MINISTRY OF RAILWAYS NORTHEAST FRONTIER RAILWAY (CONSTRUCTION ORGANISATION) 62nd PLENARY SESSION OF NORTH-EAST COUNCIL AT NEW DELHI 16th JULY-2013
INVESTMENT IN N.E REGION OVER LAST 5YEARS (NEW LINES, GAUGE CONVERSION & DOUBLING) Total –Rs 10,503 Crs(Last 5yrs) Rs in Crore
NEW LINE, GAUGE CONVERSION & DOUBLING IN NORTH EAST REGION - COMPLETED IN LAST 5(FIVE) YEARS KM
New Line , Gauge Conversion, Doubling completed in NE Region since its inception in 1979
Rly. Budget 2013-14: New Projects Sanctioned for the North East Region
Rly. Budget 2013-14: New Surveys Sanctioned for the North East Region- SURVEY COMPLETED ON GOING SURVEY
NE REGION OUTLAY SUMMARY FOR 2012-13 & 2013-14
ADDITIONAL FUND REQUIREMENTS IN 2013-14 FOR PROGRESSING ALL THE WORK AND COMPLETING THE PLANNED TARGET IN N.E REGION • Additional fund required in 2013-14 for • Projects targeted to be completed in 2013-14 -Rs 500 Crs • Additional fund required in 2013-14 for • smooth progress of Projects targeted to be • completed in 2014-15 - Rs 2007 Crs • Additional fund required in 2013-14 for • projects targeted to be completed beyond • 2014-15 - Rs 636 Crs • Total Additional fund Required • in 2013-14 = Rs 3143 Crs • Total Fund Required in 2013-14 = Rs 2498(B. Grant)+3143(Add.Fund Reqd.) • =Rs 5641Crs
PROJECT WISE COST,EXPENDITURE & BALANCE REQUIREMENT OF FUND IN N.E REGION
PROJECT WISE COST,EXPENDITURE & BALANCE REQUIREMENT OF FUND IN N.E REGION
PROJECT WISE COST,EXPENDITURE & BALANCE REQUIREMENT OF FUND IN N.E REGION
PROJECT WISE COST,EXPENDITURE & BALANCE REQUIREMENT OF FUND IN N.E REGION
PROJECT WISE COST,EXPENDITURE & BALANCE REQUIREMENT OF FUND IN N.E REGION
PROJECT WISE COST,EXPENDITURE & BALANCE REQUIREMENT OF FUND IN N.E REGION
ISSUE OF CONCERN AND ASSISTANCE REQUIRED. 1. Non-availability of adequate fund as proposed. 2. Forest Clearance for Land. 3.Expeditious land transfer to the project from State Govt. 4.Improving condition of State /National Highways for smooth transportation of construction materials and machineries to the project site. 5.Militant activity and prevailing security Scenario in North East Region.
ASSAM STATE – PROJECTS IN DETAIL
Rail cum road bridge over river Brahmputra near Bogibeel with Link lines
Rail cum road bridge over river Brahmputra near Bogibeel with Link lines • Name : Bogibeel Bridge with linking lines between Dibrugarh and North Bank (National Project). • 1. Project Details: • Year of Inclusion : 1997-98 • Total length.(Assam) :73 km including 5 km of bridge • Anticipated cost :Rs.4997 crore • Expenditure upto 31-03-2013 :Rs.2701 crore • Fund allocation in FY 2013-14 :Rs.440crore • Additional fund requirement in 2013-14 :Rs 240 crore(For planned TDC) • Target date of completion :December’15 • (Subject toavailability of Fund) • December-17 • (With present funding level) • Overall Progress(Financial) :54%
Rail cum road bridge over river Brahmputra near Bogibeel with Link lines
Rail cum road bridge over river Brahmputra near Bogibeel with Link lines 2. Present Status: • Chalkhowa-Moranhat - • South bank Rail link (44 Km) : Completed • South Guide Bund : Completed • North Guide Bund : Completed • 22 kms of rail link on North Bank • (14 km) and South bank (8 km) : Completed • Main bridge Substructure : June-14 • Main bridge Superstructure : Dec-2015 • (Subject to fund availability)
Rail cum road bridge over river Brahmputra near Bogibeel with Link lines Present Progress of the Project Main bridge Sub-structure Target of Sub-structure work : June-2014
Rail cum road bridge over river Brahmputra near Bogibeel with Link lines (NATIONAL PROJECT) • 5. Time over Run factors: • Due to Change in rivercourse and flash flood, total length of bridge increased from 36nos. of spans to 41 spans. • land availability: i.Upto 50% after 2yrs (2004) • ii.Upto 75% after 10yrs (2008) • iii.Upto 100%, after 14yrs (2011) • Thus, after 14yrs, Total land could be made available by State Govt. • Fund Availability: • i.1997-98 to 2003-04 : 162.02Crs @av 23crs per yr • ii.2003-04 to 2007-08: 681crs @av 227crs per yr • iii.2007-08 to 2012-13 : 1731crs @av 346crs per yr • Thus, after 15yrs, only 51% budget grant allotted since inception of the project in 1997-98
Name of project- New Mainaguri- Jogighopa new line project including MM of New Mal Jn- Changrabandha GC . • 1- Projects details- • Year of Inclusion : 2000-01 • Total Length(Assam-126Km, W.Bengal-119Km) : 257Km • Anticipated Cost : 2350 crs • Total expenditure up to Mar’13 : 1347 crs • Fund Allocation in FY 2013-14 : Rs 140 crs • Additional fund required in FY 2013-14 : Rs 645 crs • (For planned TDC) • Target of completion : March-15 • (Subject to availability of fund) • :March-18 • (Withpresent funding level) • Overall progress(Financial) :57%
Name of project- New Mainaguri- Jogighopa new line project including MM of New Mal Jn- Changrabandha GC .
Name of project- New Mainaguri- Jogighopa new line project including MM of New Mal Jn- Changrabandha GC . • 2.Present Status – • Activity Total Scope progress % progress • Land (Hect) 1064 924 87 • Earth Work(L-Cum) 210 120 57 • Minor bridges(Nos.) 331 248 75 • Major bridge ( Substructure) 68 48 71 • Major Bridge( Superstructure) 68 47 69 • Track linking 288 191 66 • Overall Progress (Physical) 71%
Name of project- New Mainaguri- Jogighopa new line project including MM of New Mal Jn- Changrabandha GC . • 3. Assistance required - • Additional Fund of Rs 645crs is required in 2013-14 to complete the project as per planned TDC. • 4. Issue of Concern- • Work is affected in approx. 28 Km length of the section due to land problems. • Land Acquisition process lapsed due to public representation for higher compensation. • Fresh Land acquisition process has been initiated for which U/S 4(1) and 6(1) has been done and estimate is under sanction of State Govt. • State Govt. should expedite the handing over of land to Railway for early commissioning of the section.
Name of project- New Mainaguri- Jogighopa new line project including MM of New Mal Jn- Changrabandha GC . • 5. Time over Run on the projects: • land availability: i.Upto 50% after 6yrs (2007) • ii.Upto 65% after 10yrs (2012) • iii.35% land not yet handed over • Thus, after 12yrs, only 65% land could be made available by State Govt. • Fund Availability: i.2000-01 to 2007-08-174.93Crs • @22crs per yr • ii.2007-08 to 2012-13-1084.19crs • @217crs per yr • Thus, after 12yrs, only 60% budget grant allotted since inception of the project in 2001-02