70 likes | 78 Views
This update includes information on the building's Temporary Certificate of Occupancy, contract impacts under review, delays related to electrical permits, rain delays, operator strikes, wall sizing issues, and recovery plans.
E N D
Blakely Schedule Update May 30, 2019
Building Temporary Certificate of Occupancy (TCO) Commons Teacher Room Storage Deliveries • CONTRACT • July 15, 2019 • July 29, 2019
Contract ImpactsUnder Review • KPUD Fiber Line to Island Wood • Impacts civil, start of structural concrete • Electrical Permit Submission by ARUP • Delay related to the submission of the electrical permit, impacted electrical underground and structural concrete scopes • Rain delay’s – April 18 • Impacts concrete slab pour and structural steel erection • Structural Steel Dimensional Coordination items between FOMA and Mithun/PCS • Structural steel RFI’s relative to steel fab coordinated / complex steel coordination (earthquake fault line) • Impacts to production/flow for framing and electrical in multiple quads
Contract ImpactsUnder Review • Operators Strike • Impacts civil, structural steel erection, structural concrete • RFI 185 / Brace Frame Wall Reinforcing/Concrete reinforcing in Quad B • Impacts rebar supply/Install, structural concrete, steel erection, metal stud framing • Steel Joist Deflection/discrepancy between joist spec and framing specifications • Impacts framing & electrical in Quad C & Quad A. • Snow/Weather Delay February • Impacts all trades
Contract ImpactsUnder Review • Wall Size at Classroom Demising Wall/ Quad B • Wall sizing in architectural drawings proved to be too thin for original electrical/AV rough in/ routing at demising walls. Change order priced to increase wall size declined. Alternate solution created by design team: impacted electrical rough in, drywall hang/tape and paint • CCD-03 AV / Paging changes • Changes to meet District technology construction standard • Impacts to electrical, insulation, drywall hang/tape and paint • Ventilation Shaft Quad B & D / Duct Revisions @ Soffit Quad B • Conflicts between shaft sizing and mechanical vents. Transition from round to square vents in soffit • Impacts Mechanical, electrical, roofing, rough carpentry, frame, drywall hang/tape and paint through-out building • AV / Paging • Impacted electrical, insulation, drywall hang/tape & paint subs. • Ventilation / Shaft Issues Quad B/D & Post Shop Duct Design Revision for Aesthetics • Impacts mechanical, electrical, roofing, rough carpentry, roofing, frame, hang, tape & paint in Quad B
Work Plan- Recovery • Meeting June 7, 2019 :: Contractor: Architect: Capital Projects • Schedule analysis • Scope • Critical path delay • Overtime • Mitigation • Building Access (TCO) • August 27 August 13