270 likes | 459 Views
Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT January 22, 2014. Outline. Learning objectives –why work plan? Top five reasons why a work plan is important What are the recent updates?
E N D
Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT January 22, 2014
Outline • Learning objectives –why work plan? • Top five reasons why a work plan is important • What are the recent updates? • Target date, signing first or second page, emergency contact, pre-construction & post construction activity, etc. • Work plan development (Process): preparation, review, revision & approval. • Practical exercise
Why is a work plan Important? • Because it is the law! he • 105 IAC 13-3-3 (b) (1): A work plan shall be submitted whether or not any facility relocations are required. • It is not a matter of opinion or an option, it is the LAW. • Utilities are obligated to submit their work plans to accommodate a highway improvement project.
Why is a work plan Important ? 2. Because it focuses on deliverables: • Target out of conflict date. • Pre-construction schedule. • Construction schedule. • Relocation drawing. • Cost estimate • Proof of property interest.
Why is a work plan Important? 3. Because it is a signed commitment/contract • A work plan is a signed commitment by a utility to accurately relocate its facilities on schedule. • Projects are let based on information obtained from utility work plans. • A utility may be held accountable, for utility related delay claims.
Why is a work plan Important 4. No Surprises during construction: • Work plan is a major tool to avoid surprises during construction. • The utility team shall demonstrate due diligence in reviewing & approving work plans. • Last chance before construction stage!
Why is a work plan Important? 5: Because we use the work plan as an input: • Utility risk management report. • Gantt chart. • Utility special provision. • Utility coordination certificate.
Preamble • 105 IAC-13-2-19: Work plan is defined as a plan of the utility to carry out facility relocation to accommodate an improvement project. • Use preliminary final project plan (Stage 3/90%). • Prepare and send letter Request Work Plan. • Use the most recent work plan template. Go to the INDOT website.
When is a work plan due? • Sixty (60) days for a minor project; and • One hundred twenty (120) days for a major project. • An additional thirty (30) days will be allowed to furnish the work plan if coordination is required with another utility or utilities. • If a work plan is not received on time: contact the authorized representative and notify the oversight agent.
Work plan revision • Non compatible work plans shall be returned to the utility immediately. • The utility shall submit a revised work plan within 30 days. • If the revised work plan is not compatible, the UC will prepare an alternate work plan. • The utility shall accept/make changes to the alternate plan within 30 days.
Section 3 & 4 • Property interest & Work in contract
Section 7, 8, & 9: Attachments $500,000.00 (Not Reimbursable)
Work Plan Review • Ensure each work plan is compatible with: • INDOT permit requirements • The project plans • The construction schedule • Other utility relocation work plans • Ensure the relocation scheme and cost for compensable work is reasonable
Work Plan Approval Letter • Relocation permit to occupy public right-of-way. • Notice to proceed with preconstruction activities. • In rare cases a notice to proceed with construction activities.
Work plan addendums: • Addendums can either be INDOT initiated or utility initiated. • A utility shall submit a revised work plan with a new cost estimate (if reimbursable). • The utility coordinator shall review the addendum; and send it to the approval of the oversight agent. • If an addendum is issued during construction, a copy shall be sent to the construction engineer.
Work Plan Addendum Letter • What is the change of work. • What is the cost. • Who is paying for it. • What is the impact on construction schedule. • Revise exhibits to executed agreements, if reimbursable.
Notice to Proceed • Does the work of the utility depend on the schedule(s) of other utilities? • Are all the parcels needed by the utility acquired, ROE obtained? • Is the right-of-way cleared from trees & other obstructions, staked? • Does the work of the utility depend on the INDOT contractor?
Questions? Questions?
Practical Exercise • Group exercise • Identify 3 or 4 items that need to be corrected.