Hybrid Algorithm for mean T. Baker p.49. Hybrid Algorithm : Dominance matrix to decompose problem in to sub-problems. Branch and Bound. Original problem for DP n! = C(n,1) + C(n,2) + ………….+ C(n,n) 30~35 jobs → out of computation time. N!. N 1 !.
E N D
Hybrid Algorithm for mean T Baker p.49 Hybrid Algorithm: Dominance matrix to decompose problem in to sub-problems. Branch and Bound Original problem for DP n! = C(n,1) + C(n,2) + ………….+ C(n,n) 30~35 jobs → out of computation time N! N1! N2!
Decomposition Ex. Divide 50 persons into 4 subgroups by according to their height. Mutual exclusive S Decompose S1,S2,………,Sn and For any , put i in Then the objective function
Hybrid Algorithm Notation: SPT EDD
Bj tj Hybrid Algorithm Property 3.2: (i before j) Property 3.3: (j before i)
Steps: Baker p.51
Final table 2-5-1-4-6-7-XXX-10 389
By DP 2-5-1-4-6-7-9-3-8-10
HW. Use Hybrid to solve
Single Machine Heuristics Sule p.14 • Earliest Due Date (EDD) Rule • Cost Over Time (COVERT) Rule • Shortest Processing Time (SPT) Rule • Largest Penalty per Unit Length (LPUL) Rule • Largest Weight (WT) and LPUL Rule • Shortest Processing Time and LPUL Rule • Shortest Weighted Processing Time (SWPT) Rule • Critical Ratio (CR) Rule
COVERT Notations: TT - Total processing times of all jobs RT - Remaining total processing times of the set of unscheduled jobs ST - Starting time for the next scheduled job,0 for the first job CF - Coefficient PR - Priority
PR=0 PR=1 Di TT Pi ST+Pi ST COVERT Rules Step l: calculate PR for all jobs RT Step 2: calculate CF for job i, yet to be scheduled. Step 3: Job with the Max CF is scheduled next. Repeat step1
Ex. Iteration 1. Step l : Caculate PR TT=93 RT=93
Ex. Step 2: Step3: job 3 is scheduled. Iteration 2. . . . .
Backward & Forward Method • Backward&ForwardMethod Initial scheduled Improve:Swapping to jump out the local optimal • Use any one of the Lower Bound Heuristic method • Not the optimum
BF Method 5 jobs X X X X X 5 4 3 2 1 4: 5 – 1 3: 5 – 2 , 4 – 1 2: 5 – 3 , 4 – 2 , 3 – 1 1: 5 – 4 , 4 – 3 , 3 – 2 , 2 –1 Lag =
Ex. (1) Backward Phase: Step1. TT = 37+27+1+28 = 93 Calculate the penalty for each job if it is to be complete at T=93. Job1: (93-49)*1=44 Job2: (93-36)*5=285 Job3: (93-1)*1=92 Job4: (93-37)*5=280 • job 1 has the least cost, so it is scheduled in the last position
EX. Step2. T= 93-37 = 56 Calculate the penalty for each job if it is to be complete at T=56. Job2: (56-36)*5=100 Job3: (56-1)*1=55 Job4: (56-37)*5=95 • job 3 has the least cost, so it is scheduled in position 3
EX. Step3. T= 56-1 = 55 Calculate the penalty for each job if it is to be complete at T=55. Job2: (55-36)*5=95 Job4: (55-37)*5=90 • job 4 has the least cost, so it is scheduled in position 2 Step4. The final sequence 2-4-3-1 The total penalty for the sequence 2-4-3-1 is (18*5)+(55*1)+(44*1)=189
Ex. (2) Forward Phase: Initial sequence : 2-4-3-1 penalty = 189 Lag = 3 : 1-4-3-2 penalty = 490 – no change Lag = 2 : 3-4-2-1 penalty = 144 – change New sequence : 3-4-2-1 penalty = 144 Lag = 3 : 1-4-2-3 penalty = 644 – no change Lag = 2 : 2-4-3-1 penalty = 189 – no change Lag = 2 : 3-1-2-4 penalty > 144 – no change Lag = 1 : 4-3-2-1 penalty = 172 – no change Lag = 1 : 3-2-4-1 penalty = 139 – change New sequence : 3-2-4-1 . . . We can get the final sequence is 3-2-4-1
HW. • Use Forward + Covert to solve the following problem : (or you want to compare your solution with BF)