1 / 18

Status Report on Bonding at Catania

Status Report on Bonding at Catania. Salvatore Costa University and INFN – Catania. Machine Fix, Upgrade,Tune-up. …Wire breaking problem… Help from colleague with extensive past experience with Hughes, Enrico Scarlini of Florence (thanks!)

ross-curry
Download Presentation

Status Report on Bonding at Catania

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report on Bonding at Catania Salvatore Costa University and INFN – Catania

  2. Machine Fix, Upgrade,Tune-up • …Wire breaking problem… • Help from colleague with extensive past experience with Hughes, Enrico Scarlini of Florence (thanks!) • Adjusted bonding parameters [e.g. a much lower ”Z speed”: 10 vs. 100, default is 231, do not exceed 20] • Replaced tool • Mounted wire despooler • Disabled upper wire clamp • Lubricated head travel shafts (it would not reach full rest position or it would jam onto piece) • Cleared axis initialization failures

  3. Bonding Test # 2 (1) • Pre-Bonding visual inspection under microscope showed same damaged pads (scratches across rows of pads) in PAs. [Piece was no longer sticking to ESD box when I opened the box]. • Used Hughes loop mode “5”, a simple 1-parameter (loop height) arch. • Set loop height=150 (mm or .1 mil ?) …measure ?… for all bonds (SEN-SEN and PA-SEN)

  4. Bonding Test # 2 (2) Test bonds on Test Areas… • (Destructive) Pull Tests with automatic Puller: • 8-12 g break force • mid-span break

  5. Bonding Test # 2 (3) HPK - ST SEN bonds • Used following bond parameters (for both ends): • Force: 20 • Time: 40 • U/S: 55 • No problems during bond program execution • Post-Bonding visual inspection: All bonds OK

  6. Bonding Test # 2 (4) PA - HPK SEN bonds • Used same bond parameters as for HPK - ST SEN bonds • Some problems during bond program execution: • Wire would not hold onto scratched spots of pads manually bonded choosing a different spot on pad • 3 funny loops pulled out and redone • 1 wire almost touching neighbor gently pushed aside with pliers • At last bond, PA seemed short of 1 pad: First one missing!

  7. Bonding Test # 2 (5) PA - ST SEN bonds • Using same bond parameters as for HPK - ST SEN or PA - HPK SEN bonds, wire would not stick to PA pads • Increased some parameters: • Time: from 40 to 50 • U/S: from 55 to 65 • At visual inspection first few SEN pads will show traces of pulled wires from SEN pad • Except for this, all bonds should be OK.

  8. Bonding Jig • Being distribued by Filippo Bosi, Pisa • Got “Type 1” jig for (single sided) TIB modules • Should get “Type 2” jig for (double sided) TIB modules sometime • He said he is currently designing jigs for stereo TIB and for TID modules

  9. BondingTool • From Saneco, n. 4284 • Concave…

  10. Test System • We have identified a person in charge of this • ARC has been installed and is going to be tested

  11. Bonding Lab Upgrade • Purchased (for a nominal price) a second (used) Hughes, being dismissed by CERN • Will transport to Catania tomorrow • Might be operational in September (after we move to new building)

  12. NextStep Bonding a dummy module Bari has promised they will assemble a dummy module for us to bond ad soon as HPK sensors arrive

  13. …break…

  14. DataBase Interface Update Salvatore Costa University and INFN – Catania

  15. Interface Releases (1) • Version 0.1 was released on 13 March 2002 • Non-working evaluation version: • See interface look • Stimulate communication of center-specific input data from Center DB responsibles to me. • Version 0.2 to be released soon • Working evaluation version: • Exercise all functions • Will include User’s Manual • Includes people’s comments to v. 0.1 • Center specific defaults and lists (where available) • All data stored in Catania…will eventually be deleted!

  16. Interface Releases (2) • Version 1.0 will follow shortly • Production version: • Available for download from Web site in Catania • Will include installation instructions • Installation will create Center-specific version (same look, different default and list values) • Initially for Unix only, will make version for Windows if requested • Data will be stored locally to Center and will be broadcast to TrackerDB when “VALIDATED”

  17. Center “DB Readiness”

  18. Data Recording In TrackerDB • Do we all agree that, as it is currently foreseen in the Interface v. 0.1, PRE-BONDING, BONDING, POST-BONDING and BONDING REPAIR data are independently recorded in the central TrackerDB as soon as they are individually VALIDATED? • Of course the Interface will have itself checks so that you cannot VALIDATE, say, POST-BONDING data until BONDING data have been.