1.040/1.401 Project Management Spring 2007 Deterministic Planning Part I

1.040/1.401 Project Management Spring 2007 Deterministic Planning Part I. Dr. SangHyun Lee. lsh@mit.edu. Department of Civil and Environmental Engineering Massachusetts Institute of Technology. Project Management Phase. DESIGN PLANNING. DEVELOPMENT. OPERATIONS. CLOSEOUT. FEASIBILITY.

simonet
Download Presentation

1.040/1.401 Project Management Spring 2007 Deterministic Planning Part I

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 1.040/1.401Project ManagementSpring 2007Deterministic Planning Part I Dr. SangHyun Lee lsh@mit.edu Department of Civil and Environmental Engineering Massachusetts Institute of Technology

  2. Project Management Phase DESIGN PLANNING DEVELOPMENT OPERATIONS CLOSEOUT FEASIBILITY Fin.&Eval. Organization Risk Estimating Planning&Scheduling

  3. Outline • Objective • Bar Chart • Network Techniques • CPM

  4. Objective • What are some of the Different Representations for Deterministic Schedules ? • What are some Issues to Watch for?

  5. Outline • Objective • Bar Chart • Network Techniques • CPM

  6. Gantt Chart Characteristics • Bar Chart • Henry L. Gantt • World War I - 1917 • Ammunition Ordering and Delivery • Activities Enumerated in the Vertical Axis • Activity Duration Presented on the Horizontal Axis • Easy to Read

  7. Simple Gantt Chart

  8. Gantt (Bar) Charts • Very effective communication tool • Very popular for representation of simpler schedules • Can be cumbersome when have >100 activities • Key shortcoming: No dependencies captured • Most effective as reporting format rather than representation

  9. Hierarchy of Gantt Charts

  10. Activity Aggregation • Hammock Activities • A graphical arrangement which includes a summary of a group of activities in the project. • Duration equal to longest sequence of activities Source: Shtub et al., 1994

  11. Activity Aggregation • Milestones • A task with a zero duration that acts as a reference point marking a major project event. Generally used to mark: beginning & end of project, completion of a major phase, or a task for which the duration is unknown or out of control. • Flag the start or the successful completion of a set of activities Source: Shtub et al., 1994

  12. Outline • Objective • Bar Chart • Network Techniques • CPM

  13. Activity on Arrow AOA Activity A Activity A Activity B Event i Event j Network Scheduling • A network is a graphical representation of a project plan, showing the inter-relationships of the various activities. • When results of time estimates & computations are added to a network, it may be used as a project schedule. Activity on Node AON Source: Badiru & Pulat, 1995

  14. Advantages • Communications • Interdependency • Expected Project Completion Date • Task Starting Dates • Critical Activities • Activities with Slack • Concurrency • Probability of Project Completion Source: Badiru & Pulat, 1995

  15. Start Network - Definitions Node (Activity) Arc A D Milestone Merge Point Finish B G E Dummy H F C Burst Point I Source: Badiru & Pulat, 1995

  16. Start Network - Definitions A D Finish B G E H F C I • Predecessor Activity of D • Successor Activity of F Source: Badiru & Pulat, 1995

  17. Definitions (Cont’d) • Activity • Time and resource consuming effort with a specific time required to perform the task or a set of tasks required by the project • Dummy • Zero time duration event used to represent logical relationships between activities • Milestone • Important event in the project life cycle • Node • A circular representation of an activity and/or event Source: Badiru & Pulat, 1995

  18. Definitions (Cont’d) • Arc • A line that connects two nodes and can be a representation of an event or an activity • Restriction / Precedence • A relationship which establishes a sequence of activities or the start or end of an activity • Predecessor Activity • An activity that immediately precedes the one being considered • Successor Activity • An activity that immediately follows the one being considered • Descendent Activity • An activity restricted by the one under consideration • Antecedent Activity • An activity that must precede the one being considered Source: Badiru & Pulat, 1995

