7 TH ANNUAL MEETING CLUB-ER RURAL ELECTRIFICATION STRATEGIES IN AFRICA KENYA RURAL ELECTRIFICATION PROGRAMME Presentation by: Zachary Ayieko CEO, REA MOMBASA KENYA, 23-26 MARCH 2010. CONTENTS . HISTORY AND INSTITUTIONS ACHIEVEMENTS CHALLENGES AND MEASURES TO ADDRESS THE CHALLENGES

sierra
Download Presentation

7 TH ANNUAL MEETING CLUB-ER RURAL ELECTRIFICATION STRATEGIES IN AFRICA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 7TH ANNUAL MEETING CLUB-ER RURAL ELECTRIFICATION STRATEGIES IN AFRICA KENYA RURAL ELECTRIFICATION PROGRAMME Presentation by: Zachary Ayieko CEO, REA MOMBASA KENYA, 23-26 MARCH 2010

  2. CONTENTS HISTORY AND INSTITUTIONS ACHIEVEMENTS CHALLENGES AND MEASURES TO ADDRESS THE CHALLENGES BENEFITS OF RURAL ELECTRIFICATION CONCLUSION

  3. 1. HISTORY AND INSTITUTIONS • The Government established the Rural Electrification Programme in 1973 for purposes of subsidizing electricity supply in the rural areas • During the same year (1973) the Government appointed the then East African Power and Lighting Company (EAPL), now the Kenya Power & Lighting Company (KPLC) as the implementing agency for the programme • The Ministry of Energy was in charge of the overall coordination of the programme including policy formulation

  4. ELECTRIFICATION STATUS BY 2003

  5. Status of Electrification upto the year 2003 • By 2003, i.e. 30 years after inception of the programme, • Only about 1,729 Public institutions were connected to electricity by then • connectivity in the rural areas was only about 4% • This connectivity was very low: Average for the developing world: 35-40%

  6. MEASURES TAKEN BY GOVERNMENT • Due to the low connectivity, the Government through the Economic Recovery Strategy of 2003 & Sessional Paper No. 4 of 2004 on Energy undertook to create a rural electrification agency to accelerate rural electrification • Rural Electrification Authority (REA) was eventually created under the Energy Act, No.12 of 2006 and became operational in July 2007 • Increased funding

  7. MANDATE OF R.E.A. • Management of the Rural Electrification Programme Fund • Development and updating of the rural electrification programme masterplan • Implementing and sourcing of funds for the rural electrification programme • Promotion of renewable energy sources • Management of delineation, tendering and award • of contracts for licences and permits for rural • electrification.

  8. VISION 2030 • Vision 2030, aims at providing a high quality of • life to all citizens by 2030 and has singled out • electricity as one of the drivers of high quality life • In this respect, the aspiration of Vision 2030 • dictates that every citizen must have electricity • by this time, i.e. 100% connectivity by 2030

  9. IMPLEMENTATION STRATEGY OF THE VISION 2030 • Phase I 2008-2012 -Connect all public facilities • -Connect 1 million customers (REA- 200,000) • -Increase connectivity from about 12%-22%) • Phase II 2013-2022 -Connect Customers (increase connectivity from 22% to 65% ) • Phase III 2022-2030 -Connect Customers (increase connectivity from 65%to 100% ) • This is in line with REA’s strategy and Goal

  10. REA’S GOAL • The overall goal of the Rural Electrification Authority is two-fold: • To increase access to electricity in the rural areas from about 65-70%currently to 100% by 2012, and • To achieve 100% connectivity by 2030.

