2010 Fox Valley projects Doc Musekamp, Local Affairs. 2010 Substation construction and feeder work. Darboy Substation – Town of Harrison, CTH N, south of CTH KK - 34.5kV to 12kV substation built on existing company owned parcel - 25MVA transformer, 4 feeder exits
E N D
2010 Fox Valley projects Doc Musekamp, Local Affairs
2010 Substation construction and feeder work • Darboy Substation – Town of Harrison, CTH N, south of CTH KK - 34.5kV to 12kV substation built on existing company owned parcel - 25MVA transformer, 4 feeder exits - serves continuing residential growth and increasing commercial development in area - Enclosed, “cabinet” style construction minimizes overhead steel with shorter profile - Enhanced landscape plan at town request - Construction started - Complete by late fall, 2010
2010 Substation construction and feeder work • Pearl Street Substation – CTH G, City of Seymour - Retiring 2 existing 4kV substations - New 12kV substation will allow bridging to Seymour and eliminate electric “island” - Provides for future growth and enhanced reliability
2010 Fox Valley projects – Electric Cable replacements • Replacing aging underground cable on an annual, planned basis • 24 projects for 2010 – Grand Chute to Green Valley • Working with affected customers and communities to minimize impacts • Will improve reliability in these areas
2010 Fox Valley projects – Electric Facility Relocations • Appleton – Wisconsin Avenue, CTH JJ, S. Memorial Drive, Conkey Road • Neenah – Green Bay Rd / Winneconne Av. roundabout • Outagamie County – STH 47, Black Creek to Bonduel
2010 Fox Valley projects – Electric Forestry • Construction related – Seymour, Freedom/Center Valley areas – 58 miles • Reliability related – Greenville and west Appleton areas – 20 miles • Maintenance related – STH 47 - Black Creek to Bonduel, Various areas – 154 miles
2010 Fox Valley projects - Gas • Little Chute gate station – line heater -complete replacement of all mechanical equipment and systems • Facility relocations – Lake Street (Menasha), Larsen Road (Clayton), Maple and Main Streets (Black Creek) • Western district projects – from Green Lake to Rice Lake to Marshfield
2010 Fox Valley projects Taken together – the preceding represents an investment in excess of $ 10 million dollars in utility infrastructure for the Fox Valley area in 2010. This investment enhances gas and electric reliability and safety while providing the basic utility services necessary to support the continued economic vitality of our area.
2010 Fox Valley projects Questions ?
2010 Focus on Energy Update Randy Sabel Principal Account Manager
Focus Programs With Reduced Incentives • Custom Projects • Most Lighting • Air Compressor Equipped with VSD • Variable Frequency Drives • Energy Recovery Ventilators • New Construction whole building track incentive rate • Incentive Cap per Customer Tax ID
Focus Programs Removed • Compressed Air System Leak Survey and Repair • Heating and Cooling System Tune-up • Incentives for roof top units • Packaged Terminal A/C • 3-Phase Electric Motor Incentive • Feasibility Studies for Energy Efficiency and Renewable Energy • Customer Technologies– LED and Induction Technology (including traffic lights and street lights)
2010 Focus Update Questions ?