Program Management Systems Committee EVM for Service Contracts Working Group Joint Industry/Government Meeting May 21, 2009
Subcommittee Charter • Problem Statement • EVMS is being applied to a variety of services type work scenarios and there is no consistent guidance or policy on how EVMS should be implemented • Charter for Subcommittee: • To develop and recommend policy, process guidance, and/or training to support the implementation of EVMS on services type work • Targeted Exit Criteria: • White Paper - “Guidance for Implementing EVMS on Services Work
Earlier Conclusions • EVM is useful for managing services work; however its application should be scaled to balance the benefits of EVM with program risks and the cost of EVM implementation • EVM is compatible with performance based services acquisition, • It’s important to seek ways to define objective methods for measuring earned value of services • Over-reliance on LOE for services can mask progress on other work • Recommend separate analysis of performance data for development and service work • It may be more appropriate and beneficial to implement EVM at the program level rather than at the individual contract level, e.g., staff augmentation (personal services) work • More flexibility in EVM Systems may be required to enable optimal application of EVM to services contracts, e.g., • Summary-level planning/shorter planning horizons • Allowances in the process for more frequent re time-phasing of budgets
Contract Element Required for EVM • A discrete SOW, from which an end product-oriented work breakdown structure can be defined, and a schedule. From these, a time-phased, resource loaded plan for executing the required work within the timeframe specified in the contract can be developed. • As stated in the NDIA PMSC EVMS Application Guide: • “Where work is discrete, EVM can be effectively employed. Where work is T&M/LOE, performance must be evaluated using other means that are not related to schedule milestones or measurement of progress.” • “For contracts issued in support of a program where the supplier does not control and manage the work scope and schedule (such as a staff augmentation contract), EVMS requirements should not be applied to the contract itself but at the program level where scope, schedule and cost are present.” (Source: NDIA PMSC EVMS Application Guide).
PBSA - Contracting • PBSA is a very disciplined way to write and manage service contracts • Performance standards (SLAs) that define the performance level required to meet contract requirement, are measurable and permit assessment of supplier’s performance. • Allow contractor maximum flexibility without government interference – Primarily FP Contracts • Quality Assurance Surveillance Plan to measure each service • Service measured during the payment period. • Service requirement starts over each payment period.
EVM and PBSA May Apply on One Contract • EVM and PBSA are management frameworks. • Both use the WBS process to define the work • Work is of two types • Project, the work is done over a period of time with the benefit realized either at major milestone points during project execution or at the end of the project when the finished product is delivered. Use EVMS • In service efforts, the work is done in a continuous, often repetitive manner and the benefit is realized as the service is performed. Use PBSA • Projects can have a significant amount of service work. • Service programs can have significant project work.
Original Scope Has Evolved • Original – How can EVM be made to fit the management of service contracts. • New – Select the management technique(s) best suited to the effort based on the characteristics of the work and the contractual elements present. • Paper will contain recommendations for FAR Part 7, Acquisition Planning, changes. • Government use WBS to define the work and to identify the appropriate project management method. • Contracts can specify more than one management method • Contracts must indicate what areas require EVM and what areas require PBSA. • Proper use of EVM and PBSA will reduce LOE
Outline for Guidance Document • Define, compare and contrast products vs. services • Provide guidance for selecting appropriate management methods applicable to the contract scope of work • Many contracts are hybrids – both EVM and PBM could be used on different WBS elements within a single contract • Methods may also vary by contract type • Collect and describe characteristics of various types of services • Provide WBS examples for service work • Write guidance for each, e.g., IT, logistics, depot maintenance, program management, etc. • Provide guidance for contracting, i.e., to put management requirements on contract correctly