All Experimenter’s Meeting: Proton Improvement Plan Status. C.Y. Tan for PIP Team 05 Nov 2012. RFQ PIP Status. RFQ injector is connected to Linac Tank 1. Beam has been sent to end of RFQ.
E N D
All Experimenter’s Meeting: Proton Improvement Plan Status C.Y. Tan for PIP Team 05 Nov 2012
RFQ PIP Status • RFQ injector is connected to Linac Tank 1
Beam has been sent to end of RFQ 43 mA of H- beam has been transmitted to the end of the RFQ (60 mA at source @ 71% transmission efficiency)
RFQ Plans • MEBT tasks • Align MEBT • Attach power, RF and water to MEBT • Condition Buncher • Plans for beam to NTF • Beam commissioning during Thanksgiving week. • Must finish commissioning by 04 Dec because of NTF patient treatment schedule. (NTF may extend schedule by 1 week to 10 Dec)
RFQ Project Timeline 4 years from concept to realization. We are near the finish line!
Linac PIP Status Highlights Linac Utilities • MCC upgrade • expected to be complete this week. • collaboration with AD/MSD and AD/EE support • Vacuum • two new blowers received and installed (DTL 1 & 2 vacuum section and DTL 5) complete • A0 dewar repair complete • 400 MeV beam valves ordered (waiting delivery) Instrumentation • receiving partial deliver new PCB boards • all new NIM crates and cables installed in all 5 different locations. 200 MHz RF power system • Effort continues on Marx Modulators in collaboration with SLAC for FY13. • SLAC proposes engineering study to build lower voltage two cell prototype for design testing $75k. • FNAL has started the design of a lower voltage 10 cell modulator prototype ($40k materials + labour)
Booster PIP Status • Booster solid state (SS) conversion status • 10 out of 19 are SS • Driver racks are being cabled in the west gallery • Three cavities have been refurbished: 5, 7, 8 • BRF6 beginning cavity testing at MI60 • LCW work at CUB is done. Water is circulating