Joe Jachlewski-ME- Team Leader Aaron Bailey-ME Paul Kingsley-ME Brian Nealis-ME Matt Rose-ME

Multidisciplinary Engineering Senior Design Project 05307 Wind Solar Project 2005 Critical Design Review May 13, 2001. Joe Jachlewski-ME- Team Leader Aaron Bailey-ME Paul Kingsley-ME Brian Nealis-ME Matt Rose-ME Pam Snyder-ME Chris Wall-ME Customer: Dr. P. Venkataraman

Download Presentation

Joe Jachlewski-ME- Team Leader Aaron Bailey-ME Paul Kingsley-ME Brian Nealis-ME Matt Rose-ME

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Multidisciplinary Engineering Senior DesignProject 05307 Wind Solar Project2005 Critical Design ReviewMay 13, 2001 Joe Jachlewski-ME- Team Leader Aaron Bailey-ME Paul Kingsley-ME Brian Nealis-ME Matt Rose-ME Pam Snyder-ME Chris Wall-ME Customer: Dr. P. Venkataraman Mentor: Dr. E. Hensel Coordinator: Dr. W. Walter

  2. Project Background • Recent push for “green” power sources • NYSERDA Proposal • The long-term goal of this project is to create a marketable wind/solar hybrid power generation system that can be applied to outdoor lighting and other applications. 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  3. Mission Statement The mission of the 2004-2005 Wind Solar Team is to design and build a prototype of an outdoor lighting system that is powered solely by wind and solar energy. The team will test the prototype for a minimum of one week and evaluate the system performance. The prototype will be safe and easy to modify. 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  4. Desired Outcomes • Safe operation • Integration of wind turbine, solar panel, a light, an energy storage system, support structures, and signal processing equipment. • Ability for Turbine interchangeability for future testing 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  5. Key Requirements & Critical Parameters • Complete first design • Build first prototype • Test prototype for at least a week • Evaluate system performance • Provide recommendations for future designs • Power the light 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  6. Design Process Feasibility Assessment Project Definition Concept Development Analysis & Synthesis of Design Preliminary Prototype Design Build Prototype System Testing and Evaluation Future Recommendations 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  7. Concept Development 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  8. Concept Development 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  9. Feasibility Assessment Total power required for each concept Required size of the power generation system 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  10. Feasibility Assessment Concept C was selected for further design. 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  11. Synthesis of Design • Light Selection Color: Warm White Diameter: 4.80” Height: 4.76” Current: 76 mA Wattage:9.2 W Brightness: >43000 LUX Nominal Current: 20 mA Nominal Voltage: 3.0~3.6 V Manufactured by: Light Waves Concepts Par 38 120 LED 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  12. Design Point Synthesis Of Design Power Generation System Design Space *Based on a 20 Watt power requirement and a 15 % efficient turbine 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  13. Synthesis of Design • Solar Panel Selection Model #: BP SX 10 Maximum power: 10 W Warranted power: 9 W Voltage at maximum power: 16.8 V Open-circuit voltage: 21.0 V Current at maximum power: 0.59A Short-circuit current: 0.65 A 12 year Warranty for 90% output 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  14. Synthesis of Design • Wind Turbine Design • Savonius Turbine • 1.46 m2 swept area • Assuming 15 % efficiency, theoretical 13 Watt mechanical power production • Two-stage, gapless, constructed with 0º/90º woven E-glass and epoxy • PVC central shaft *A tubular rib was added to increase the stiffness of the top and bottom plates 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  15. Analysis of Turbine Deflection without supporting ribs Deflection with supporting ribs *Under gravitational loading 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  16. Voltage-RPM Calibration Current-Torque Calibration Synthesis of Design • Generator Selection and Calibration • Donated by team member • 40 VDC nominal *The motor was manufactured by Ametek, and is currently out of production, so motor specifications were not available from the manufacturer. 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  17. Energy storage Minnkota Sealed Lead Acid Dual Purpose Nominal Voltage: 12 Volts Capacity: 72 Ah (at 20 hr rate) Recommended charging voltage: 12.4 Volts Internal Resistance: 0.17 Ohms Supply power to the light for 3-5 days Electrical Conditioning 12VDC to 120VAC inverter (purchased) DC step up circuit DC voltage leveling charge pump was purchased for charging the SLA battery. Synthesis of Design 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  18. Wood Post 6”x6”x16’ Pressure treated lumber safety factor of 3.3 Stationary Shaft 2” Aluminum Rod Stock 6’ long safety factor of 4.60 = 47.17 MPa Analysis and Synthesis of Design Support Structures 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  19. Gears Stationary Shaft Chain Rotating Bearing Collar Generator Adaptor Stationary Shaft Mount Generator Mount Chain Tensioner Synthesis of Design • Drive Train • 1:1 Gear Ratio Selection • To maximize