640 likes | 859 Views
PMP/CAPM Prep Workshop Time. Course Objectives. The class will Prepare you to take the PMP Exam Cover the required classroom training hours The class will not Make you an expert on Project Management Make you an expert Project Manager Serve as your only reference for the exam.
E N D
PMP/CAPM Prep WorkshopTime PMP/CAPM Prep Workshop
Course Objectives • The class will • Prepare you to take the PMP Exam • Cover the required classroom training hours • The class will not • Make you an expert on Project Management • Make you an expert Project Manager • Serve as your only reference for the exam PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Tonight’s TopicProject Time Management • Reference Material • Chapter 6 PMBOK 5th Edition • Chapter 6 PMP Exam Prep 8th Edition PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Scope Baseline • The approved project scope statement and its associated WBS and WBS dictionary form the scope baseline. • Performance in meeting project scope goals is based on the scope baseline. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
WBS in Chart and Tabular Form PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Work Packages A work package is a task at the lowest level of the WBS. It represents the level of work that the project manager monitors and controls. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Work Packages • You can think of work packages in terms of accountability and reporting. • If a project has a relatively short time frame and requires weekly progress reports, a work package might represent work completed in one week or less. • If a project has a very long time frame and requires quarterly progress reports, a work package might represent work completed in one month or more. • A work package might also be the procurement of a specific product or products, such as an item purchased from an outside source. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Time Management Definition Time Management includes the processes required to accomplish timely completion of the project. The Project Time Management process includes the following • Define Activities • Sequence Activities • Estimate Activity Resources • Estimate Activity Duration • Develop Schedule • Control Schedule PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Table 3-1. Project Management Process Groups and Knowledge Area Mapping PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
General Information • Mostly Used in the Planning Effort • The main documents produced • activity list and attributes • a milestone list • a network diagram • the activity resource requirements • the activity duration estimates • a project schedule • Don’t Think About Software PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Schedule Management Plan • Schedule management baseline to measure against • Identification of performance measure • Decide how schedule variance will be managed. • Identification of schedule change control procedures. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Definition Ensure that project team members have a complete understanding of all the work they must do as part of the project scope so that they can start scheduling the work. . PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Goal • Take the Work Packages developed in the WBS and break them down further (decompose) in order to reach the activity level. • Activity: A level small enough to estimate, schedule, monitor, and manage. • Get the activities ready to be sequenced. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Def Summary and Tips • Don’t take Activity Definition Lightly • Remember the main outputs: Activity List, Activity Attributes, Milestone List, and Requested Changes • Rolling wave planning • Remember that activity definition comes after the WBS is developed PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Sequencing PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Sequencing Definition Identifying and documenting dependencies among schedule activities. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Goal • Take the activities and sequence them into how the work will be performed • Develop a Network Diagram which shows just dependencies PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Sequencing • Keys to activity sequencing • What is the sequence? • Identify all dependencies • Sequencing can be performed with software • For the test forget about software PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Types of Dependencies • Mandatory Dependencies (hard logic) • Inherent in the nature of the work being done • Discretionary Dependency (preferred or soft logic) • Based on experience, desire, or preferences • External Dependency • Based on the needs and desires of parties outside of the project PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Network Diagrams • Network Diagrams in the pure form show just dependencies • Sometimes referred to as Network Logic Diagrams • Shows how tasks will flow from the Start to the End of a Project PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
How to Construct Network Diagrams • In the Activity On Arrow(AOA) approach, or the arrow diagramming method (ADM), activities are represented by arrows and connected at points called nodes to illustrate the sequence of activities • only show finish-to-start dependencies (most common type of dependency). PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
