1 / 16

TIME LINE SOME BACKGROUND REASONS TO SUPPORT

Environmental Protection Commission of Hillsborough County Extending Piney Point Emergency Permit November 3, 2003. EXTENSION REQUEST. TIME LINE SOME BACKGROUND REASONS TO SUPPORT. EXTENSION REQUEST TIME LINE.

silvio
Download Presentation

TIME LINE SOME BACKGROUND REASONS TO SUPPORT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Environmental Protection Commissionof Hillsborough CountyExtending Piney Point Emergency PermitNovember 3, 2003

  2. EXTENSION REQUEST • TIME LINE • SOME BACKGROUND • REASONS TO SUPPORT

  3. EXTENSION REQUEST TIME LINE • September 11, 2003 - Piney Point Update Agency on Bay Management • September 18, 2003 - EPC voted unanimously to send a letter to FDEP Secretary Struhs requesting they explore extending the EPA Emergency Permit • September 29, 2003 –EPC Chairman sent request letter to Secretary Struhs

  4. TIME LINE • October 13, 2003 – Secretary Struhs contacted EPC Chairman Platt and advised that FDEP would formally request EPA extend the Emergency Permit • October 16, 2003 - EPC voted unanimously to send a letter to EPA Region 4Administrator Palmerurging approval of the permit extension request from FDEP

  5. TIME LINE October 21, 2003 – FDEP sent letter to EPA formally requesting an extension of the Emergency Permit October 21, 2003 -EPC sent a letter to EPA urging approval of the extension request from FDEP November 3, 2003 – Consideration of ABM support for FDEP Extension Request

  6. PRIMARY OBJECTIVE Piney Point Closure • Reduce Inventory of Process Water and Initiate Closure Activities • Long Term Water Management Plan (WMP) • Closure Plan – Dewater, Line, Isolate, and Close Pond Storage Compartments

  7. Site has Received Excessive Rainfall during the last 12 months • Average Rainfall Adds 160 MGal to the Site each year • Closure Activities Delayed • 2004 Dry Season Closure Plan – Close one stack compartment and prepare to close two additional compartments MEETING WMP OBJECTIVE

  8. WATER MANAGEMENT CHALLENGE • 600 MGal Ponded Process Water • 600 MGal Pore Water • Increase Storage so that Significant Closure Work can be Accomplished Prior to the 2004 Rainy Season • Must Discharge “Double-Lime” Treated Water

  9. AMENDED WMP • Water Balance Model Recalibrated • Increase Target Wastewater Removal Rates (2 MGD to Over 4 MGD) • Time Period – Minimum 3 to 5 Months • Increase Storage so that Significant Closure Work can be Initiated

  10. EMERGENCY ORDERFIFTH MODIFICATION SEPTEMBER 5, 2003 • Double Amount of Water Removed From 2 MGD to 4 MGD • Increase Amount of Reverse Osmosis Water 0.6 MGD to a Minimum of 1.0 MGD (By 10/15/2003) • Increase Amount of Double-lime Aeration Water Minimum of 3.0 MGD (By 10/15/2003) • Resumption of Double-lime Aeration Water to Bishop Harbor • Target Ammonia Nitrogen Loading Rates (WQ Modeling Report) • 308 Pounds Per Day (15 Day Rolling Average) • 600 Pounds Per Day (Maximum)

  11. Potential Bishop Harbor Load Overall Tampa Bay Load Reduction Target N Load (pounds per day) LTB Load Reduction Target

  12. REASONS TO SUPPORT EXTENSION REQUEST • Risk of a Catastrophic Accident Remains until Site is Permanently Closed • Immediate need to Reduce Water On-Site to Initiate Closure Activities • RO is not the only Solution • “Double – Lime” Treated Water must be Discharged somewhere

  13. REASONS TO SUPPORT EXTENSION REQUEST • Only Current High-Volume Alternative to Discharge to Bishop Harbor is Gulf Dispersion • Extension will Reduce Discharges and Nitrogen Loading to Bishop Harbor • Extending the Permit Removes an Additional 70 to 75 MGal per month from the Site • Additional Water off-site improves Water Balance, Dam Safety and Minimizes the Risk of Accidental Discharges

  14. REASONS TO SUPPORT EXTENSION REQUEST • FDEP has met Current Conditions of Emergency Permit • No Adverse Environmental Impacts to Marine Water Quality or Marine Life • Continued Ocean Dispersal should be Part of a Multi-Faceted Treated Wastewater Reduction Plan

  15. BOTTOM LINE • SHARE THE LOAD… • USE OTHER HIGH VOLUME ALTERNATIVES AS LONG AS POSSIBLE… • MINIMIZE THE LOAD TO BISHOP HARBOR AND TAMPA BAY !!!!

  16. Environmental Protection Commissionof Hillsborough CountyExtending Piney Point Emergency PermitNovember 3, 2003

More Related