1 / 5

MTA Schedule and Issues

MTA Schedule and Issues. Schedule for MTA. Highest Priority goes to vacuum RF studies – 805 button cell and 201 MICE prototype Button runs take about 3 weeks total Maybe we can speed this up with automation? We have 10 potential samples plus 5 or so from the UK 45 weeks of data taking!

Download Presentation

MTA Schedule and Issues

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MTA Schedule and Issues

  2. Schedule for MTA • Highest Priority goes to vacuum RF studies – 805 button cell and 201 MICE prototype • Button runs take about 3 weeks total • Maybe we can speed this up with automation? • We have 10 potential samples plus 5 or so from the UK • 45 weeks of data taking! • 201 running can for the most part run in parallel • But we have to move the 201 to gain access to change out buttons on the 805 • Second round of KEK convectively cooled LH2 absorber tests • We were attempting to do this in August (3 weeks), but we do not know if our Japanese colleagues can make it to Fermilab then • Muon’s Inc HP cell tests (their first draft of run plan – 22 weeks) • Some tests also need magnet • Requires 805 button cell to be removed • Manpower issue for fast turn-around • Beam tests – how and when?

  3. Schedule for MTA • Reconfiguration of MTA • Raise components to beam height • Install cryo-infrastructure • Transfer line system • valve boxes • Cryogen hookup to magnet • Estimate 3-4 month down time • Impact of Beam line installation during shutdown still not fully understood • Need to develop run schedule for August – July08 over the next month

  4. 201 MHz Cavity Operation in B Field • Initial 201 MHz operation in B Field • Limited to few hundred Gauss • Using Fringe Field of 4T magnet (in blue) • Need new vac pump to allow 201 to be moved right next to magnet • Gives 1T at window • Want to run with Coupling Coil as soon as it is available

  5. Reconfiguration of MTA • Need Coupling Coil (2.5T) MICE design • Shown in green schematically • THIS IS A CRUCIAL TEST FOR MICE AND FOR NF & MC in general • High Gradient RF operation in a magnetic field

More Related