How to Construct Network Diagrams • Activity On Node(AON) or the precedence diagramming method (PDM) is a network diagramming technique in which boxes represent activities. • These are more widely used as they can show all dependency types. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity on Node – Precedence Diagramming Method • Boxes represent tasks and arrows show dependencies • Task C can’t start before task B and D finish • Dummies not allowed Task B Task C Task A End Start Start Task F Task E Task D PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Types of Relationships in PDM PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Sequencing – Key Terms • Milestones – significant events in a project schedule • Leads – start an activity before the predecessor activity is completed (code before design complete) • Lag – inserted waiting time between activities (waiting for paint to dry) • Requested Changes - network diagrams sometimes expose requested changes • Graphical Evaluation and Review Technique (GERT) – a network diagram drawing method that allows loops – (design and test) PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Estimate Activity Resources PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Resource Estimation Definition GOAL: Estimating the type and quantities of resource required to perform each schedule activity PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Resource Estimating • Resources are people, equipment, materials • Resources must be planned and coordinated to avoid resources being assigned to other work • Consider developing a Resource Breakdown Structure (RBS) – hierarchical structure of the identified resources by resource category • Crashing and fast-tracking which we will cover later PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Estimate Activity Durations PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Duration Estimation Definition Estimating the number of work periods that will be needed to complete individual schedule activities PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Goal Once the type and quantity of resources needs are determined, the amount of work effort to complete the schedule activity needs to be estimated. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Duration Estimating • One-Time Estimate • Analogous Estimate • Parametric Estimation • Regression Estimation • Learning Curve • Heuristics • Three-Point Estimates • Reserve Analysis • Always have the people doing the work provide the estimates. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Activity Duration Guidelines • Evaluate one activity at a time • Assume “Normal” level of labor and equipment • Assume “Normal” work week • Disregard contract completion date on first cut PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Develop Schedule PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Schedule Development Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Goal Project schedule development is an iterative process that determines planned start and finish dates for project activities. PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
What do you need to develop a Schedule ? • An understanding of the work required on the project (Project Scope Statement) • Defined Activities (WBS, WBS Dictionary, and Activity List • The Order of How the Work will be done (Sequence Activities) • An Estimate of the Resources Needed (Estimate Activity Resources) • An Estimate of the Duration of Each Activity (Estimate Activity Duration) PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Other important facts • Things to Remember • Work with Stakeholders Priorities • Look for Alternative ways to Complete the Work • Look for Impacts on Other Projects • Meet with Managers to Negotiate Resources • Give the Team a Chance to Approve the Final Schedule • Compress the Schedule (Crashing and Fast Tracking) PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Schedule Network Analysis • PERT • Critical Path Method • Schedule Compression • What-If Scenario Analysis • Resource Leveling PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
PERT Memorize the Formulas PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Critical Path Method (CPM) • Determines the longest pathin the Network Diagram • Determines the earliest and latest an activity can start and the latest it can be completed • Method requires an understanding of • Critical Path • Near Critical Path • Float or Slack PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Critical Path • Helps prove how long the project will take • Helps the Project Manager determine where best to focustheir Project Management efforts • Helps determine if an issueneeds immediate attention • Provides a vehicle to compress the scheduleduring project planning and whenever there are changes • Provides a vehicle to determine which activitieshave float and can therefore be delayed without delaying the project PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Near Critical Path • The path close in duration to the critical path • Something that shortens the Critical Path could Lengthen the Near Critical Path and actually change the Near Critical Path to the Critical Path • Manage to both the Critical Path and the Near Critical Path to ensure the project isn’t delayed PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Float or Slack • Must be able to calculate it manually • Total Float – amount of time an activity can be Delayed without delaying the project • Free Float – amount of time an activity can be Delayed without delaying the early start date of a successor • Project Float – amount of time a project can be delayed without delaying the externally imposed deadline committed to by the Project Sponsor PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Float is an asset • Extremely Useful • Allows you to focus your management on the project • Helps team members juggle multiple projects and priorities PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Using CPM • You Must Determine the Earliest and Latest an activity can start and the latest each activity can be finished • Remember the formula for Float or Slack: • LS – ES • LF – EF • Early figures found by calculating from the Beginning to End – Forward Pass • Late figures found by calculating from the End to the Beginning - Backward Pass PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Drawing a Network using CPM • Draw the node and insert boxes in each corner as shown below: Duration ES EF Float LS LF PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Forward Pass • First Node in a Network Diagram has an Early start of 0 • Work through the Network Diagram and the Critical Path from Start Until End PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
More on Critical Path • There can be more than one critical path • Multiple critical paths increase risk • Critical Path can change • Should have Zero Float PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.
Schedule Compression • Done during planning or Integrated Change Control • Is desired completion date attainable? • Helps define impacts to Time, Cost, Scope, and Risk • Compress the schedule without changing Scope • Techniques • Fast Tracking • Crashing PMP/CAPM Prep Workshop Contains Confidential information which may not be disclosed with out express written authorization from PMI-CIC.