82 = .71 cubic meters

  13. Total Cost • Grave (A-grade): $7.00 • Concrete: $200.00 • Rebar: $14.45 • Wood: $37.00 • Total: $258.45 + tax (multiply by 1.13) = $292.05

  14. Curb #1(Rose Garden) The curb for the rose garden will be beside sidewalk one that was calculated on day 2 with the plywood. • Small Circle: C=2*3.14*18 113.04 ** don’t forget to divide by 4 113.04/4 = 28.26’ • Remember that 6” = .5’ • Remember that 4” + 2” = 6”

  15. V=l*w*h V=28.26 * .5 * .5 V=7.07 cubic feet

  16. Plywood • We will need to frame all four sides • P= l+l+l=l • To find the missing inside curb length. Use the circumference fomula again and divide by 4. • The radius is the 18’ - .5’ for the curb. C=2*3.14*17 106.81 ** don’t forget to divide by 4 106.81/4 = 26.7’ • P= 28.26+.5+26.7+.5 = 55.96’

  17. You try curb #2

  18. Curb #2(Flower Bed by Bedroom #3) • This is a rectangular flower bed shaped like an L • We will need 3 edges as 3 are natural walls with the house.

  19. Measurements • The front side is 2’ • The front edge is 11+2 = 13’ • The side edge is 12 +2 (closet) +2 (garden) = 16’ • 2+13+16 = 31’

  20. Calculate • V=l*w*h V=31*.5*.5 V=7.75 cubic feet • Inside edge is .5’ less along the house, 1’less along the front and .5’less on the side. • 31-1-.5-.5 = 29 P = 31+29 +.5+.5= 61’

  21. Plywood Cost • 116.96’/8’ =14.62 • 14.62/8 strips = 1.83 sheets • We can not order .83 sheets so we will order 2

  22. Concrete Cost • It takes 2.3 bags of ready mix to fill 1 cubic foot. • We have 14.82 cubic feet. • 14.82 * 2.3 = 34.09 • We will need to order 35 bags

  23. What is the total price? • Now lets add our prices from all three days! • Driveway - $ 3685.78 • Sidewalks - $ 3647.36 • Deck piers - $ 261.74 • Fire pit - $ 292.05 • Curbs - $ 283.65 TOTAL: $8170.58 (without wear and tear and labour)

  24. What if we total at the end instead of by the job?

  25. Total Amounts

  26. Let’s price the whole job (without wear and tear and labour) • Gravel B-grade: 18 * $6.00= $108.00 • Gravel A-grade: 19 * $7.00= $133.00 • Concrete: 28 * $200.00= $5600.00 • Wood: 9 * $37.00= $333.00 • Rebar: 31 * $14.45= $447.95 • Tubes: 3 * $11.37= $34.11 • Brackets: 6 * $2.97= $17.82 • Ready Mix: 65 * $5.99= $389.35 • Total: $7063.23

  27. Now add the tax! • $7063.23 * 1.13 = $7981.45 • So, if we priced this individually it would cost $8170.58. It is cheaper to price the whole job and there will be less scrap material. It will also allow you to give a more competitive price!

More Related