An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of the GIF++ Project GIF++ will be an irradiation facility at CERN combining a particle test beam with a strong gamma source in the SPS experimental area http://cern.ch/WP7/Documents/20080919_Specs_GIF++_V2.pdf M.Capeans

  2. GIF++ Specifications SPS West Area Particle beam: muon beam (~ 104 particles per spill traversing an area of 10 cm x 10 cm) with option of an electron beam. Beam momentum ~ 100 GeV Source: 137Cs (662 keV) ~10TBq; 2 Gy/h at 50 cm Photon rate attenuation in steps and up to 5 orders of magnitude Uniform Irradiation area: M.Capeans

  3. GIF++ Infrastructure Peripheral infrastructure to condition the areas surrounding and feeding into the irradiation areas and user set-ups (gas, cooling, cable trays, barracks, etc) and auxiliary infrastructure outside the irradiation area such as preparation and storage areas to minimize set-up times, and the space needed for users to follow up the tests Minimal infrastructure provided to users inside the irradiation area (dose rate monitoring, beam, environmental data, etc) GIF++ common control, safety and log systems M.Capeans

  4. GIF++ document: shopping list It’s crucial for RD51 to give feedback asap to contribute on the facility design. Gas supply is just an example!

  5. GIF++ Timescale June 08 – April 09 Design May 09 – Dec 09 Construction & Procurement • Collection of User Requirements • Proposals by AB • Approval of Final Technical Description Jan 10 – May 10 Commissioning May 10 Ready RD51 can contribute to the infrastructure and set up an area in the GIF++ for the use of the collaboration M.Capeans

  6. The current GIF For time request, please contact Richard.Fortin@cern.ch • Most gas detectors installed in LHC have been validated at the GIF (CMS-RPC; CMS-RPC-RB; CMS-RPC-RE; LHCb-MWPC; COMPASS; ATLAS-MDT; ATLAS-RPC; ATLAS TGC; ATLAS-CSC; ATLsMDT; ATLAS-MDT (Magnet); Alice TOF; Alice-AMS; Alice CPC; ALICE-RPC; RPC_gas_filtering) • Running facility in B.190, till end of 2009 • Source: 137Cs 574 GBq, dose ~48 mSv/h @ 1m • No particle beam since end 2004 • Uniform irradiation: 600 cm x 400 cm x 360 cm (height) M.Capeans