1. CASE STUDY Manufacturing Organization
Project Name: Wastage Reduction in Manufacturing process of XYZ Ltd
Process : Manufacturing
Green Belt : Mr ABC
2. DMAIC Steps
3. Define Phase-
• Project Charter
• Business Case
• SIPOC
• Voice of Customer (VOC)
• Critical To Quality (CTQ)
4. DMAIC Project Charter
5. Define the problem statement-Project charter Background/problem description: Current process wastage is very high as close to 20%hence process becomes sub-optimal and high resource is required to do inspection of final output.
Project objective/goal: High wastage leads to pressure on COGS. Hence it is essential to reduce the wastage to less than 10%.
Project deliverables: identify the reduce the High wastage leads to pressure on COGS.
6. BUSSINESS CASE AND IMPACT- • XYZ is the first product XYZ Ltd, India is exporting to US market
• This product is very critical as it is new product in the Kids range in US
• Based on success of this product J&J India can get other new products from
US and from other franchises like Neutrogena
• The process of pouching soap in to bi-layered tredegar film(aperatured
plastic film) is developed by XYZ Ltd India team
• Current process wastage is very high as close to 20% hence process becomes
sub-optimal and high resource is required to do inspection of final output
• Due to limitation in manual checking a rejected soap can go to the market
and can lead to serious market complaint
• High wastage leads to pressure on COGS
• Tredegar film contributes around 18% to total COGS
Hence it is essential to reduce the wastage to less than 10%
• Business Impact –
– USD 10101 or Rs. 505,050 PER ANNUM
7. High Level Improvement Timeline
8. SIPOC
9. .
10. .
11. voice of Customer by Kano Model
12. Analyze Phase- Multi-Vari Analysis
– Operator
– Shift
– Machine
Hypothesis testing using ANOVA
Cause & Effect diagram
– Improper sealing
– Uneven cutting
13. Analyze Phase- Multi-vari analysis out put.
– Shift is having slight impact on rejection. In the A
shift rejection is less which is mainly due to more
supervision.
– In case of operator unskilled operator showed high
amount of wastage
– Machine 3 & 4 showed less wastage, so concentrate
on machine no. 2
14. Identify the y to be improved-
Y= reduce the High wastage leads to pressure on COGS.
15. Fish Bone Diagram/Cause & Effect/Ishikawa Diagram
16. Cause & Effect analysis:-
17. .
18. Fish Bone Diagram/Cause & Effect/Ishikawa Diagram
19. .
20. . • Improper sealing and uneven cutting are two major
reasons for generating high amount of wastage.
• Out timing was noticed to be main cause of shifting
the position of soap in sealing and cutting station
• Group discussed to concentrate on reasons for out
timing
21. Cause & effect analysis-
22. . Innovative
Improvement-
• Solution prioritization matrix
• FMEA of defects
• Cost Benefit Analysis
23. Control Phase- Process capability & sigma
– Process yield improves from 61% to 88%
– Sigma improves from 1.9 to 2.7
• System modification
– Tredegar machine maintenance SOP revised to include
schedule for replacing soap feed conveyor links to quarterly
basis
– Suction system implemented for trim collection
• Key Learning's
– Use of PE methodology to systematically analyze the
process which gives opportunity for process improvements