1 / 14

GLAST Large Area Telescope: Cost/Schedule Review November 3, 2004

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Cost/Schedule Review November 3, 2004 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6 David J. Thompson Thomas E. Johnson NASA Goddard Space Flight Center Subsystem Manager/Instrument Manager David.J.Thompson@nasa.gov

shawna
Download Presentation

GLAST Large Area Telescope: Cost/Schedule Review November 3, 2004

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Cost/Schedule Review November 3, 2004 AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6 David J. Thompson Thomas E. Johnson NASA Goddard Space Flight Center Subsystem Manager/Instrument Manager David.J.Thompson@nasa.gov Thomas.E.Johnson@nasa.gov

  2. Significant Accomplishments • Started flight PMT assembly. 16 units are completed, 10 are being coated, 20 additional units beginning assembly. • Completed vibration testing of the Spare/Qual Electronics Chassis. • Installed fiber ribbons on the flight structure. • Successfully completed all mechanical qualification testing of the new PMT mounting design. • Completed Spare/Qual Electronics Chassis functional testing. • Made preparations to go to EMI testing. • Received 36 new PMTs from Hamamatsu. • Completed the assembly and functional testing of all (4) single row Electronic Chassis (minus the PMTs)

  3. Recent Accomplishments - Electronic Component Status

  4. Fabrication, Assembly and Testing status Number needed in parenthesis STATUS KEY 6 Prototyped 130 Clear fiber cables (130) In Fabrication or Ordered 130 (All) Received In assembly 12 All 89 + spares All All 45 Assembled Tested ACD Assembly (1) Detector assemblies - TDA - (4 basic types, 89 needed total) 1 8 8 8 8 Tile Shell Assembly –TSA (1) 8 Fiber ribbon detectors (8) 8 360 360, All 1 1 Detector Flexures (366+20 spares) Base Electronics Assembly (BEA) From next page Composite Shell Assembly (1)

  5. Fabrication, Assembly and Testing status 1 1 1 1 1 1 1 1 1 1 Base Electronics Assembly (1) Electronics Chassis (8) (4 double + 4 single) Photomultiplier Tube rails (8 + 2 spares) – All in Power distribution board (8+2 spares) – All in Base Frame Assembly (1) – in and assembled Chassis and connector frames (8) – All in Connectors (32) – All in

  6. TSA I&T • Fiber Ribbon Installation Complete • Resolved issues with overall length (they were too long) and supporting the ribbons (they sagged) • All 25 TOP TDAs INSTALLED and GAPS MEASURED • Data Assessment Showed Some Vertical Gaps Too Large And Some Too Small • Large Gaps Affect ACD Performance • Small Gaps Could Lead To Tiles Interference During Vibration Environments • Mechanical, Science And Systems Teams Met And Agreed To A Plan For Accepting ‘Predicted’ Final Gaps • Reduced Minimum Allowable Gap From .035” To .024” • Allowed Largest Gaps at Outer Tile Locations • FINAL GAP PLAN ESTABLISHED • FINAL INSTALLATION OF TDAs IS UNDERWAY.

  7. I&T Flow 10/4 – 11/30 11/25 – 12/7 12/2 – 1/11 Qual Electronics Chassis Environmental Test 1st flight chassis Environmental Acceptance Test The remaining Seven Flight Chassis Environmental Acceptance tests 12/29/04 – 1/14/05 6/10 – 11/19 12/14 – 1/13 12/7 – 12/13 Assemble last 2 rows of TDAs & WSF (124-130, 224-230, 324-330, 424-430) onto TSA Initial TDA/TSA I&T in B7 Install & test 1st & 2nd flight Chassis onto ACD Install & test remaining six flight Chassis onto ACD 1/27/05 – 2/10/05 2/23/05 – 3/4/05 2/11/05 – 2/23/05 2/10/05 1/25/05 – 1/27/05 1/14/05 – 1/25/05 1/14/05 ACD Subsystem Efficiency Verification test (include rotate ACD 90 degree) Vibration Test EMI/EMC Test Pre- Environmental Review (PER) Install Thermal Blanket & MMS ACD Full Functional Test ACD Integration complete 4/12/05-4/19/05 (was 3/26/05 – 4/2/05) 3/4/05 –3/10/05 3/10/05 – 4/7/05 4/7/05 – 4/8/05 4/11/05 4/19/05 – 5/17/05 Mass Properties Pre-ship Review (PSR) Acoustic Test Thermal Balance/ Thermal-Vac Test Post-ship Checkout & Full Functional Test at SLAC ACD ship to SLAC

