170 likes | 387 Views
DCS Installation Review 14.3.03 L.Jirdén. What to install and where Global layout, installation packages When to install Schedule How to install Procedure, tools, commissioning Who installs Manpower resources, responsibilities. ALICE Controls Context. Services. External Systems.
E N D
DCS Installation Review14.3.03 L.Jirdén • What to install and where • Global layout, installation packages • When to install • Schedule • How to install • Procedure, tools, commissioning • Who installs • Manpower resources, responsibilities
ALICE Controls Context Services External Systems DCS Back-end infrastr. magnet LHC ECS gas Offline electricity Trigger cooling DCS safety DAQ access ITS TPC MUON pixel strip drift T T p hv hv hv hv hv lv lv lv lv lv Detectors
1. DCS Infrastructure PVSSconsoles ALICE CONTROL ROOM PVSS PVSS PVSS PVSS server Profibus CANbus RS232 2. Detectors COUNTING ROOMS HV PS LV PS CAVERN ON DETECTOR HV-rods CHAMBER RCU Installation packages
CERN Services 3. Detector Services Prim. Services ALICE DCS Control Super- vision Super- vision TCR ACR network DIP DIP Process control PX UX Process control P2 Not treated here • Detector Services • Racks, crates • Detector Cooling • Detector Gas • Det. Infrastructure • Detector Safety • Primary Services • Prim. Electricity • Prim. Cooling • Prim. Gas • Magnet • Personal Safety Installation packages
ALICE CONTROL ROOM ECS/DCSconsole DCS network COUNTING ROOMS 4. Interface to External Systems DCS-DAQ server DCS-TRG server DCS-Offl. server DCS-LHC server Router Ext. network External Systems Not treated here DAQ SYSTEM TRG SYSTEM OFFLINE SYSTEM LHC SYSTEM Installation packages
How to install • Pre-installation of TPC and HMPID in SXL2 • Functional test of • DCS Infrastructure components • PVSS II, configuration, log, archiving, alarms, FSM, etc. • Detector DCS – TPC and HMPID subsystems • HV, LV, FEE, Laser, Liquid circulator, etc. • Detector Services DCS (partly) • Rack control, cooling, gas, environment monitors, safety, • DCS Interface to DAQ + TRG
PC IT/CS ALICE CONTROL ROOM ACC DCS network PC PC PC PC Profibus RS232 CANbus ACC TEST UNIT A TEST UNIT B TEST UNIT C COUNTING ROOMS Standard SW: OS, PVSS, Framework Specific SW: Servers, dev. drivers CAVERN Field-bus analyzer ON DETECTOR Final Installation: DCS Infrastructure
Detector groups PC SW applications SW tools ALICE CONTROL ROOM DCS network ACC PC PC PC PC RS232 Profibus CANbus HV PS COUNTING ROOMS LV PS Detector groups ST/EL CAVERN ON DETECTOR HV-rods CHAMBER RCU Final Installation: Detectors
Superv. PC SW applications ALICE CONTROL ROOM Detector groups + ACC + Glimos ACC Process control PLC Racks & crates Cooling Gas Safety Infrastructure ST/EL + ACC ST/CV Devices Sensors EP/TA1 COUNTING ROOMS ST/EL IT/CO Devices Sensors ACC CAVERN Devices Sensors ON DETECTOR Final Installation: Detector Services
ALICE CONTROL ROOM Superv. PC SW applications ACC + Detectors COUNTING ROOMS DAQ PC TRG PC Offline PC LHC PC Router SW: DIM servers State Machines Ext. network External Systems Not treated here DAQ SYSTEM TRG SYSTEM OFFLINE SYSTEM LHC SYSTEM ACC Final Installation:Interface to external systems
DCS commissioning • Systematic check of DCS functionality and operational states • for each control slice • and at each level • Final DCS commissioning during ALICE commissioning
ECS DCS DAQ TPC TRD LV CU LV CU HV CU FEE CU COOL CU … GAS CU … LV DU LV DU HV DU FEE DU COOL DU GAS DU LV Physical Device LV Physical Device HV Physical Device FEE Physical Device COOLING Physical Device COOLING Physical Device DCS commissioning
DCS/ECS commissioning ECS DCS DAQ TRG OFF LHC DET GAS INF DSS MAG … 12 detectors ITS TPC TRD TOF HMP PHO ZDC FD PMD MU EMC COS 19 sub-detectors SPD SDD SSD RO FC CAL CPV FMD T0 V0 TRI TRA ~100 sub-systems … … … … 2-300 device units … … … 2-300 physicaldevices > 105 channels > 106 parameters
Resources • Work-packages have been established for the following non-ALICE groups installations finished • IT/CO Controls, JCOP, DSS mid 2005 • IT/CS Networking end 2004 • ST/EL Power distribution, cabling mid 2005 • ST/CV Cooling & Ventilation Control mid 2005 • EP/TA1 Gas Control mid 2005 • EP/TA3 Magnet Control mid 2005 • EP/ESS Rack and Crate Control mid 2004 • ALICE groups involved • ACC Controls Coordination 4 eng/phys + 1 el. Techn. • EST/LEA Integration team • Detectors 1 – 2 eng/phys + 1 el. Techn. per detector