  11. 2. ACHIEVEMENTS OF RURAL ELECTRIFICATION (PUBLIC FACILITIES ELECTRIFIED)

  12. ACHIEVEMENTS Cont…… • To demonstrate its commitment the Government from 2003/04 FY significantly increased the funding for the rural electrification programme • As a result, the number of public facilities connected to electricity increased from 1,729 in 2003/4 to 10,594 by June 2009 and expected to increase to 12,094 by June 2010

  13. FUNDING FOR RURAL ELECTRIFICATION UPTO 2009/10

  14. By the 2009/10, about Ksh.42 billion will have been spent on rural electrification in the country as shown in the table above, with about 80% of these funds spent between 2003/4 and 2009/10 • During the 2009/10 FY, REA expects to electrify about 1,500 public facilities and the balance in the next three years • About Kshs.34 billion will be required to electrify the remaining 7,906 public facilities

  15. METHODS OF RURAL ELECTRIFICATION • Grid Extensions - For the interconnected areas • Stand alone Diesel Station- For off-grid areas • Solar Pvs - For institutions & homes within the off-grid areas • REA is also promoting use of other renewable energy sources such as Mini hydro, wind and Biogas

  16. FACTORS/STRATEGIES CONTRIBUTING TO THE SUCCESS OF RURAL ELECTRIFICATION PROGRAMME • Increased Government support through increased • budgetary allocation. • Timely disbursement of funds from the Treasury • and the Ministry of Energy • Continued support from Development Partners

  17. FACTORS/STRATEGIES CONTRIBUTING TO THE SUCCESS OF RURAL ELECTRIFICATION PROGRAMME Cont...... • Passion/Drive/zeal to light up the rural Kenya by • Government, Ministry and REA. • Use of L&T contractors. • Bulk and timely procurement of construction • materials.

  18. FACTORS/STRATEGIES CONTRIBUTING TO THE SUCCESS OF RURAL ELECTRIFICATION PROGRAMME Cont……. • Creativity in project implementation • Community involvement, Public and major • stakeholders support • Development and promotion of use of renewable energy. • Installation of diesel stations in off-grid areas.

  19. 3.CHALLENGES FACED AND MEASURES PUT IN PLACE

  20. Funding • An average of Kshs.6.7 billion for project implementation • against a target of Kshs.11 billion annually • Solution • Increase budgetary allocations • Increase support from development partners and the private • sector • Public - private partnership to mobilize more resources e.g. CDF • matching facility

  21. Procurement of Materials • Long lead times in procurement and delivery of materials • Most materials are imported and often manufactured on • order • Solution • Bulk and early procurement of materials • Promoting more local manufacturing of materials

  22. Way leaves Acquisition • Huge compensations required • Delay in acquisition of consent • Solution • Involvement of communities, Members of Parliament and • local leaders to sensitize communities on the importance of • granting free way leaves

  23. Commissioning of Projects • Inadequate project supervisory staff • Solution • Recruitment of additional supervisors • Capacity building • A Joint REA/KPLC committee formed to • handle issues on commissioning ofprojects

  24. Customer connectivity • High connection fee • Low income • Perceived high cost of electricity • Inadequate marketing to drive connectivity • Low level of connectivity • Solution • A revolving fund set up to provide credit facilities • Development and implementation of a marketing strategy • Interconnection of the grid with neighbours

  25. Limited use of renewable energy • Limited capacity in the use of renewable energy in the • rural areas • Solution • Promote use of solar PV’s in the off-grid areas • Promote more use of wind and biogas • Development of hybrid systems combining renewable energy • and conventional sources

  26. Limited Private Sector Participation • Overtime private sector participation has been very low • Solution • Development of public private sector participation in Rural • Electrification • Creating partnership with local and international corporate • organization

  27. Population distribution in rural areas • Sparsely populated and scattered settlements • Harsh terrain • Solution • Develop land policy that promote organized group settlement

  28. Vandalism • Vandalism of transformers and other line equipment • Solution • Promoting community participation/ownership of • projects • Locating Transformers in secured areas

  29. 4. BENEFITS OF RURAL ELECTRIFICATION Rural electrification empowers the rural communities through the following: • Agriculture- Improved farming • Fisheries- cooling plants • Education- increased standards • Health- better facilities

  30. BENEFITS Cont……… • Telecommunications – Increased information flow through Mobile phones, ICT facilities, TV, Radios • Employment creation – Industries & Jua kali • Social status – improved standard of living • Lighting and security

  31. 5. CONCLUSION • With the increased pace of Rural Electrification Rural Communities in Kenya are getting empowered and becoming more productive

  32. ASANTE SANA