  8. Near Term Milestones

  9. Interdependencies • EGSE/G3 – Ongoing development with I&T and Electronics groups. • LAT team to arrive at Goddard tomorrow. • ICD, IDD, etc – Rich Bielawski is helping track a set of needed changes. • Another IDD (LAT-DS-00309) update has been sent to us for review. It is currently being reviewed by the mechanical team.

  10. Issues, Concerns, Documentation, & Qual Program • Issues • PMTs • EGSE/Electronics Chassis testing • Concerns • EGSE/Electronics Chassis testing • PMTs • Numerous “minor” technical issues causing schedule and cost concerns. • Documentation • Recent “upgrades” to the CM system have caused several issues. This comes at an especially bad time since we have an ISO audit on November 19. • Status of PR/PFRs • 88 PR’s Closed • 2 PFR’s Closed • 10 PR’s Open • 6 PFR’s Open (1 black, 3 yellow, 2 red)

  11. ACD Schedule Variances • 4.1.6 – ACD Subsystem (-$574K cum, -$176 current) • 4.1.6.1 – Management/Science/Systems (-$28K cum, -$10K current) – LOE tasks scheduled incorrectly in PMCS • 4.1.6.2 – Safety and Mission Assurance (-$37K cum, -$23K current) – LOE tasks scheduled incorrectly in PMCS • 4.1.6.3 - TSA Schedule Variances ($0K cum, $1K current) • 4.1.6.4 BEA Schedule Variances (-$239K cum, -$30K current) • All variance is due to the PMTs. • 4.1.6.7 ACD I&T (-$243K cum, -$114K current) • Technical issues have delayed progress. PMCS schedule has the ACD in TVAC this month. This will continue to get worse, unless rebaseline or CR action is taken. • 4.1.6.B GSE (-$23K cum, $0K current) • ($23K) – Shipping container work being pushed out to reduce manpower.

  12. ACD Cost Variances • 4.1.6 ACD (-$42K cum, $93K current period) • 4.1.6.1 ACD Project Management/Sys Eng/Science (+$213K cum, +$24K current period) • Science support lower than planned. This is one area that has been identified as needing additional support in the form of a Grad student. • 4.1.6.2 Safety and Mission Assurance (-$81K cum, -$69K current period) • (-$44K) - Materials support on the PMT anomaly was assessed to 4.1.6.2 instead of 4.1.6.4 • 4.1.6.3 Tile Shell Assembly (-$122K cum, -$70K current period) • (-$76K) - Design and analysis manpower • (-$46K) - Fabrication charge backs higher than planned

  13. ACD Cost Variances • 4.1.6.4 Base Electronics Assembly (-$92K cum, $197K current month) • CCB action corrected majority of cost variance this month • (-$44K) - SLAC ASIC charges. • 4.1.6.5 MS/TB (+$35K cum, +$5K current month) • 4.1.6.6 ACD Mech Qual and Cal Unit (-$33K cum, -$2K current month) • 4.1.6.7 I&T (-$66K cum, -$17K current month) • Have not received credit for the amount of work done. • 4.1.6.B Ground Support Equipment (+$104K cum, +$25K current month) • (+$38K) – Labor. Costs lagging on mechanical design and EGSE support. • (+$66K) – Materials. Not billed for work completed

  14. Threats to Schedule and Cost • GASU/G3 EGSE • PMT Assembly • Electronics assembly and test • Minor Technical Issues that require manpower and time to resolve.

More Related