120 likes | 492 Views
PASCOR Group. Industry Adviser : Craig Smit Product Engineer Faculty Adviser : Chien Wern, Ph.D. Presenter : Joe Hartley Team Members : Jeremie Bilisari Steve Greene Robby Hoff Matt Smith. Overview. Background Mission Statement Project Plan Project Scope
E N D
PASCOR Group Industry Adviser: Craig Smit Product Engineer Faculty Adviser: Chien Wern, Ph.D. Presenter: Joe Hartley Team Members: Jeremie Bilisari Steve Greene Robby Hoff Matt Smith
Overview • Background • Mission Statement • Project Plan • Project Scope • Project Design Specifications • House of Quality • Conclusion
Background • PASCOR – Pacific Air Switch Corporation
Background • Brazing Process
Background • Current Strip Forming System
Mission Statement • Develop a fully automated silver strip cutting and forming device. The device is required to produce formed strips quickly and accurately while also being robust and portable.
Project Plan • Internal/External Search Presentation - February 20th • Conceptual and System Design - March 30th • Prototype Construction and Testing - April 15th June 7th
2”, 3”, 5” & 6.5” 1/4” Tolerance ( +/- 1/16” ) R=1/4” Project Scope • Customers -Internal -External • Design Constraints - Formation - Tolerance - Rate of Production
Project Design Specifications • High Priority Criteria -Safety: Emergency Switch & Safety Guards - Performance: Adjustability, Tolerance & Parts/sec. • Medium Priority Criteria -Durable - Use of Replaceable Parts -Cost of Production < $5,000 • Low Priority Criteria -Curvature of Strips
Conclusion • Design a high quality strip/forming device. • Deliver a working prototype by June ’06. • Keep cost below set budget.