Steam Net Simulation at Borealis' Cracker Site in Stenungsund

This presentation discusses the steam network simulation at Borealis' Cracker site in Stenungsund, presented at the Nordic Process Control Workshop in Porsgrunn on January 29, 2009. It covers topics such as power engineering, process engineering, automatic control, chemical engineering, computer technology, mathematics, and nuclear power safety.

sallen
Download Presentation

Steam Net Simulation at Borealis' Cracker Site in Stenungsund

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Steam Net Simulation at Borealis' Cracker Site in Stenungsund Presentation at Nordic Process Control Workshop 15, Porsgrunn 29 January 2009 Veronica Olesen

  2. Solvina Västerås Göteborg

  3. Solvina • Power Engineering • Process Engineering • Automatic Control • Chemical Engineering • Computer Technology • Mathematics • Nuclear Power Safety • Power Engineering • Process Engineering • Automatic Control • Chemical Engineering • Computer Technology • Mathematics • Nuclear Power Safety

  4. Borealis Stenungsund

  5. Borealis Stenungsund New LP steam from LD5 HP steam Ethylene

  6. Cracker Steam Net From production HP To PE Boilers MP From LD5 New New LP Dump To processes

  7. Trip of LD5 From production To PE Boilers From LD5 Dump To processes

  8. Trip of LD5 From production To PE Boilers From LD5 Dump To processes

  9. Trip of LD5 From production ? To PE Boilers ? Major pressure drops ? From LD5 Dump To processes

  10. Pressure Control From production To PE Boilers From LD5 Dump To processes

  11. Findings • Restrictions necessary on the PE site to slow down the course of events.

  12. Findings PI PI PI • Restrictions necessary on the PE site to slow down the course of events. • Use the same measuring point for all control loops in the LP net.

  13. Findings • Restrictions necessary on the PE site to slow down the course of events. • Use the same measuring point for all control loops in the LP net. • Feed forward needed in boiler control Acceptable pressure range t0

  14. Findings • Restrictions necessary on the PE site to slow down the course of events. • Use the same measuring point for all control loops in the LP net. • Feed forward needed in boiler control • Dynamic simulations necessary prior to mayor changes.

  15. Thank you for listening Questions? http://www.solvina.se/