  19. Definitions (Cont’d) • Merge Point • Exists when two or more activities are predecessors to a single activity (the merge point) • Burst Point • Exists when two or more activities have a common predecessor (the burst point) • Network • Graphical portrayal of the relationship between activities and milestones in a project • Path • A series of connected activities between any two events in a network Source: Badiru & Pulat, 1995

  20. Outline • Objective • Bar Chart • Network Techniques • CPM

  21. Critical Path Method (CPM) • DuPont, Inc., and UNIVAC Division of Remington Rand • Scheduling Maintenance Shutdowns in Chemical Processing Plants • ~1958 • Construction Projects • Time and Cost Control • Deterministic Times

  22. CPM Objective • Determination of the critical path: the minimum time for a project

  23. CPM Precedence • Technical Precedence • Caused by the technical relationships among activities (e.g., in conventional construction, walls must be erected before roof installation) • Procedural Precedence • Determined by organizational policies and procedures that are often subjective with no concrete justification • Imposed Precedence • E.g., Resource Imposed (Resource shortage may require one task to be before another) Source: Badiru & Pulat, 1995

  24. Arrow Finish Event Clear & Grub Start Form Footings Excavate Footings Fabricate Footings Forms at Site Workshop 1 Mobilize 7 3 2 4 6 Dummy Activity Fabricate Rebar Footings Activity 5 8 Fabricate Forms Footings Fabricate Rebar Footings Excavate Footings Form Footings Start Dummy Activity Arc Clear & Grub Mobilize Finish CPM: AOA & AON • Activity-on-Arrow • Activity-on-Node Source: Feigenbaum, 2002 Newitt, 2005

  25. CPM Calculations • Forward Pass • Early Start Times (ES) • Earliest time an activity can start without violating precedence relations • Early Finish Times (EF) • Earliest time an activity can finish without violating precedence relations Source: Hegazy, 2002 Hendrickson and Au, 1989/2003

  26. Forward Pass - Intuition • It’s 8am. Suppose you want to know the earliest time you can arrange to meet a friend after performing some tasks • Wash hair (5 min) • Boil water for tea (10 min) • Eat breakfast (10 min) • Walk to campus (5 min) • What is the earliest time you could meet your friend?

  27. CPM Calculations • Backward Pass • Late Start Times (LS) • Latest time an activity can start without delaying the completion of the project • Late Finish Times (LF) • Latest time an activity can finish without delaying the completion of the project Source: Hegazy, 2002 Hendrickson and Au, 1989/2003

  28. Backward Pass - Intuition • Your friend will arrive at 9am. You want to know by what time you need to start all things • Wash hair (5 min) • Boil water for tea (10 min) • Eat breakfast (10 min) • Walk to campus (5 min) • What is the latest time you should start?

  29. Slack or Float • It’s 8am, and you know that your friend will arrive at 9am. How much do you have as free time? • Wash hair (5 min) • Boil water for tea (10 min) • Eat breakfast (10 min) • Walk to campus (5 min)

  30. CPM Example Draw AON network Source: Badiru & Pulat, 1995

  31. Forward Pass F 4 A 2 End D 3 ES EF 0 0 G 2 B 6 Start E 5 C 4 Source: Badiru & Pulat, 1995

  32. Forward Pass 2 6 F 4 0 2 11 11 A 2 2 5 End D 3 9 11 0 6 0 0 G 2 B 6 Start 0 4 4 9 E 5 C 4 Source: Badiru & Pulat, 1995

  33. Backward Pass 2 6 F 4 0 2 11 11 A 2 2 5 End D 3 11 11 9 11 0 6 LS LF 0 0 G 2 B 6 Start 0 4 4 9 E 5 C 4 • LF(k) = Min{LS(j)} j S(k) • LS(k) = LF(k) – D(k)  Source: Badiru & Pulat, 1995

