300. Powerpoint sequence of the construction of a traditional strip foundation Excavate trench Lay concrete foundation and leave to set Lay foundation blocks Lay brickwork to outer leaf upto dpc Lay blockwork inner leaf to dpc Backfill trench Lay dpc to both leaves
E N D
300 • Powerpoint sequence of the construction of a • traditional strip foundation • Excavate trench • Lay concrete foundation and leave to set • Lay foundation blocks • Lay brickwork to outer leaf upto dpc • Lay blockwork inner leaf to dpc • Backfill trench • Lay dpc to both leaves • Continue brick/block walls 900 (Note that the internal ground floor has been removed for ease of understanding. Also note that each brick is 65mm high BUT it has a 10mm mortar joint so each course is 75mm in total. The bricks and blocks are each 100mm wide with a 100mm wide cavity. The foundation blocks are 215mm high excl a 10mm mortar joint.) 225 150 600