1 / 15

Pre-Feasibility Study Cost Estimation Resources

Pre-Feasibility Study Cost Estimation Resources. ©2002 Dr. Bradley C. Paul. Pre-Feasibility Study. Order of Magnitude Estimates Determined which things would be considered Pre-Feasibility Study Determines whether there is enough promise to justify the effort required to move forward

saxon
Download Presentation

Pre-Feasibility Study Cost Estimation Resources

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pre-Feasibility Study Cost Estimation Resources ©2002 Dr. Bradley C. Paul

  2. Pre-Feasibility Study • Order of Magnitude Estimates Determined which things would be considered • Pre-Feasibility Study Determines whether there is enough promise to justify the effort required to move forward • Feasibility Study (generally 10-30% +/-) • Next Moves to Project Approval (5-10%)

  3. Pre-Feasibility Study • Pre-Feasibility Study • Requires that you have a concept for what going to build • Break project down into areas and tasks • Outby Haulage • Ventilation • Mine Workings • Costs of Components Done Separately • Need to include everything

  4. Methods of Getting Pre-Feasibility Cost Data • Clear List of What is Included to make sure all components are included • Begin to Find Manuals Available • EPRI Coal Mine Cost Model (about 1981) • Bureau of Mines Cost Estimating System (1984) • SERPA Cost Program (current) • Western Mine Cost Service

  5. Typical Cost Manual Approaches • Factored Cost Estimates • Use Curves that are a function of some over-all characteristic • Example US Bureau of Mines Cost Estimating System • Itemized Cost Estimates • Specify cubic yards of concrete • Apply a cost per cubic yard • Used by EPRI and Serpa

  6. Strengths and Weaknesses • Factored Cost Estimation Approach • Requires a lesser degree of engineering detail be worked out to run • all costs linked to a specific generally known parameter • Lets get closer to answer with less work • Itemized Cost Estimates • Structure is same as Feasibility Estimate • allows more transparent transition to Feasibility study estimates

  7. General Comments on Major Cost Estimation Resources • EPRI - Coal Mine Cost Model • Most cost model resources are for hard rock and industrial minerals - this one is coal • Model covers coal mining costs but is weak in ancillary facilities and some capital costs • Example - No capital cost capability for shaft or slope • Model linked to a computer program that has not been updated • 1981 software in the 21rst century looses a lot

  8. More EPRI Comments • 1980 and 1981 cost base • needs significant inflation indexing • will see later that knowing how much to index with what is important • doesn’t show which indices to use on what • Productivity Sensitive • crews and advances done with simulations current in 1980 • coal mine productivity has increased about 250% • are some productivity indices from BLS but not a common updating procedure

  9. SERPA • A Hardrock Package • A comprehensive mine cost package that has been maintained to fairly current status with costs • is private so seeing exactly what is in the package is not really possible • fairly current still means the driving routines run in DOS • cryptic key sequences and IO problems • suspect that costs are updated but engineering assumptions in code may not be

  10. SERPA • Has a lot of defaults built in • Has relatively simple categories of mine needs • May almost be able to run at at the fairly precise order of magnitude estimate stage • most manuals really can’t help you till get to prefeasibility • Ability to add details and replace defaults gives system power that extends up into pre-feasibility • weaknesses in showing details of output probably make use in feasibility stage really questionable

  11. Western Mine Cost Service • Collection of cost models and typical item prices • comes as articles over time • makes comprehensive approach at any one time questionable • may have to inflation index different parts of mine cost separately • very vulnerable to holes in needed costing • Hardrock manual that has some coal mining equipment items in it • can use on coal but comprehensive approach problem

  12. Western Mine Cost Service • Place where manual shines • identify a critical cost area and you want to get down to itemizing equipment or features and need costs • great alternative to fishing for vendors that will give you prices before your really shopping for equipment • event is likely to occur as Pre-feasibility study moves into true feasibility study • Manual caters all the way from Order of Magnitude to Feasibility but is comprehensive nowhere

  13. US Bureau of Mines Cost Estimating System • Prob the most comprehensive high precision pre-feasibility manual ever written • No holes - covers everything • Too much detail and work to function in Order of Magnitude Estimation • Factored cost estimate approach is not compatible with itemized detail needed in critical areas of Feasibility Study • Manual is clearly hardrock • not good for quarry’s either

  14. Status of BM CES • Mid 90s Congress killed Bureau of Mines • manual has been without caretaker • lots spin off people went to Western Mine Cost and Serpa came from BofM • Had beautiful spreadsheet program that ran manuals rapidly • was designed for Lotus 123 • not updated to latest spreadsheets and some macros don’t work

  15. Status of BM CES cont • Had automatic cost indexing but that’s not been maintained • fortunately same index structure was picked up by Western Mine Cost which has been maintained • getting recent indexing into spreadsheet model is an on your own • can do it manually as you will see

More Related