HU151: Industrial Safety

HU151: Industrial Safety. Pharos University in Alexandria Faculty of Engineering. Lecture 3: Risk Acceptance. Prof. Abdelsamie Moet Fall 2012/13. " Safety ". is the control of hazards to attain an. acceptable level of risk. Generic Risk Response Plan. Risk Acceptance.

shanae
Download Presentation

HU151: Industrial Safety

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HU151: Industrial Safety Pharos University in Alexandria Faculty of Engineering Lecture 3: Risk Acceptance Prof. Abdelsamie Moet Fall 2012/13

  2. "Safety" is the control of hazards to attain an acceptable level of risk HU151_Lect3_RiskAcceptance

  3. Generic Risk Response Plan HU151_Lect3_RiskAcceptance

  4. Risk Acceptance • “The systematic process by which relevantstakeholders agree that risk may be accepted.” HU151_Lect3_RiskAcceptance

  5. Approaches to Risk Acceptance • Active Acceptance • to establish a contingency reserve, including amounts of time, money, or resources to handle the threat. (Contingency Plan) • Passive Acceptance • Requires no action leaving the project team to deal with the threats as they occur. (Workaround) HU151_Lect3_RiskAcceptance

  6. Risk Acceptance Criteria • Risk Acceptance must be reviewed at appropriate management level (and the aggregated risk for the system). • Risk Acceptance may be justified only when there are positive answers the questions: • “Have we done all that is Reasonably Practicable to reduce the level of Risk?” • “Are they now Broadly Acceptable or Tolerable and As Low As Reasonably Practicable?” HU151_Lect3_RiskAcceptance

  7. The ALARP principle • No industrial activity is entirely free from risk and so many companies and regulators around the world require that safety risks are reduced to levels that are As Low As Reasonably Practicable, or "ALARP". • The "ALARP region" lies between unacceptably high and negligible risk levels. • Even if a level of risk for a "baseline case" has been judged to be in this ALARP region it is still necessary to consider introducing further risk reduction measures to drive the remaining, or "residual", risk downwards. • The ALARP level is reached when the cost of further reduction measures become unreasonably disproportionate to the additional risk reduction obtained. HU151_Lect3_RiskAcceptance

  8. ALARP HU151_Lect3_RiskAcceptance

  9. Risk Evaluation - ALARP TolerabilityPrinciples Intolerable Region Risks cannot be justified X ALARP Region Increasing Individual Risk and Societal Concerns $ X Level of residual risk is not regarded as significant and further effort to reduce risk is not likely to be required as the resources to reduce the risks are likely to be grossly disproportionate to the risk reduction achieved. Broadly Tolerable Region Negligible Risk Risk Level Control measures must be introduced for risk in this region to drive residual risk towards the broadly acceptable region. If the residual risk remains in this region, and society desires the benefit of this activity the residual risk is tolerable only if further risk reduction is impracticable or requires action that is grossly disproportionate in time, trouble and effort to the reduction in risk achieved.

  10. Risk Utility HU151_Lect3_RiskAcceptance

  11. Risk Utility Function HU151_Lect3_RiskAcceptance

  12. Optimized Value HU151_Lect3_RiskAcceptance

  13. HU151_Lect3_RiskAcceptance