An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Qatar RailwaysDelivery of an Integrated Railway Network

  2. Delivery of Qatar Rail Program Qatar Rail… a journey together Supporting the Qatar 2030 Vision by providing a World Class Integrated Transport System, reducing congestion and improving the Quality of Life for Qatar’s people

  3. Metro Network Final Alignments Proposed Metro network Supporting Qatar’s 2030 vision

  4. Metro Network for FIFA FIFA- (Approved requirements) Alignment approved Stations approved Land acquisition underway Utility diversions under design Railway Law and Legislation in Final Draft

  5. Long distance and high speed passenger Long Distance rail network linking Bahrain Causeway and GCC network High speed to Dukhan and RasLaffanusing freight railway Study for alignment and demand for commuting services to be carried out in 2012

  6. Freight Rail The plans for domestic and International freight being designed during 2012 The transfer of freight to the New Doha Port in 2015 alone will relocate 0.75-1.0 M TEU pa of Container Freight on to the roads between Mesaieed and Greater Doha

  7. Lusail Light Rail Phase 1 of the LLRT is under construction with target of August 2016 for start of operations This will be Qatar’s 1st operational railway System (Design, Build & Maintain) Tenders are now being evaluated Shadow / Early Operator required during 2012/13

  8. West Bay Transit West Bay road system is crowded and theCross Doha Bay Crossing and Lusail Expressway will add to the burden. Consultants appointed to consider thefeasibility of an alternative transit solution. This needs to be part of a comprehensive Land Use/Integrated transport strategy.

  9. Corporate development • Qatar Rail is now an established company with delegated powers to contract • Organizational chart is finalized • Business plan and budget are set • Finance, HR policies and procedures agreed and being implemented. • Team increased from 12 people 1 year ago to 150 employees and 150 consultants • Qatar Rail moved to its 18th floor headquarters

  10. Communication and stakeholder management • Corporate campaign • Industry awareness • Material and plant supply conference

  11. Design • Urban integrated plan example

  12. Design of stations • Architectural conception underway

  13. Commercial and contract • Key Contract Milestones • Contract schedule is set Q2 2012 Q2 2012 Q2 2012 Q4 2012 (total of 6 years for D&B) Q2 2013 Q1 2014 Q2 2014 Q2 2015 Q3 2018 Q4 2019

  14. Questions?