  34. Backward Pass 2 6 F 4 0 2 11 11 7 11 A 2 2 5 End D 3 4 6 11 11 6 9 9 11 0 6 0 0 G 2 B 6 Start 9 11 0 0 3 9 0 4 4 9 E 5 C 4 0 4 4 9 Source: Badiru & Pulat, 1995

  35. Slack or Float • The amount of flexibility an activity possesses • Degree of freedom in timing for performing task 2 6 4 F 4 0 2 11 11 7 11 A 2 End 2 5 D 3 4 6 11 11 6 9 9 11 0 0 G 2 B 6 0 6 Start 9 11 0 0 3 9 0 4 4 9 E 5 C 4 0 4 4 9 Source: Hendrickson and Au, 1989/2003

  36. Total Slack or Float • Total Slack or Float (TS or TF) • Max time can delay w/o delaying the project • TS(k) = {LF(k) - EF(k)} or {LS(k) - ES(k)} 2 6 TS = 4 F 4 0 2 11 11 7 11 A 2 End 2 5 D 3 4 6 11 11 6 9 9 11 0 0 G 2 B 6 0 6 Start 9 11 0 0 3 9 0 4 4 9 E 5 C 4 0 4 4 9

  37. Free Slack or Float • Free Slack or Float (FS or FF) • Max time can delay w/o delaying successors • FS(k) = Min{ES(j)} - EF(k) j S(k)  2 6 F 4 0 2 11 11 7 11 A 2 End 2 5 D 3 4 6 11 11 FS = 3 6 9 9 11 0 0 G 2 B 6 0 6 Start 9 11 0 0 3 9 0 4 4 9 E 5 C 4 0 4 4 9

  38. Independent Slack or Float • Independent Slack or Float (IF) • Like Free float but assuming worst-case finish of predecessors • IF(k) = Max { 0, ( Min(ES(j)) - Max(LF(i)) – D(k) ) } j S(k), i P(k)   IF = 1 2 6 F 4 0 2 11 11 7 11 A 2 End 2 5 D 3 4 6 11 11 6 9 9 11 0 0 G 2 B 6 0 6 Start 9 11 0 0 3 9 0 4 4 9 E 5 C 4 0 4 4 9

  39. CPM Analysis Activity Duration ES EF LS LF TS FS IF Critical A 2 0 2 4 6 4 0 0 B 6 0 6 3 9 3 3 3 C 4 0 4 0 4 0 0 0 Yes D 3 2 5 6 9 4 4 0 E 5 4 9 4 9 0 0 0 Yes F 4 2 6 7 11 5 5 1 G 2 9 11 9 11 0 0 0 Yes Adapted from: Badiru & Pulat, 1995

  40. Critical Path • The path with the least slack or float in the network • Activities in that path: critical activities • For algorithm as described, at least one such path • Must be completed on time or entire project delayed • Determines minimum time required for project • Consider near-critical activities as well!

  41. Critical Path If EFi = ESj, then activity i is a critical activity (here, activity i is an immediate predecessor of activity j 2 6 F 4 0 2 11 11 7 11 A 2 End 2 5 D 3 4 6 11 11 6 9 9 11 0 0 G 2 B 6 0 6 Start 9 11 0 0 3 9 0 4 4 9 E 5 C 4 0 4 4 9 Source: Badiru & Pulat, 1995

  42. Path Criticality • Rank paths from more critical to less critical = minimum total float = maximum total float = total float or slack in current path

  43. Path Criticality - Example • Calculate Path Criticality • αmin = 0, αmax = 5 • Path 1: [(5-0)/(5-0)](100 %) = 100 % • Path 2: [(5-3)/(5-0)](100 %) = 40 % • Path 3: [(5-4)/(5-0)](100 %) = 20 % • Path 4: [(5-5)/(5-0)](100 %) = 0 % Source: Badiru & Pulat, 1995