An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Efficiency Measures in Island County Improving the Permitting Process in the Shoreline Environment Presented by: Helen Price Johnson – Island County Commissioner William Simpson – Island County Planning & Community Development

  2. Agenda

  3. Focusing on Type I Shoreline Exemption Applications Shoreline Planning Jurisdiction • 196 miles of Marine Shoreline • 11 miles of lake shoreline • High volume of shoreline permits • Problems with delayed permits, complaints, and public perception • Permitting backlog affected other land use permits

  4. Goals and Strategies

  5. Implementation Measures • Daily stand-up meetings for the first 45-60 days • Revised Type I and Type II Shoreline Exemption Permit Applications • Require submittals by appointment • Planners review applications upon submittal • Training with Permit-tracking software/protocol review • Restructured work space • Revised schedules to minimize distractions • Interdepartmental GIS needs assessment

  6. Results • As of June 3, 2013: • Type I Shoreline Exemption Permits accepted: 44 • Average processingtime: 32 days • Reduction in processing time: 56 days

  7. Personal Reflections • Value of Kaizen comes from the opportunity to collectively step back, evaluate the process, and reform the process • Staff needs support from management & elected officials • Dynamics in local government are inherently different than in the private sector • Requires commitmentat the staff level • Demands flexibility during the implementation stage • Communication with the public is vital