280 likes | 618 Views
EcoChem Analytics. Experience with PADEP, CEM Phase I Approval Under Rev 7 ARIPPA Technical Symposium July 27, 2005 Jim Carroll & Ron Baker. Presentation Overview. Project Scope Hardware Description Project Schedule Application Experience Interaction with the Department Recommendations
E N D
EcoChem Analytics Experience with PADEP, CEM Phase I Approval Under Rev 7ARIPPA Technical SymposiumJuly 27, 2005Jim Carroll & Ron Baker
Presentation Overview • Project Scope • Hardware Description • Project Schedule • Application Experience • Interaction with the Department • Recommendations • CEM Supplier Perspective
CEM Project Scope • Install new stand alone CEMS enclosure • Install two (2) new EcoChem MC3 multi-component analyzer packages • NOx, SO2, CO, CO2, O2 • Two (2) new sample handling systems • Probes • Sample lines • Sample pumps
CEM Project Scope ( Cont’d) • New DAS by ESC for PA STEMS (Part 60) and NOx Budget (Part 75) reporting • Maintain use of existing stack flow monitors in new system • Maintain use of existing Opacity Monitor (near term)
Heated tubes (185°C PFA) • Sample gas from probe to analyzer • Spare Power for probe Heating element • Non-heated tubes (PFA-PTFE) • Calibration Gas (from calibration cylinder and solenoid valves to probe) • Isolation Air (isolation of probe from flue gas during calibration & temperature failures) • Blowback air (used for purging probe) Power for sample line heating and temperature sensors Insulation Heated Sample Line
Gas Range Interval CO 0-200 PPM, 0-3000 PPM SO2 0-150 PPM, 0 - 400 PPM 0-160 PPM NOx O2 0-25% CO2 0-20% H2O 0-30% MC3 Configuration
Project Schedule • Prelim Meeting - August 2003 • New CEM Spec Issued – August 2004 • EcoChem Selected – Sept 2004 • PO issued/Order placed – Sept 2004 • Teleconference with PADEP – Sept 2004 • Phase I Submittal – Oct 2004 • Included a listing of project milestones (testing)
Project Schedule (Cont’d) • Phase II Submittal – Nov 2004 • FAT Testing – Jan 2005 • Installation/Commissioning – Feb 2005 • Phase I and II Status Request – Feb 22 • PADEP Response – Feb 24, 2005 • Proposed Certification – March 16, 2005 • New Schedule Proposed – March 17, 2005
Project Schedule (Cont’d) • Performance Testing – April 2005 • RATA Testing – April 13 & 14, 2005 • Phase I Approval – April 18, 2005 • Submittal of Performance Testing Data – May 2005 • Submittal of Part 75 Certification EDRs – May 2005 • EDR Certification Data – App’d in 10 days • Phase III Acknowledgement Letter – June 2, 2005 (Response by July 2, 2005) • Certification is currently pending
Application Experience • Opted to utilize the electronic Phase I forms • Theory: Electronic submittal may expedite the approval process (Not!) • Completed forms encompassed 41 pages • Forms were cumbersome to work with • Some requested data was not well defined • Requested more fluff than stuff
Application Experience (Cont’d) • Requested data aids in fulfilling the Department’s CEMS database • ID codes, Result Codes, Source Codes, Analyzer Codes & CEMS Codes are meaningless to the preparer • It’s difficult to keep them straight!
Application Experience (Cont’d) • Regurgitate many of the standards in the CSMM • Defining the Lowest Monitored Standard (LMS) • LMES now replaces the old “Span”
Interaction with Department • Phase I Pre-submittal teleconference is beneficial • Also beneficial to speak with Bob Vollaro of EPA to review Part 75 issues • There was little or no communication unless we initiated it • Phone call follow-ups were initiated starting in December
Interaction with Department (Cont’d) • Exchanged LMES calculations via FAX in January • They opted not to visit the plant during installation or testing • Communication via letter stimulated the best response • The Department is still working to understand all the nuances of Rev 7. • Their plates are FULL.
Recommendations • Schedule an informal pre-submittal conference • Build a lot of time into your schedule • 1 year from Phase I submittal to Certification • Submit your project schedule with the Phase I • Understand & be clear about your LMES calculations in your Phase I
Recommendations (Cont’d) • Keep your project on the radar screen after the Phase I is submitted • Submit your Phase II early • Correspond with the Dept in writing about project milestones • Make sure the Dept understands your Part 75 issues
CEM Supplier Perspective on PADEP Rev. 7 • Awaiting Responses Caused Project Delays • Phase I Submittal Approval took >4 months • Rev. 7 Phase I Electronic Version confusing • Reconciling NOx Budget, Part 60 and PADEP overlapping requirements inefficient • PADEP Going Thru Transition
Benefits of More Current CEM Beside Simply Meeting Regulations • Hot-wet system provides moisture concentrations – assists with auditing tube leaks • New sample system and automatic audits reduces manual oversight • Enhanced remote troubleshooting reduces frequency of lengthy E&I staff call-outs • Convenient format and data access useful management tool • Avoid total obsolescence
Operator Interface and Remote System Access • Presents data in larger color screen • Most functions 1-2 touch screen taps • Provides meaningful system history to do troubleshooting right at the CEM location (fewer trips back and forth to control room or office) • Can control the system remotely PC Anywhere Excel
A Contrast in Case Histories • Removed old system and installed new CEM in three days – during scheduled outage • No overlap with original CEM • RATA test within 10 days • No “Phase I” submittal – letter notification • No NOx Budget Issues Waste Coal Plant – Utah
EcoChem’s Suggestions for a “Win-Win” CEM Upgrade • Build in sufficient scheduling contingency - allow 9-12+ months depending upon scope • Allow appropriate overlap with existing CEM – You usually don’t have a choice! • Don’t forget training and spare parts inventory • Use experienced CEM integrator & DAS vendor • Pray for Rev 8 to be more efficient