2012 – 2013 SIRPP Welcome 1 st Inter-Regional Stakeholder Meeting 9:00 AM – 10:00 AM CDT

2012 – 2013 SIRPP Welcome 1 st Inter-Regional Stakeholder Meeting 9:00 AM – 10:00 AM CDT. Purpose and Goals 2011 – 2012 SIRPP Process Economic Planning Studies Review Stakeholder Feedback on Process 2012 – 2013 SIRPP Process Projected Timeline Economic Planning Studies

seamus
Download Presentation

2012 – 2013 SIRPP Welcome 1 st Inter-Regional Stakeholder Meeting 9:00 AM – 10:00 AM CDT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2012 – 2013 SIRPP Welcome 1st Inter-Regional Stakeholder Meeting 9:00 AM – 10:00 AM CDT

  2. Purpose and Goals 2011 – 2012 SIRPP Process Economic Planning Studies Review Stakeholder Feedback on Process 2012 – 2013 SIRPP Process Projected Timeline Economic Planning Studies Next Meeting Activities

  3. 2011 – 2012 Final Economic Planning Study Results

  4. The Five Economic Planning Studies • SCE&G to Progress Energy Carolinas (200 MW) • Study Year: 2017 • Southern Company to Duke Energy Carolinas (50 MW) • Study Year: 2017 • SCRTP to FRCC (200 MW) • Study Year: 2017 • LG&E/KU to Southern Company (200 MW) • Study Year: 2013 • Southern Company to LG&E/KU (200 MW) • Study Year: 2013

  5. SCE&G to PEC Transmission System Impacts for the SIRPP • Three (3) 230 kV Lines • One (1) 230/115 kV XFMR • Five (5) 115 kV Lines Total Cost: $26,415,000

  6. SOCO to Duke Transmission System Impacts for the SIRPP • One (1) 230/115 kV XFMR • Four (4) 115 kV Lines Total Cost: $17,715,000

  7. SCRTP to FRCC Transmission System Impacts for the SIRPP • One (1) 500 kV Static-Var Compensator • Two (2) 230 kV Lines • One (1) 230/115 kV XFMR • Three (3) 115 kV Lines Total Cost: $122,815,000

  8. LG&E/KU to SOCO Transmission System Impacts for the SIRPP • None Reported Total Cost: $0

  9. SOCO to LG&E/KU Transmission System Impacts for the SIRPP • None Reported Total Cost: $0

  10. 2012 – 2013 SIRPP Process Timeline

  11. 2012 – 2013 SIRPP 1st Inter-Regional Stakeholder Meeting SIRPPSG selects up to five Economic Planning Studies October 22, 2012 Economic Planning Study Scoping Meeting Verify study assumptions and address stakeholder feedback on scope document November / December 2012, if necessary 2nd Inter-Regional Stakeholder Meeting Discuss preliminary study results April / May 2013 3rd Inter-Regional Stakeholder Meeting Discuss final study results July / August 2013

  12. 2012 – 2013 Economic Planning Studies 12

  13. Next Meetings Activities Economic Planning Study Scoping Meeting November / December 2012, if necessary Web / Phone Conference 2nd Inter-Regional Stakeholder Meeting April / May 2013 In Person w/ Web/Phone Conference Available

  14. Questions?