January 9, 2010 Fermilab 101Fermilab Community Advisory Board The Finances of Fermilab 101
Where does Fermilab get its funding? Nearly 100% from the Office of High Energy Physics (OHEP) within the DOE’s Office of Science. Largest “single program” in the Office of Science FY2013 President’s Budget: • DOE $27.2B • Office of Science $5.0B • Office of High Energy Physics $776M • Fermilab $359M • Currently expecting $375M Mission Support Planning Workshop 2/20/2013
Fermilab 5-Year Funding by Source ($M) Mission Support Planning Workshop 2/20/2013
FY15 FY14 FY13 Mission Support Planning Workshop 2/20/2013
For more info . . . Mission Support Planning Workshop 2/20/2013
FY13 Financial Outlook – HEP • Continuing Resolution expires March 27, 2013 • All-year CR at FY12 levels is most likely scenario now • Science Lab Initiative infrastructure $2.5M (not HEP)on hold as “new start” • Sequestration may take effect March 1st . . . • . . . but will it endure, and if so, at what level? • No immediate effect on lab - will have 6 months of funding as of 2/28/13. • 5% exercise done by DOE - would be ~$18M cut if pro-rated across HEP • Significant concerns at funding level of $375M (down ~7.5% from FY12) • Accelerator R&D/SRF program is $4M short of Lab plan • NOvA Project cost review resulted in transfers to Lab > $3M to date • Squeezing to do first-phase CDF refurbishment for IARC program by deferring several GPP projects - ~$3M • Debt ceiling crisis has passed for now – expected to hit limit again ~August Mission Support Planning Workshop 2/20/2013
Cost of Doing Business – Indirect Costs • Indirect Costs are costs that cannot be directly identified with a single “final cost objective” • Fermilab’s “final cost objectives” are the DOE B&R categories • Most of us in this room, most of the time we’re working, are “indirect costs” • Indirect costs must be allocated in a consistent way based on the “causal-beneficial” relationship between the indirect cost and the activity it’s being charged to. • The most common method to do this is to pool similar indirect costs together, define a base of costs that will pay for each pool, and establish a rate to apply to the costs in the base that will allocate the pool. • Indirect cost allocation is governed by Cost Accounting Standards • Cost Accounting Standards is a provision in FRA’s contract with DOE • FRA is required submit a Cost Accounting Standards Disclosure Statement to DOE for approval any time the methodology for allocating indirect costs changes significantly. Mission Support Planning Workshop 2/20/2013
Cost of Doing Business – Indirect Costs (cont.) Mission Support Planning Workshop 2/20/2013
Indirect Costs by Organization FY08-FY13 Mission Support Planning Workshop 2/20/2013
Questions? Mission Support Planning Workshop 2/20/2013