An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RCT Shift Report 29 July - 5 Aug. 2009 Jessica Leonard next shifter: Kira

  2. DCS/Hardware Summary • 29 July 2009 cooling problems • High dewpoint caused cooling to shut off • RCT on and off from ~1 - 6 PM • Turned back on after assurances cooling was okay • 2-3 August 2009 “offline” periods • RMCs 1, 2, 10 briefly appeared offline night of 2 August • RMCs 4, 9, 10 early morning of 3 August • 4, 10 “came back” right away • 9 still appeared offline until CMSfwRCT_sendToRMC.ctl script restarted

  3. Pattern tests • 30 July (during dedicated maintenance shifts) • New problems • EM Crate 1 card 6 -- low 2-bit • EM Crate 6 most cards -- ordering and/or stuck bits • EM Crate 7 all cards -- low 16-bit in isolated stream • Showed up in most patterns, not just one or two • HF Crate 15 -- HF tower 1,5 low 32-bit • Pattern tests planned for maintenance shifts tomorrow, magnet ramp Friday

  4. Shift Call • 29 July evening: shifter requested all of EB be unmasked (two supermodules had been masked) • Called Pam, who did the unmasking • Pam then gave some of us a mini tutorial session the next day on how to mask/unmask channels/supermodules so we can do it ourselves

  5. DQM • CRAFT09 • Run 109603 • EEG_EHSUMS_TAU3_DECO_25_CRAFT09 • Aug. 2, 208 minutes • Looked at 20k events • HCAL problem fixed with new global tag, plots look much better! • More CRAFT long runs available online at https://test-rct.web.cern.ch/test-Rct/

  6. Iso Electrons (109603) None of these errors seen in pattern tests or correspond to masked channels Light green and yellow spots come and go Persistent

  7. HF bit + tau bit (run 109603) • Persistent

  8. Region sums (run 109603) • Known: HF ET problem • Light green and yellow spots come and go • Light green/dark green structure persistent in overlap eta row • Persistent (one source card)