390 likes | 545 Views
VERGNET S.A. INTEGRATION OF A WIND FARM INTO THE UTILITY GRID. Eric ANDRIEU, Electrical Design Department Manager Pierre PESNEL, Export Manager 18 – 20 October 2006. Thank you for welcoming us in Jamaica !. What will we talk about?. W ho is VERGNET today ? Our experience in the Caribbeans
E N D
VERGNET S.A. INTEGRATION OF A WIND FARM INTO THE UTILITY GRID Eric ANDRIEU, Electrical Design Department Manager Pierre PESNEL, Export Manager 18 – 20 October 2006
What will we talk about? • Who is VERGNET today ? • Our experience in the Caribbeans • Grid connection & Protection planof wind farms • Scada System
THE VERGNET GROUP • Created in 1989 • 100% private • 2 plants in France • More than 90% of turnover abroad • By history and culture, VERGNET’s focuses in cyclonic and isolated areas. • A new product range, the GEV MP (275 kW)
Vergnet in the Caribbean Guadeloupe : • 17 people, dedicated to O&M • 10 wind farms / 5 locations • > 20 MW • 50 GWh / year Martinique • 4 wind turbines • 1,1 MW
Vergnet in Guadeloupe • > 10 % of the island’s energy • Electric solutions with EDF • Maintenance « in the vicinity of the wind Farm »
Vergnet in the Pacific • New Caledonia : • 15 people, dedicated to O&M • 7 wind farms / 4 locations • More than 25 MW installed power • 50 GWh / year produced • Fidji Islands : • 1 wind farm under construction • Commissionning: Q1/2007 • 37 WTG, 10 MW, very cyclonic area • In the Pacific : • New projects in progress
The anti-cyclonic GEV MP – 275 kW Original technological solutions
GEV MP A light original architecture • 55 m or 60 m hub height • 26 to 32 m Two-Blades rotors • Pitch regulated • Teetering Hub • Down Wind • Guyed Tilting Tower • Very small foundations: • 15m3 concrete • anchored on micro-piles • Asynchronous generator, 2 speeds • Flexible, then earthquake resistant
Hurricane protection • The WTG can be tilted down into protection position. • Same position is used for assembly and maintenance.
Adapted Logistics • The GEV MP is lighter than other turbines of the same size • All parts fit in 20’ and 40’ containers • Installed with usual trucks and 25 tons cranes • Nacelle with blades: 8.7 tons Tower : 12 tons
Very light Civil Work • Per Wind Turbine : • 9 drillings, 6’’ diameter, for the anchorages • Approx 15 m3 concrete
Easy maintenance • Maintenance performed from the ground • Blade cleaning in the ground at each maintenance • No need for a special crane to change heavy components
Simple electrical works • Each WTG features a shelter, for • WTG control • LV/MV transformer • Cos Phi control • MV cables in trenches link the WTGs to the dist. substation • An optic fibber links all WTGs to the control room and the Scada
Respect the power quality of the grid - Respect the grid protection plan- Allow control and clear monitoring What is an efficient grid connection ? Grid Integration Analysis - To assess the impact of connecting the wind farm to the grid - To define the setting of the MV protection at the PCC
R = minimum network short-circuit resistance at the PCC - X = minimum short-circuit reactance at the PCC- Max permitted voltage fluctuation in steady state and switching operation- Max permitted frequency fluctuation- Max permitted flicker type 1 & 2 Preliminary datas • From Utility • From Turbine Manufacturer : DEWI report (Compliance with the IEC 61 400-21) Flicker, Active and Reactive Power, Harmonics, etc…
Step 1Check connection possibility at chosen location - Impact on grid Steady state voltage fluctuation - MV : +/- 7% - LV : + 6% / - 10% - Load flow analysisMax admitted current in the existing gridFrom those data, EDF : - Request grid adaptation - Gives budget offer
Step 2Detailed analysis- Transient Voltage FluctuationDrop voltage caused by the transformer connectionWhen the Wind farm produces P 0,2 and Q 0,2- Flicker in continuous operation (type 1) and switching operation (type 2) - Type 1: Pst = Plt = c(fi,v) x Sn/Scc - Type 2: Pst = f (N10, Kf, Sn, Scc) Plt = g (N120, Kf, Sn, Scc)
General electrical protection of the Wind farm Electrical fault in the wind farm Step 2Protection plan Wind farm protection Isetting < 0,8 I_earth _fault (safety condition)Isetting > 5 to 8 Ib (to avoid untimely tripping)Isetting >1,3 Im (to avoid untimely tripping) Isetting >1,2 I_short_circuit_tri_wtg(to avoid untimely tripping)
General electrical protection of the Wind farm Electrical fault on the public grid Step 2Protection plan Grid protection - To avoid islanding network (Umax-min, Fmax-min, Vo)- To avoid wind farm production in case of grid fault - via Vo for earth fault - via Umin for short circuit
Electrical DESIGN The conclusions of the grid integration analysis allow us to design the electrical part of the Wind farm : • MV substation • WTG parameters (PLC) • SCADA system
WTG parameters (PLC) Programming of the PLC to reduce type 2 flicker : Pst = f (N10, Kf, Sn, Scc) Plt = f (N120, Kf, Sn, Scc) Parameters set according to EDF requirements.
SCADA Supervisory Control And Data Acquisition • Adjustment of U max, P max, Q max at PCC to meet EDF requirements.
Communication Remote access SCADA Via the public phone line. The communication is based on remote access (Windows access Virtual Private Network) . The communication had been optimized to reduce the volume of data (25 kbyte/s is required) Dispatch permanent communication Via permanent radio communication or equivalent. Full duplex transmission of key data (metering – setting) : -P, Q, U, CB position