1 / 31

Critical Chain Management - Reducing Depot Maintenance Flow Days

Critical Chain Management - Reducing Depot Maintenance Flow Days. Scott R. Schultz Mercer University / Mercer Engineering Research Center. About the Author. Dr. Scott Schultz – assistant professor Mercer University, and consultant at Mercer Engineering Research Center. Industry Experience:

Download Presentation

Critical Chain Management - Reducing Depot Maintenance Flow Days

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Critical Chain Management - Reducing Depot MaintenanceFlow Days Scott R. Schultz Mercer University / Mercer Engineering Research Center

  2. About the Author • Dr. Scott Schultz – assistant professor Mercer University, and consultant at Mercer Engineering Research Center. • Industry Experience: • 13 years automotive experience – Ford Motor Company. • 2 years furniture experience – Furniture Manufacturing Management center. • Consulting – manufacturing and military • Teaching Experience: • 6 years as Industrial Engineer prof. at Mercer • Simulation • Production, scheduling, inventory control • Operations Research • others…

  3. Abstract In this short course we describe and discuss the concept of critical chain management. Critical chain management was originated by Eliyahu M. Goldratt as an outgrowth of his Theory of Constraints with respect to project management. Critical chain management explores why projects tend to be late, and develops an interesting approach to mitigating this problem. Now what does project management have to do with depot maintenance? Depot maintenance is not so much manufacturing, but is really more like project management. We then link the concepts of critical chain management to depot maintenance and how critical chain management can influence one of the depot’s primary measurables, “flow days”.…

  4. Why This Talk? • Critical Chain Management: • Applies to anyone involved in project management. • Applies to Depot Maintenance.

  5. Project Management - PERT/CPM Classical methods of analyzing projects – PERT/CPM CPM – Critical Path Method: addresses the tradeoff of the increased cost to reduce the time to complete a task, versus the cost reduction of completing the project as a whole. PERT – Program Evaluation and Review Technique: deals with project uncertainty by using the mean and standard deviation of individual task times to determine the probability of completing the overall project within certain time ranges.

  6. Project Management - PERT/CPM PERT/CPM – both methods require knowledge of the critical path. J,2 H,5 7 M,5 D,12 K,8 A,5 B,8 C,15 G,11 0 E,10 11 1 2 3 4 5 6 9 10 0 L,14 N,5 F,8 I,4 8 Critical Path – the longest path through the precedence network diagram. Precedence Diagram – graphically describes which tasks must complete before others begin, and which tasks can be performed in parallel.

  7. Critical Chain Management • Developed by Eliyaha M. Goldratt – 1997 • An application of his Theory of Constraints as applied to project management. • First major work on project management since PERT/CPM. • Goldratt References: • The Goal, a process of ongoing improvement, 1984 • Theory of Constraints, 1990 • Critical Chain, 1997

  8. Theory of Constraints (TOC) Overall Idea – The goal of a company is to make money. The theory of constraints is a methodology to help identify what might be hindering a company from obtaining its goal, and how to achieve the goal. The Goal is a fictional account of a manufacturing plant which significantly improves its production capacity (and other measures) through the application of TOC.

  9. Theory of Constraints (TOC) Identify the system’s constraint/bottleneck Exploit the constraint (squeeze the maximum capacity out of it without altering capacity capability) Subordinate everything else, don’t put improvement efforts into non-constraints, focus on bottleneck Elevate if still needing more throughput (add more capacity to constraint) Go back to Identify, (continuous improvement)

  10. Back to Critical Chain Production World – production throughput is like a chain. Production flows from one operation to the next. Op 10 Op 20 Op 30 Op 40 • A chain is only as strong as its weakest link • The weakest link is the bottleneck operation • No value in improving other links of the chain (e.g. Subordinate everything else)

  11. Chain Physics • If chained machines all working at full capacity, and capacity is equivalent on each machine, and if there exists any variance in production, the chain will never produce at capacity. • The greater the variance, the less the production. • The longer the chain, the less production. Op 10 Op 20 Op 30 Op 40 • Manufacturing managers/engineers attempt to mitigate the chaining effects

  12. Critical Chain and Project Management • Current State of Project Management World – • Only way to protect the whole (project) is through protecting the completion date of each step. • Therefore, we pad each step with safety time. • We then suffer from three mechanisms, when combined, waste most of the safety time. • Student syndrome (start as late as possible) • Multi-tasking (switching between tasks without completing) • Delays accumulate, advances do not • Thus, projects tend to complete late.

  13. Critical Chain and Project Management • Why Current State of Project Management? • Cause and Effect: • Wrong measurement, each task’s (or manager’s) performance is measured to their specific task. • No incentive to finish early since re-budget of time/dollars based on “last time” will result. • A delay in one step is passed to the next, while an advance in one step is usually wasted before the next.

