290 likes | 779 Views
Material Requirements Planning. Material Requirements Planning Defined. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product
E N D
Material Requirements PlanningDefined • Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product • MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced • Dependent demand drives MRP
Dependent Demand • The demand for one item is related to the demand for another item • Given a quantity for the end item, the demand for all parts and components can be calculated • In general, used whenever a schedule can be established for an item • MRP is the common technique
Benefits of MRP Better response to customer orders Faster response to market changes Improved utilization of facilities and labor Reduced inventory levels
Material Requirements PlanningSystem • Based on a master production schedule, a material requirements planning system: • Creates schedules identifying the specific parts and materials required to produce end items • Determines exact unit numbers needed • Determines the dates when orders for those materials should be released, based on lead times
6 Firm orders from known customers Forecasts of demand from random customers Aggregate product plan Engineering design changes Inventory transactions Master production Schedule (MPS) Material planning (MRP computer program) Bill of material file Inventory record file Secondary reports Primary reports Exception reports Planning reports Reports for performance control Planned order schedule for inventory and production control • The McGraw-Hill Companies, Inc., 2004
Elemen MRP Effective use of dependent demand inventory models requires the following • Master production schedule • Specifications or bill of material • Inventory availability • Purchase orders outstanding • Lead times
Master Production Schedule (MPS) • Specifies what is to be made and when • Must be in accordance with the aggregate production plan • Aggregate production plan sets the overall level of output in broad terms • As the process moves from planning to execution, each step must be tested for feasibility • The MPS is the result of the production planning process • MPS is established in terms of specific products
Master Production Schedule (MPS) Can be expressed in any of the following terms: • A customer order in a job shop (make-to-order) company • Modules in a repetitive (assemble-to-stock) company • An end item in a continuous (make-to-stock) company
Bill of Materials (BOM) FileA Complete Product Description • Materials • Parts • Components • Production sequence • Modular BOM • Subassemblies
BOM (Table Example) Top Leg Short Rail Long Rail
BOM (Product Structure) Table (End Item) Leg Assembly (1) Top (1) Short Rails (2) Long Rails (2) Legs (4)
Code Level CodeComponent 0 Table (end-item) 1 Leg assembly (1) 2 Short rails (2) 2 Long rails (2) 2 Legs (4) 1 Top(1)
Elements of Success in MRP • Implementation planning • Adequate computer support • Accurate data • Management support • User knowledge
A B(4) C(2) D(2) E(1) D(3) F(2) Example of MRP Logic and Product Structure Tree Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed Product Structure Tree for Assembly A Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day Total Unit Demand Day 10 50 A
LT = 1 day First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” on the 9th day to receive them on day 10.
LT = 2 Spares A 4x50=200 B(4) C(2) D(2) E(1) D(3) F(2) Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time.
20 A B(4) C(2) D(2) E(1) D(3) F(2) Finally, repeating the process for all components, we have the final materials requirements plan:
X A(2) B(1) C(2) D(5) C(3) MRP Example Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10
X A(2) It takes 2 A’s for each X
X A(2) B(1) It takes 1 B for each X
X A(2) B(1) C(3) It takes 3 C’s for each A
X A(2) B(1) C(3) C(2) It takes 2 C’s for each B
X A(2) B(1) C(3) C(2) D(5) It takes 5 D’s for each B
No Realistic? Feedback Feedback Yes Execute: Capacity Plans Material Plans Closed Loop MRP Production Planning Master Production Scheduling Material Requirements Planning Capacity Requirements Planning