May 2011 Closing Report -TGmb Authors: Date: 2011-05-12 Dorothy Stanley (Aruba Networks)
Abstract This document contains the TGmb closing report for May 2011. Dorothy Stanley (Aruba Networks)
Accomplishments Completed Second Recirculation SB Comment Resolution (D8.0) 863 comments Third Recirculation SB (20 day) to start shortly Scheduled Teleconference calls on June 24, July 8, 15 10am Eastern (7am Pacific) Timeline Analysis No change from plan that 11mb will incorporate 11s Revisit in July Slide 3 Dorothy Stanley (Aruba Networks)
Current TGmb Plan of Record May 2008 – Issue Call for Comment/Input July 2008 – begin process input and old Interpretation requests Acknowledge previous Task Group referrals Sept 2008 – PAR revision process started Nov 2008 – close receipt of new input Nov 2008 – WG/EC approval of PAR Revision Dec 2008 – NesCom/SASB approval PAR Revision May 2009 – First WG Letter ballot Nov 2009 – Recirc start July 2010 – Conditional Sponsor Ballot Approval from EC August 2010 – Form Sponsor Pool (45 days) – Closes Sept 14 November 2010 – Initial Sponsor Ballot completion Jan 2011 – Sponsor Recirc. Start Nov 2011 – WG/EC Final Approval March 2012 – RevCom/SASB Approval Slide 4 Dorothy Stanley (Aruba Networks)
Goals for July 2011 Recirculation Sponsor Ballot comment resolution (D9.0) Slide 5 Dorothy Stanley (Aruba Networks)