1 / 17

LHC Access System – Status and Planning August 2006

LHC Access System – Status and Planning August 2006. Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC Access Project Team. LHC Access System. LHC Access Control System – LACS Supports the physical equipment regulating the access to the accelerator

sbreton
Download Presentation

LHC Access System – Status and Planning August 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC Access System – Status and PlanningAugust 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC Access Project Team

  2. LHC Access System • LHC Access Control System – LACS • Supports the physical equipment regulating the access to the accelerator • Allows operation of access equipment • LHC Access Safety System – LASS • Provides interlock between EIS-faisceau and EIS-acces • Ensures the collective protection of personnel from the radiation hazards

  3. LHC Access Control • 34 Access Points • 95 controlled sector doors • 65 interlocked end-of-zone doors • 26 interlocked ‘portes crionolines + ventilation’ • 17 interlocked movable shielding walls • 200 junction boxes • 170 racks • 110 surveillance cameras • 200 controllers (PLCs, PCs) • Control system from CCC and experiments • Supervision system

  4. LHC0: design validation

  5. Installation Status: sector doors and junction boxes • Sector doors: • Point 8: 90% • Point 7: 90% • Point 1: 75% • Junction Boxes: • Point 8: 100% • Point 7: 100% • Point 1: 100% • Point 6: 90%

  6. Access points - Underground • Installation of the access points in UX85, UJ83 and UJ87 in progress • Complete test of the access point UX85, including the IHM and control from the CCC, supervision and maintenance procedures -> mid September • Circulation of personnel not affected

  7. Installation Strategy – Underground Access Points • Not used for personnel passage before the definite closure of the area (installation of the grids) • Configured for biometric recognition and RFID badge identification

  8. Access for the Pits Head • Prerequisites: • Access points UX85, UJ83 and UJ87 integrated and validated • Access Help Desk manned and operational • User information: • Posters, group secretariats, TCC, bulletin • Constraints: minimize the impact on the personnel flow during the LHC installation period • Strategy: • Biometric recognition disabled • Use of the new CERN site access cards (equipped with MIFARE RFID chips) for the personal identification – Under validation • Current CERN site ACCESS magnetic cards is being progressively replaced by the new RF cards (TS/CSE responsibility) • Dosimeters not required during the LHC installation • Before LHC start-up, users shall be requested to get a dosimeter equipped with the RFID chips

  9. New CERN Site Access Cards:

  10. Persons working on the Points 7 and 8 will be asked to retrieve the new access cards at the Building 55 already in September • Access to the LHC interlocked areas in the LHC operation phase: personnel dosimeter equipped with the RFID chip and biometric identification

  11. Short term objectives Points 7 and 8: • PM85: • Dismantling of the existing system: beginning October (1 week) • Installation and integration of the new system (1 week) • Presence of the security guardian required during dismantling and installation • Operational mid October • PM76 operational end October • PZ85 operational beginning November

  12. Global Planning • Installation and Commissioning detail planning • Integrated within the LHC IC General plan (TS/IC) • EDMS 769853 • Machine and Experiments • Deployment: • P8, P7, P4 -> 2006 • P1: January 2007 • P5: February 2007 • P3: March 2007 • P6: April 2007 • P2: May 2006 • Final installation (inter-site doors, biometric identification, dosimeters with RFIDs, grids) June 2007 • Tests: • Site functional tests per site at the end of the site installation; in coordination with machine groups concerned • Global and Final tests • at the end of the installation during summer 2007 • special requirements (coordination with different groups concerned, access restricted to personnel involved in tests) • Follow-up with MTF

  13. Tests • Tests strategy defined all along the I&C phases till transfer to Operation and Maintenance • EMDS 497865 • HW, SW Functional and Safety (INB requirements !) • Tests Phases: • Local acceptance • Integration • Functional Site • Functional Inter-site • Global Tests and Final Tests • AB/DSO INB Tests • Roles and Responsibilities being defined with different groups concerned • project team, contractors, HC, equipment groups, experiments, AB

  14. LASS General Status • Safety software under development • Functional software (Man machine interfaces..) under development • Electrical design: power supplies, rack installation drawings, LASS command interface (Pupitre), cable loop – delays, but progressing well recently • Goal: follow-up with the installation the pace of the LACS installation in order to synchronize the testing

  15. Conclusions • Objectives: • LASS and LACS operational in LHC7, LHC8, CCC by mid November 2006 • All pieces of the ‘LEGO’ are there or under production • Planning relies on: • No major technical issues during integration • Contractors and subcontractors respect the deadlines

More Related