330 likes | 387 Views
This presentation outlines existing conditions, design objectives, mechanical alternatives, electrical options, construction and life cycle cost analysis at Straumann USA. Kevin Kaufman discusses mechanical system comparisons, VAV and DOAS system advantages, and energy cost comparisons for various options, such as direct-fire absorption chillers. The focus is on energy efficiency and cost-effectiveness in the renovation project at Straumann USA.
E N D
Straumann USA 60 Minuteman Road Andover, MA Kevin Kaufman Mechanical Option The Pennsylvania State University Architectural Engineering
Presentation Outline Existing conditions Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Straumann USA • INTRODUCTION • Existing • Conditions • Design • Objectives • Mechanical Alternatives • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Building Background Straumann USA • Introduction • EXISTING • CONDITIONS • Design • Objectives • Mechanical Alternatives • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Manufacturing Area • Manufacturing storage and support areas • Dental training and operatory • Administrative offices Kevin Kaufman Mechanical Option
Original Project Straumann USA • Introduction • EXISTING • CONDITIONS • Design • Objectives • Mechanical Alternatives • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Renovation of 153,000ft2 • Complete airside upgrade • No central plant changes • Construction May 2004 – May 2005 • Cost $10.6 million Kevin Kaufman Mechanical Option
Mechanical Systems Straumann USA • Introduction • EXISTING • CONDITIONS • Design • Objectives • Mechanical Alternatives • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • 9 VAV AHU’s • 1 CAV AHU • 2 natural gas boilers • (11.3 MBH) • 3 centrifugal chillers • (750, 500, 350 tons) • 2 cooling towers • (750, 680 tons) 1st Floor Mezzanine Kevin Kaufman Mechanical Option
Design Objectives Straumann USA • Introduction • Existing • Conditions • DESIGN • OBJECTIVES • Mechanical Alternatives • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Educational experience • Reduce annual energy costs • Provide a lower 20 year LCC Kevin Kaufman Mechanical Option
System Comparisons Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Airside • VAV vs DOAS • Waterside • Chillers • Direct-fire Absorption • Electric Centrifugal • Waterside Free Cooling • Series • Parallel Kevin Kaufman Mechanical Option
VAV System Advantages Single system for ventilation and space cooling Full air side economizing available Lower pumping costs than DOAS Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
DOAS System Advantages Reduced fan energy costs Smaller air-handling units require less space and are cheaper Decouples sensible and latent loads Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
DOAS Rooftop Unit Zones Reduced from 10 to 8 zones RTU-1 RTU-5 RTU-2 RTU-6 RTU-3 RTU-7 RTU-4 RTU-8 Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
DOAS Design Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Radiant panel capacity – 54 Btu/ft2 • Space DPT – 55°F • Water MWT – 56.5°F Radiant Panel (Sterling) • Ventilation rate – ASHRAE 62.1 • Design Temperatures • Winter – 7.7°F • Summer – 90.8°F/73.7°F Kevin Kaufman Mechanical Option
Annual Energy Cost Comparison Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Direct-fire Absorption Chiller Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Reduce electric load and demand • Natural gas available on site • Possibility for simultaneous heating and cooling Absorption Chiller (Carrier) Kevin Kaufman Mechanical Option
Chiller Annual Energy Comparison Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Waterside Free Cooling - Parallel Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Reject heat without a chiller • Must be able to reject entire load Kevin Kaufman Mechanical Option
Waterside Free Cooling - Parallel Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Reject heat without a chiller • Must be able to reject entire load Kevin Kaufman Mechanical Option
Waterside Free Cooling - Parallel Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Reject heat without a chiller • Must be able to reject entire load Kevin Kaufman Mechanical Option
Waterside Free Cooling - Series Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Partially or completely rejects heat from chilled water • Operates more hours than parallel • Requires more complex controls Kevin Kaufman Mechanical Option
Waterside Free Cooling - Series Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Partially or completely rejects heat from chilled water • Operates more hours than parallel • Requires more complex controls Kevin Kaufman Mechanical Option
Waterside Free Cooling - Series Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Partially or completely rejects heat from chilled water • Operates more hours than parallel • Requires more complex controls Kevin Kaufman Mechanical Option
Waterside Free Cooling - Series Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Partially or completely rejects heat from chilled water • Operates more hours than parallel • Requires more complex controls Kevin Kaufman Mechanical Option
Waterside Free Cooling - Results Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Electrical Breadth Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • ELECTRICAL • BREADTH • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Electrical Breadth Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • ELECTRICAL • BREADTH • Construction Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Construction Breadth Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • Electrical • Breadth • CONSRUCTION BREADTH • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Construction Breadth Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • Electrical • Breadth • CONSRUCTION BREADTH • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Life Cycle Cost Analysis Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • Electrical • Breadth • Construction • Breadth • LIFE CYCLE • COST ANALYSIS • Conclusions Kevin Kaufman Mechanical Option
Conclusions Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • Electrical • Breadth • Construction • Breadth • Life Cycle • Cost Analysis • CONCLUSIONS • DOAS has a higher initial cost but has a lower annual operating cost and can be paid back in 3.7 years. • Absorption chillers increase annual operating costs. • Series waterside free cooling adds a few additional hours of free cooling but will add more complex controls. Kevin Kaufman Mechanical Option
Acknowledgements Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • Electrical • Breadth • Construction • Breadth • Life Cycle • Cost Analysis • Conclusions • AE Department • Mechanical Faculty • Bruce Chappell • William McGee • Paul Petrilli • Straumann USA • Brickstone Companies • Justin Bem • Markus Benzenhofer Questions? Kevin Kaufman Mechanical Option
Chiller Heater Feasibility Straumann USA • Introduction • Existing • Conditions • Design • Objectives • MECHANICAL ALTERNATIVES • Electrical • Breadth • Construction Breadth • Life Cycle • Cost Analysis • Conclusions • Heating requirements: 3222 hrs • Simultaneous heating/cooling available: 733 hrs • Capable of meeting heating load: 507 hrs (16%) Kevin Kaufman Mechanical Option
Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • Electrical • Breadth • Construction • Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • Electrical • Breadth • Construction • Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option
Straumann USA • Introduction • Existing • Conditions • Design • Objectives • Mechanical • Alternatives • Electrical • Breadth • Construction • Breadth • Life Cycle • Cost Analysis • Conclusions Kevin Kaufman Mechanical Option