BEISEL ROAD. 8/10 mile . SCOPE. SURVEYING ENGINEERING WITH FOCUS ON ENVIRONMENTAL ISSUES AND IMPROVING DRAINAGE IMPROVED DRAINAGE WITH UNIFORMLY SIZED CONCRETE PIPE AND DEFINED DITCHES ROADBED FORTIFIED WITH CONCRETE BASE ASPHALT PAVING. IMPROVED DRAINAGE. FUNDING.
E N D
SCOPE SURVEYING ENGINEERING WITH FOCUS ON ENVIRONMENTAL ISSUES AND IMPROVING DRAINAGE IMPROVED DRAINAGE WITH UNIFORMLY SIZED CONCRETE PIPE AND DEFINED DITCHES ROADBED FORTIFIED WITH CONCRETE BASE ASPHALT PAVING
FUNDING • $85,000. – TITLE II FUNDS • $199,000. COUNTY TRANSPORTATION COMMITTEE (CTC) FUNDS • TOTAL PROJECT EXPENDITURES: $212,066.91
Road Marking • 4 inch double yellow line: $1,689.6 • Bi-directional raised pavement markers: $1,100. • Total amount requested: $2789.6