efficiency of the turbine 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  20. Final Design Installed April 27th and still operating • Insert video 100_0417 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  21. Testing and trouble shooting • What we observed • What changes were made • What we measured • Desired vs. Actual Outcomes • What we learned 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  22. What we observed… • The chain was loose and the gear offset was wobbly - the chain fell off the gear • The top and bottom plates on the turbine fractured and caused vibration problems • Bolts became loose due to the unanticipated vibrations • Power generation from the turbine was significantly lower than expected 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  23. What we changed… • Machined a new gear offset with tighter tolerances • Added a chain tensioner • Modified the turbine to minimize vibrations (with the help of the wind) • Added Locktite to all bolts and screws • Disconnected generator from charging system as a trouble shooting measure 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  24. What we measured… 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  25. Desired Outcomes • Actual Outcomes 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  26. Conclusions - What we learned… 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  27. Recommendations for Improvement • Generator should be optimized for lower speeds • Use DC LED array • Locking nuts should be used in the event of vibrations in high winds • Permanently seal the battery box and generator protective case. • Use a stiffer material for the turbine • Higher quality anemometer • Permanent weather proof data logger • System should be optimized for overall system efficiency, not just turbine efficiency 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  28. Opportunities for Future Research • Obtain values for the amount of sunlight incident on the ground • Illuminance map for the LED light source • Other turbine configurations should be tested. • Engineering Economics for changing to autonomous system • Predict the life of the system • Predict the year-round performance • Develop a comprehensive system model 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  29. For a Marketable Product… • Solar Panel and Turbine size need to be optimized based on cost, aesthetics, and size • Stronger, more durable materials should be used for the turbine • Power generation system incorporated into a permanent lighting structure • Design for Manufacture, Profitability, Maintenance and Performance • A final market must be selected • Environmental impact study 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  30. Team Accomplishments • Designed, developed and built a prototype • The prototype was installed 2 and a half weeks ago, which allowed ample time for debugging the systems and learning more about the systems. • Provided accurate documentation of recommendations for future development • Came in under budget and on time - we spent $1600 out of the available $3000. • Completed comprehensive background research that would be invaluable for future teams • Developed a design space representing the tradeoffs between turbine size and solar panel size 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  31. Acknowledgements • Dr. Hensel for his invaluable guidance and mentoring • Dr. Venkataraman for his initial concept and continued input throughout the project • Dave Hathaway and Steve Kosciol – Machining and Part ordering assistance • John Wellin – assistance with the DAQ system • Dave Harris and the rest of Facilities Management Services for their support throughout the installation process • Electrical help was provided by Dr. Wayne Walter, Dr. Daniel Phillips, and Dr. David Borkholder. • Joel Slavis from Light Waves Concept, Inc provided the LED arrays at a discount. 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  32. References • B. F. Blackwell, R. E. Sheldahl, and L.V. Feltz. “Wind Tunnel Performance Data for Two- and Three- Bucket Savonius Rotors.” Sandia Laboratories. SAND76-0131. (July 1977). 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  33. Questions 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  34. Torque for 1, 2 and 3 stage turbines 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  35. Budget= $3000 Epoxy: $140 per m2 Solar Panels: $5.40 per Watt Battery: $0.08 per Watt-Hour Cost Assessment 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  36. Power Production Vs. Consumption 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  37. Project Plan for SD2 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  38. Power available from the wind for various wind speeds and efficiencies. 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  39. Power Produced vs. Power Consumed 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05

  40. Post Anchoring • Strong but temporary • The base of the post is buried 3’ in a 1’ diameter hole, which is filled with cement. • Additional guy wires were anchored into 5 gallon buckets filled with cement and buried 1 foot deep • This provided restraints on the pole to ensure that it will not fall down. • After testing the cement segments can be dug up and the whole system can be relocated to the engineering test area 05703 – Wind-Solar Hybrid Project Critical Design Review 5/13/05