Mini-Thermosyphon CP Test

Mini-Thermosyphon CP Test. J. Direito (EN/CV/DC). Objectives. Validation of the Thermosyphon concept in a small scale test (low cost). Study the behavior of system during Start up/operation/shut down (data acquisition) Gain experience during operation of this small scale test.

shen
Download Presentation

Mini-Thermosyphon CP Test

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mini-Thermosyphon CP Test J. Direito (EN/CV/DC) 2ndThermosyphon Workshop, CERN

  2. Objectives • Validation of the Thermosyphon concept in a small scale test (low cost). • Study the behavior of system during Start up/operation/shut down (data acquisition) • Gain experience during operation of this small scale test. 2nd Thermosyphon Workshop, CERN

  3. Thermodynamic Cycle • Available Height of 13m => max dP of 1.9 bar 2nd Thermosyphon Workshop, CERN

  4. Layout at B-191 Condenser Chiller Dummy Load 2nd Thermosyphon Workshop, CERN

  5. P&I ~15m 2nd Thermosyphon Workshop, CERN

  6. Part List(1st estimation) 2nd Thermosyphon Workshop, CERN

  7. Advancement Status • Quotations received and DAI’s lunched • Installation of pipes in Building 191 in 2-3 weeks • Installation of components in 3-4 weeks • Control system is being prepared • First results in 6 to 8 weeks 2nd Thermosyphon Workshop, CERN