An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tier-0 Power needs estimates May 2010 Update on Computing at CERN - Frédéric Hemmer

  2. Plans for 2010-2012 • Consolidation of the existing 513 capacity • 600 KW of backed-up power • 3.5 MW of Physics capacity • Issue: not before mid 2012! • Provision of “container” style of capacity • Incremental addition of ~400 KW units • Issue: not before mid-2012! • Investigations of remote capacity usage • As a logical extension of 513, not as Grid/Cloud capacity • Already experimenting 100 KW in the Geneva area • But is this really (economically) feasible? Update on Computing at CERN - Frédéric Hemmer

  3. Upgrade Milestones • All Market Surveys to be started June 2010 • Site committee September 2010 • Barn to be cleared by the end of October • Adjudication of contracts at March FC • CE works completed July 2011 • EL+CV installations Aug/2011-May/2012 • Increased physics power not available before end Feb 2012 • Increased critical power not available before end May 2012 Computer Centre Upgrade - 3

  4. Containers • Initial provisioning of up to three 300 KW containers, • with a infrastructure capable of 5-6 of such containers on the Prévessinsite (close to building 983), • to accommodate incremental computing capacity increases during the period 2012-2014. • The cost of the underlying infrastructure is estimated at 3 MCHF1 (cost of containers excluded) and • could be made available mid 2012 earliest (civil engineering and associated build permit is needed for modifying/replacing building 983). • Costs of individual containers are currently estimated at 2.5 and 3 MCHF for non-critical and critical equipment respectively. • Containers could also be the solution to accommodate for so-called “private Tier-2’s” requests, where individual institutes are asking for computing equipment to be hosted at CERN. Update on Computing at CERN - Frédéric Hemmer

  5. Remote hosting • Presentation to FC by Sergio Bertolucci • Call for proposals Update on Computing at CERN - Frédéric Hemmer