An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost of Compliance/Design and Implementation Geoff Rabinowitz Alpha Environmental Management Corp 407-365-5598 www.alphaemc.com

  2. You pay for everything in either…. • Time • Effort • Money • Emotion

  3. Cost of Designing a SWPPP/Sediment and Erosion Control Plan • Direct SWPPP Cost: $500-$XXXX • Field Analysis • Geo-tech Work • Preconstruction meeting • The focus should not be on the least expensive SWPPP but rather the most effective planning approach

  4. Implementation • Silt Fence: $0.75/LF • Reinforced Silt Fence: $1.50 LF • Seeding: $.025 - $.15 sq ft. • Sweeping: $50-150/Hour • Floc Log Dewatering Treatment: $? • Grading: $65+/Hour • Proper Planning: Priceless

  5. Maintenance Cost • Possible Activities: • Repair: Silt Fence • Cleaning: Inlet protection • Replacing: Erosion Control Blanket • Refreshing: Gravel at construction entrance • Need to ask how many times will BMP need to be replaced during the life of the project.

  6. BMP Removal • What gets installed must be removed. • Silt Fence • Inlet Protection • Gravel • Concrete washout

  7. Enforcement • Local: Varies • Regional: Varies • State: Up to $10,000 PDPV • Federal: Up to $37,500 PDPV

  8. Enforcement Continued State of Florida: • $500-$10,000 Per Day Per Violation • Each violation can be distinct • Penalties based on a matrix (generally) of “Extent of Deviation From the Law” and “Potential for Environmental Harm” • Plus many adjustment factors • Potential Criminal Charges for some violations

  9. Other Costs • Clean-up • New Rules / Requirements • Failure • Doing Nothing