SCIAMACHY 2nd Reprocessing Cycle Status SCIAVALIG, 21 June 2007

SCIAMACHY 2nd Reprocessing Cycle Status SCIAVALIG, 21 June 2007. Angelika Dehn, Thorsten Fehr, ESA (presented by Heinrich Bovensmann, SQWG). 2nd Reprocessing Cycle - Overview. Reprocessing Period Full mission: July 2002  Operational Switch of updated processors Processor Versions

sharer
Download Presentation

SCIAMACHY 2nd Reprocessing Cycle Status SCIAVALIG, 21 June 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SCIAMACHY 2nd Reprocessing Cycle Status SCIAVALIG, 21 June 2007 Angelika Dehn, Thorsten Fehr, ESA (presented by Heinrich Bovensmann, SQWG)

  2. 2nd Reprocessing Cycle - Overview • Reprocessing Period • Full mission: July 2002  Operational Switch of updated processors • Processor Versions • Level 1b: Version 6.03 • Level 2: Version 3.01 • Processing Sequence • Not a single SCIAMACHY L0Level 2 operational processor • Reprocessing separated • Level 1b will be initiated before Level 2 reprocessing • Level 2 is expected to “catch up” quickly • Possible δ-verification activities coordinated with the SQWG • Time for completion • Depends on • processing availabilities • impact of recent changes in the ESA Ground Segment • Expected to be significantly faster that the 1st reprocessing campaign

  3. 2nd Reprocessing Cycle - Level 1 • Configuration: • Level 1b IPF version 6.03 • Improvements see SQWG presentation • Production: D-PAC • Based on consolidated L0 data set • Reconsolidated dataset including corrective reprocessing (2002 – 2005 completed, 2006 reconsolidation ongoing) • AIX-IBM environment • Dissemination: • Standard dissemination via FTP • Other options will be considered on request

  4. 2nd Reprocessing Cycle - Level 1 Schedule • Level 1 Processor: • Prototype Verification successfully completed (SQWG) • Factory Acceptance Test successfully completed (ESA/SQWG) • On-Site Acceptance Test currently ongoing (ESA/SQWG) • Activation for forward processing in CW 28 (9-13 July 2007) • Start reprocessing planned for 2nd half of July 2007 • Time required for reprocessing: • Depends on processing availabilities and performance • New Ground Segment concept introduced • Consolidated estimate will be provided based on the first set of processed files

  5. 2nd Reprocessing Cycle - Level 2 • Configuration: • Level 2 OL version 3.01 • Improvements see SQWG presentation • Production: D-PAC • Based on consolidated Level 1 data set (IPF 6.03) from the reprocessing • LINUX Environment • Dissemination: • Standard dissemination via FTP

  6. 2nd Reprocessing Cycle - Level 2 Schedule • Schedule (in Coordination with SCIAMACHY QWG): • Level 2 • Verification completed end of June (SQWG) • Acceptance Test expected second week of July 2007 (ESA/SQWG) • Activation for forward processing End of July 2007 (ESA) • Start reprocessing Beginning of August (ESA) • Time required for reprocessing: • Depends on processing availabilities • Consolidated estimate will be provided based on the first set of processed files

  7. Outlook • SCIAMACHY QWG plans to provide a new processor baseline 1st quarter 2008 • Expected changes are significant • Justification for new reprocessing activity • Possible 3rd reprocessing campaign 2nd half 2008 • Coordination with QWG and SCIAVALIG • Level 1b IPF LINUX based