3. 2. 1. CONTRACT IMPLEMENTATION STATUS OF SUPPLY OF SOLAR PV SYSTEM UNDER REP LOT 2-LOT 5. Prepared By:- Er . Rabindra Shrestha Er . Samata Shrestha. Far Western DR (Lot 2) Baitadi Doti Accham Bajura Bhajang Darchula. CONTRACT IMPLEMENTATION AREA. MidWestern DR (Lot 3)
E N D
CONTRACT IMPLEMENTATION STATUS OF SUPPLY OF SOLAR PV SYSTEM UNDER REP LOT 2-LOT 5 Prepared By:- Er. Rabindra Shrestha Er. Samata Shrestha
Far Western DR (Lot 2) Baitadi Doti Accham Bajura Bhajang Darchula CONTRACT IMPLEMENTATION AREA MidWestern DR (Lot 3) Humla Jumla Mugu Dolpa Salyan Western DR (Lot 4) Gorkha Myagdi Mustang Central DR (Lot 4) Dhading Dolakha Ramechhap Eastern DR (Lot 5) Panchthar Taplejung Sankhuwasabha Okhaldhunga
PROJECT DESCRIPTION Total Number of Packages (796: 653 + 143 additional)
PROJECT DESCRIPTION (contd…) Number of Packages (Lot wise including 143 additional systems)
SCOPE OF WORK Equipment Collection Clearance and Sorting Transportation to Site Hub Distribution to End User Training Installation Commissioning
A E B D IMPLEMENTATION STRATEGY Sorting and Packing in Centralized Facility Training and Commissioning Delivery Planning Installation Coordination Meeting with REP and CO’s before Installation C
SORTING AND PACKING IN CENTRALIZED FACILITY • Butwal for Lot 2, Biratnagar for Lot 5, Surkhet for Lot 3, Pokhara • and Kathmandu for Lot 4
DELIVERY PLANNING • Transportation to Road-Head via Truck(over the blacktopped • and primary road) • Transportation to Sites (secondary roads and foot trails) in • Coordination with CO’s and End Users • Distribution of Equipments to the End Users by Porters • Mobilization of Local People for Transportation
INSTALLATION • Deployment of Installation Team after Delivery of Equipments • At least One Local Person to Assist and Receive Basic • Installation Training
TRAINING • Combined Operation Maintenance Training to End • Users, Member of CO and Local People
CHALLENGES 3 1 4 2 Deployment of Huge Installation Team Sorting and Packing Huge Volume of Equipments Maintaining Coordination among CO’s, End Users and Installation Team Delivery of Equipments to Respective Sites
IMPLEMENTED SCHEDULE (LOT 2 & LOT 5)
IMPLEMENTATION SCHEDULE (LOT 3 & LOT 4)
UNFORSEEN PROBLEM Time Consumed in Custom Temporary Inaccessibility During Rainy Season Temporary Inaccessibility During Winter Season
CONCLUSION • We have implemented the project on time as per the schedule • We are committed to complete the initial allocated projects as well as additional projects with little deviation in allocated time as the number of projects have been increased by 25% • We have maintained the high level quality standards as per the contract • We have tried to provide maximum benefits to the Locals by providing them opportunities like temporary employment and valuable trainings