1 / 15

IAPD Session of the 2014 WIC EBT User Group Meeting July 23, 2014 11:00 AM to 12:00 PM

IAPD Session of the 2014 WIC EBT User Group Meeting July 23, 2014 11:00 AM to 12:00 PM Presented by Cheryl Owens, MAXIMUS. Agenda. Purpose of the IAPD FNS Handbook 901 Guidance What is Standard What is Not. Purpose of the IAPD.

rodney
Download Presentation

IAPD Session of the 2014 WIC EBT User Group Meeting July 23, 2014 11:00 AM to 12:00 PM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IAPD Session of the 2014 WIC EBT User Group Meeting July 23, 2014 11:00 AM to 12:00 PM Presented by Cheryl Owens, MAXIMUS

  2. Agenda • Purpose of the IAPD • FNS Handbook 901 Guidance • What is Standard • What is Not

  3. Purpose of the IAPD • To gain FNS approval to implement WIC EBT you need to demonstrate: • You understand the scope of the project • You understand the activities that you or your contractors will undertake • You understand the level of effort that will be required • You are committing sufficient resources to the effort • You have considered all elements of the implementation in your budget request If you have a QA consultant, leverage his or her knowledge of WIC EBT to fully learn about implementing and operating WIC EBT. Ask questions! Consider including EBT 101 or 201 training sessions for State Agency and local agency staff and WIC vendors in your contract with your QA consultant.

  4. FNS Handbook 901 • Updated on February 28, 2014 • Most of the content formerly required is still required • New emphasis on strong project management and oversight It’s not complicated but does require knowledge of WIC EBT and time to put it together.

  5. What is Standard (Usually) • State Agency/Contractor Assurance • You and your contractors will comply with WIC EBT standards, rules and guidelines • Request for Waiver of Depreciation • Cost Allocation Plan • State Agency Assurances • NUPC Interface • Technical Standards • Standard Business Practices

  6. What is Standard (Pretty Much) Don’t reinvent the wheel! FNS has templates and instructions, referenced in the Handbook 901. BUT FIRST - Check if there are state or agency project management standards and plans that need to be followed. These requirements will take precedence over templates from FNS – or can be supplemented with input suggested by FNS templates. • Project Management Approach and Plans • Quality Management • Risk Management • Change Management • Communication Management • Security Planning

  7. What is Not Standard • Project Management Plan and Resource Requirements • Description of MIS readiness, effort to enable it for EBT or transfer system • Implementation approach and activities • Pilot activities • Statewide rollout activities • Implementation funding • Duration • Procurement schedule • Collaboration with other State Agencies The items that are “not standard” are those that are specific to your state. These items will require the most time to gather information and make appropriate decisions.

  8. What is Not Standard Your procurement approach is dependent on your state’s procurement regulations and guidelines. Your procurement approach may not be a procurement effort but a negotiation with the state’s SNAP EBT provider or with the WIC EBT service provider contracted to another state’s State Agency. • Procurement Plan • Procurement approach • Procurement risks • Cost determination • Standard procurement documents • Approach to preparing procurement documents • Procurement decision • Contract approval

  9. What is Not Standard • A dedicated project manager is the norm. • Will you have sufficient staff to manage day-to-day business as well as: • Overall oversight (e.g., Project Sponsor) • Participate in design and review deliverables • Develop policies & procedures • Develop the UPC database • Support WIC vendors to enablement • Train local agency staff • System testing • Staffing and Project Management • Project management • Project organization, including: • State Agency • State IT • WIC EBT service provider • MIS contractor • QA contractor • FNS • Executive Steering Committee • State Agency personnel – how you will staff your project • Team responsibilities

  10. What is Not Standard Tip of the day: Develop the detailed schedule first, then complete other sections that ask for level of effort, activities, responsibilities, costs, etc. • Schedule of Activities, Milestones and Deliverables • Schedule narrative • Milestones and deliverables • Detailed schedule • Schedule management

  11. What is Not Standard • Don’t forget – • The level of effort to perform the activities shown on slide 9 • Fringe and overhead in State Agency staff costs • The IIN application • Hardware for UPC collection • Where the cost of State IT staff is placed – in NSA (if at no additional cost to the WIC Program) or in Contractor costs (if there is a fee) • Proposed Budget • Implementation costs • State Agency staff (NSA) • Contractors • Hardware and materials • Travel • Miscellaneous • Operations costs • Paper based • WIC EBT

  12. What is Not Standard Getting ready for the Retailer Enablement Plan (and budget) section is the most time consuming portion of the planning process. You need to know retailers’ enablement status – but keep in mind it will change before you go to pilot and rollout. • Retailer Enablement Plan • Status of WIC EBT enablement • Enablement approach • Enablement needs (hardware, system upgrades, etc.) • Outreach • Retailers in pilot area • Retailers in rollout regions

  13. What is Not Standard UAT training may be conducted by the State Agency, the WIC EBT service provider or the QA consultant. System operations training is provided by the WIC EBT service provider. How your State Agency will train or support training for local agency and clinic staff is specific to each state. WIC vendor training applies to those vendors with stand-beside terminals. Participant training involves decisions on types of training materials. • Training • UAT • System operations • Local agencies • WIC vendor • Participants

  14. Clinic Management Plan • How will you address: • Satellite clinics without Internet connection • Separation of duties • Ordering, securing and managing card stock • Clients transferring during rollout • Infrastructure Readiness • Clinic Conversion and Schedule • Clinic Processes with EBT

  15. Thank You! Cheryl Owens MAXIMUS 571-218-5214 cherylowens@maximus.com

More Related