1 / 19

[ Sample Image: Place a 9.5” x 4.75” image here ]

[ Sample Image: Place a 9.5” x 4.75” image here ]. PUR 2013-07 Miscellaneous Architectural and Engineering Services RFP Mandatory Pre-Proposal Conference July 22, 2013. Agenda . Welcome – E. Buddy Davis Brief Introductions RFP Overview Deadlines Scope of Requested Services

rocio
Download Presentation

[ Sample Image: Place a 9.5” x 4.75” image here ]

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. [ Sample Image: Place a 9.5” x 4.75” image here ] PUR 2013-07 Miscellaneous Architectural and Engineering Services RFPMandatory Pre-Proposal Conference July 22, 2013

  2. Agenda • Welcome – E. Buddy Davis • Brief Introductions • RFP Overview • Deadlines • Scope of Requested Services • Tour of CBHC facility • Questions

  3. 1.2 Timeline and Summary - RFP • July 12, 2013 – RFP Packets & Instructions released. • July 22, 2013 – Mandatory Pre-proposal Meeting • July 23, 2013 – Deadlines for Written Questions • July 26, 2013 – Answers to Questions released • August 2, 2013 – 4:00 p.m. Proposal deadline

  4. 1.2 Timeline and Summary – RFP, con’t. • Week of August 5, 2013 • Evaluation Committee certifies firms and evaluates proposals. • Week of August 12, 2013 • Presentations of top 3 firms • August 15, 2013 – • Evaluation committee recommend top 3 firms to Executive Director

  5. 1.2 Timeline and Summary – RFP, con’t. • August 22, 2013 • Executive Director recommends top 3 firms in rank order to Board. • Board Approves list of firms and authorizes negotiation with #1 ranked firm. • August 23, 2013 • Notice of Intent to Award issued. • August 27 – September 5, 2013 • Contract negotiations completed.

  6. Scope of Requested Services • 1.4.1.1 • Project 1- Building Envelope Services • North and South Balcony leaks • 2nd Floor Window seal leaks • Roof Leaks

  7. North & South Balconies North Entrance South Entrance

  8. 2nd Floor Window Leaks

  9. Roof Leaks ELC tenant space CBHC IT area

  10. Scope of Requested Services, con’t, • 1.4.1.2 Project 2- Parking Lot • Remove tree roots and repair pavement • Sealcoat pavement • Re-stripe parking lines • Install traffic calming devices and speed limit signs • Add “No Parking Zones” in designated areas • Replace damaged car stops • Install new bike rack

  11. Parking Lot Repair & Improvements

  12. Repair, Sealcoat and Re-paint

  13. Improvements – Traffic calming Parking Entrance Speed Reduction

  14. Improvements, con’t. Landscape curbing Bike racks

  15. Scope of Requested Services, con’t, • 1.4.2 Potential Projects • Tenant Space Re-design • Innovations Lab Reconfiguration • Audio/Visual Technology Upgrades • HVAC units repair or replacement

  16. Tenant Space Redesign

  17. Deadline Summary • Deadline for Written Questions • 4:00 p.m. July 23, 2013 • Emailed to bdavis@childrensboard.org • Answers to Written Questions • 4:00 p.m. July 26, 2013 • Posted on www.childrensboard.org and www.demandstar.com • RFP deadline • 4:00 p.m. August 2, 2013 (CBHC clock) • Delivered to CBHC office building • Emailed to PUR201307RFP@childrensboard.org

  18. Deadlines, continued. • Evaluation Committee Review (Week of August 5, 2013) • Certify all qualified firms. • City and County qualified or based on statutory criteria in Section 287.055, Florida Statutes. • Hear presentations from top 3 firms, based on their total scores received. (Week of August 12, 2013) • Recommend top three ranked firms to CBHC Executive Director. • Executive Director recommends top three ranked firms to Board for Approval – August 22, 2013 • Board approves list of firms in rank order and authorizes negotiations with #1 ranked firm – August 22, 2013

  19. Thank You! • Questions! • The End. • Contact information: • E. Buddy Davis, Purchasing & Facilities Director • Direct Line: 813-204-1770 • Email – bdavis@childrensboard.org