WG TDC2/TCC2 Lessons learned from BA1. 10-09-2013 JL- GRENARD EN-HE. Removal of SPS DUMP. Time for the operation as estimated -> ~20min Less radioactive element handle first Position of the operators well optimized-> behind the shielding of the tractor
E N D
WG TDC2/TCC2Lessons learned from BA1 10-09-2013 JL- GRENARD EN-HE
Removal of SPS DUMP • Time for the operation as estimated -> ~20min • Less radioactive element handle first • Position of the operators well optimized-> behind the shielding of the tractor • Installation of marks for quicker positioning
Removal of SPS DUMP • Installation of cameras for some checks
Removal of SPS DUMP • Shielding of the Volk tractor
Removal of SPS DUMP • Failure tests of the Loehr trailer
Removal of SPS DUMP • All operations supervised with cameras-> follow up of operations by experts
To be still optimized • Conical head for positioning the trailer underneath the element to be optimized • Additional marks to be installed on the trailer
Removal of warm magnet • Same procedure as for the dump -> training in a mock up -> optimization of the tasks -> additional tooling Still some improvements to be done