  14. Critical Chain and Project Management Project Management World – so what is the bottleneck operation in project management? Ans. – the critical path. J,2 H,5 7 M,5 D,12 K,8 A,5 B,8 C,15 G,11 0 E,10 11 1 2 3 4 5 6 9 10 0 L,14 N,5 F,8 I,4 8

  15. Critical Chain and Project Management • Thus, TOC applies to project management where: • The bottleneck/weakest link of the chain is the critical path. Identifythe critical path Exploit Subordinate Elevate Go back to Identify,

  16. Critical Chain andProject Management • Thus, TOC applies to project management where: • The bottleneck/weakest link of the chain is the critical path. Identify the critical path Exploit the constraint – ensure the critical path is never compromised Subordinate Elevate Go back to Identify,

  17. Critical Chain and Project Management How do you Exploit the constraint? One way in manufacturing: Ensure the bottleneck operation is never idle by maintaining inventory in front of it. Bottleneck Operation X Inventory

  18. Critical Chain and Project Management How do you Exploit the constraint? On the critical path: Original: With all safety moved to end of project: Step 1 Step 2 Step 3 Step 4 Step 1 Step 2 Step 3 Step 4 Safety Buffer Note, only 50% chance of finishing each task on time, Management must change way of thinking, i.e. OK to be late some times.

  19. Critical Chain and Project Management • Thus, TOC applies to project management where: • The bottleneck/weakest link of the chain is the critical path. Identify the critical path Exploit the constraint – ensure the critical path is never compromised Subordinate – everything else Elevate Go back to Identify,

  20. Critical Chain and Project Management How do you Subordinate everything else? To the critical path: Restate task times for non-critical steps, removing safety time and starting them such that safety is at the end. Step a1 Step a2 Feeding Buffer Step 1 Step 2 Step 3 Step 4 Safety Buffer Step b1 Step b2 Step b3 Feeding Buffer

  21. Critical Chain and Project Management Impact of new way of approaching project management - Step a1 Step a2 Feeding Buffer Step 1 Step 2 Step 3 Step 4 Safety Buffer Step b1 Step b2 Step b3 Feeding Buffer • Need new performance measures – • Performance of critical path (e.g. % completion of c.p.) • Measure provided by person working on current critical path task, estimating number of days until finished • also monitor remaining days in feeder buffers (modify buffers as actual times realized in preceding steps) • Use relative buffer consumption to synchronize priorities and make early course corrections.

  22. Critical Chain and Project Management • Thus, TOC applies to project management where: • The bottleneck/weakest link of the chain is the critical path. Identify the critical path Exploit the constraint – ensure the critical path is never compromised Subordinate everything else, Elevatereduce task times, Go back to Identify,

  23. Critical Chain and Project Management How do you reduce task times? • Training • Improved methods / technology • Improved designs • Motivate employees • Provide incentives – reward early completion, penalize being late • Others?

  24. Critical Chain and Project Management • Thus, TOC applies to project management where: • The bottleneck/weakest link of the chain is the critical path. Identify the critical path Exploit the constraint – ensure the critical path is never compromised Subordinate everything else, Elevate reduce task times, Go back to Identify, are there other constraints?

  25. Critical Chain and Project Management Is the critical path the only constraint? - X Feeding Buffer X Feeding Buffer X Safety Buffer Critical path X Feeding Buffer Resource X in this case could cause all or some feeding buffers to become exhausted, would this cause all paths to become critical? Hopefully not, must be a better way to manage.

  26. Critical Chain and Project Management Call the resource constraint a critical chain? - Critical chain X Feeding Buffer X Feeding Buffer X Safety Buffer Critical path X Feeding Buffer This critical chain could be a longer path than the original critical path.

  27. Critical Chain and Project Management Feeding buffers have moved before critical path - Critical chain Feeding Buffer X Feeding Buffer X X Feeding Buffer Safety Buffer Critical path Feeding Buffer X Still a problem for X, top two feeding buffers have X scheduled at the same time. What to do?

  28. Critical Chain and Project Management Feeding buffers have moved before critical path - Critical chain Feeding Buffer X Feeding Buffer X X Feeding Buffer Safety Buffer Critical path Feeding Buffer X

  29. Depot Maintenance • An outsiders view: • Depot Maintenance – Is it manufacturing or is it project management? Each aircraft is viewed as a project. • Flow days – a key depot performance measure • Variability of Process Time – • a goal of manufacturing is to eliminate variability • the nature of depot maintenance is to manage variability • Critical Chain Management – uniquely positioned to manage variability and help reduce flow days.

  30. Depot Maintenance • An insiders view: • There is inherent variability in repair work making it difficult to follow schedules. • There is competition for mechanics, support resources, facilities, and other equipment within and across aircrafts – work waits in queue. • Unpredictable / over and above work cause schedule delays • Parts shortages cause delays. Some parts have long lead times. • Frequent priority changes forces workarounds and constant shifting of resources (Multi-tasking) • Administrative delays (inspection reports, customer approval, etc.) • Carry over work from one area disrupts progress in subsequent areas. • Operations checks and testing can result in rework that cause schedule disruptions late in the project.

  31. Conclusions • Critical Chain Management - explores why projects tend to • be late, and develops an interesting approach to mitigating • this problem. • Move safety to end of project and to feeding buffers • Manage feeding buffers • Remove multi-tasking • Depot Maintenance – more like project management than • traditional manufacturing. • Manage variability, can’t eliminate. • Critical Chain Management – uniquely positioned to manage • variability and help reduce flow days.

More Related